Actions for Volume Eight 2013 focusing on Transport and Ports
Volume Eight 2013 focusing on Transport and Ports
Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.
The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.
Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.
To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):
- ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
- ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
- consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
- review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)
Parliamentary reference - Report number #193 - released 27 October 2009
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006