Published

Actions for Sydney Road Maintenance Contracts

Sydney Road Maintenance Contracts

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time. RMS’ SMC contract management includes most elements of good practice, including governance and dispute re

Published

Actions for NorthConnex

NorthConnex

Premier and Cabinet
Treasury
Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement

The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan. NorthConnex is a nine-kilometre tolled motorway tunnel between

Published

Actions for Passenger Rail Punctuality

Passenger Rail Punctuality

Transport
Information technology
Infrastructure
Service delivery

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound. Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased s

Published

Actions for 2016 - An overview

2016 - An overview

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017. The quality and timeliness of financial reporting continued to improve across the NSW public sector in 2016. Only one qualified audit opinion was issued and most agencies signed their financial statements on time. We found the Government’s cluster governance arrangements were unclear and inconsistently i

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of prog

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.  Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferre

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an