Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Improving road safety: Young drivers

Improving road safety: Young drivers

Transport
Finance
Project management
Regulation
Service delivery

The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effective in reducing crashes and saving lives. Despite these improvements, young drivers are more likely to be involved in fatal crashes than other drivers.

 

Parliamentary reference - Report number #217 - released 19 October 2011

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Improving Road Safety: Speed Cameras

Improving Road Safety: Speed Cameras

Transport
Project management
Regulation

We found that fixed speed cameras were generally located in areas with high road safety risk. Likewise, safety cameras that enforced speed limits were initially placed at high risk sites. However as all safety cameras will now enforce speed, RTA no longer uses evidence of a speeding problem to select these sites. Overall, total crashes and injuries each fell 26 per cent, and fatalities fell by more than two-thirds, in the three years after the installation of fixed speed camera. Long term trends show that these reductions have been maintained, the average number of speeding fines per fixed and safety cameras declines over time and fixed and safety speed cameras were located in areas with high road safety risk.

 

Parliamentary reference - Report number #215 - released 27 July 2011

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Two Ways Together - NSW Aboriginal Affairs Plan

Two Ways Together - NSW Aboriginal Affairs Plan

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Project management
Service delivery

To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.

 

Parliamentary reference - Report number #213 - released 18 May 2011

Published

Actions for Dealing with Unlicensed and Unregistered Driving

Dealing with Unlicensed and Unregistered Driving

Justice
Transport
Information technology
Regulation
Shared services and collaboration

In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving.

 

Parliamentary reference - Report number #115 - released 4 September 2003

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.

 

Parliamentary reference - Report number #112 - released 17 June 2003