Reports
Actions for Severance Payments to Special Temporary Employees
Severance Payments to Special Temporary Employees
In reviewing both the severance pay guidelines and a sample of payments, we found the guidelines to be clear and all except two payments were made in accordance with them. In these two cases the severance payment was stipulated in the employment contract guaranteeing the STE a minimum of six months pay on termination, irrespective of the length of service.
Parliamentary reference - Report number #201 - released 16 June 2010
Actions for Injury Management in the NSW Public Sector
Injury Management in the NSW Public Sector
We found that during Working Together, agencies reduced the impact of workplace injuries. Most of the results have been positive in both our sample agencies and the public sector, and savings have been achieved. Between 2005 and 2008, while the number of claims in the sample agencies remained at around 15,000, the average cost of claims reduced by around 22 per cent from $22,349 to $17,360. The incidence rate of claims for the sample agencies also decreased by nine per cent to 7.3 claims per 100 staff.
Parliamentary reference - Report number #199 - released 31 March 2010
Actions for Improving the Performance of Metropolitan Bus Services
Improving the Performance of Metropolitan Bus Services
The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.
Parliamentary reference - Report number #198 - released 10 March 2010
Actions for Improving Road Safety: School Zones
Improving Road Safety: School Zones
Overall, speed cameras change driver behaviour and improve road safety. Fixed speed cameras reduce crashes and speeding. While the overall impact of speed cameras has been positive, 38 of the 141 fixed speed cameras need to be closely examined as they appear to have no significant road safety benefit. Other road safety measures may be needed for these sites.
Parliamentary reference - Report number #197 - released 10 March 2010
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Fare evasion on public transport: Follow-up audit
Fare evasion on public transport: Follow-up audit
The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.
However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.
Parliamentary reference - Report number #150 - released 26 April 2006