Refine search Expand filter

Reports

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Unsolicited proposal process for the lease of Ausgrid

Unsolicited proposal process for the lease of Ausgrid

Premier and Cabinet
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration

In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.

A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.

Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.

In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.

On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal. 

This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide). 

The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money. 

Conclusion

The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money. 

It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.

The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. 

Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.

The reasons for accepting that the proposal and proponent were unique are not compelling.

The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated. 

The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:

  • it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
  • the market would be unlikely to deliver a better result than offered by the proponent
  • going to tender presented a material risk of a worse financial result. 

The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category. 

Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • recognise that when considering uniqueness they should: 
    • require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives 
    • give thorough consideration to any reasonable counter-arguments against uniqueness.
  • rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
  • do not use speed of transaction compared to a market process as justification for uniqueness.
The process to obtain assurance that the final price represented value for money was adequate. However, the negotiation approach reduced assurance that the bid price was maximised. 

The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction. 

The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.

DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations. 

The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
  • do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
Key aspects of governance recommended by the Guide were in place, but there were some shortcomings around role segregation, record keeping and probity assurance.

The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal. 

The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent. 

DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous. 

The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
•    maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
•    keep an auditable trail of documentation relating to the negotiation process
•    maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Progress and measurement of the Premier's Priorities

Progress and measurement of the Premier's Priorities

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.

The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.

The 12 Premier's Priorities
  • 150,000 new jobs by 2019

  • Reduce the volume of litter by 40 per cent by 2020

  • 10 key projects in metro and regional areas to be delivered on time and on budget, and nearly 90 local infrastructure projects to be delivered on time

  • Increase the proportion of NSW students in the top two NAPLAN bands by eight per cent by 2019

  • Increase the proportion of women in senior leadership roles in the NSW Government sector from 33 to 50 per cent by 2025 and double the number of Aboriginal and Torres Strait Islander people in senior leadership roles in the NSW Government sector, from 57 to 114

  • Increase the proportion of young people who successfully move from Specialist Homelessness Services to long-term accommodation to more than 34 per cent by 2019

  • 61,000 housing completions on average per year to 2021

  • Reduce the proportion of domestic violence perpetrators reoffending by 25 per cent by 2021

  • Improve customer satisfaction with key government services every year, this term of government to 2019

  • Decrease the percentage of children and young people re-reported at risk of significant harm by 15 per cent by 2020

  • 81 per cent of patients through emergency departments within four hours by 2019

  • Reduce overweight and obesity rates of children by five percentage points by 2025


Source: Department of Premier and Cabinet, Premier’s Priorities website.

Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.

The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.

This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.

 


The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.

The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.

The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.


 


Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.

The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.

Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.

Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.

We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.

The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.

By December 2018, the Department of Premier and Cabinet should:

  1. improve transparency of public reporting by:
    • providing information about limitations of reported data and associated performance
    • clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
  2. ensure that processes to check and verify data are in place for all agency data sources
  3. encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.

 


The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.

The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.

Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.

By June 2019, the Department of Premier and Cabinet should:

  1. establish routine collection of feedback about PIU performance including:
    • independent assurance of PIU performance
    • opportunity for agencies to provide confidential feedback.

 

 

Published

Actions for Relocating Agencies to Regional Areas

Relocating Agencies to Regional Areas

Premier and Cabinet
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

Decisions to relocate government agencies to non-metropolitan areas are not made purely for cost reasons. They can also serve government policy objectives, such as promoting regional economic development.

Regardless of the policy objectives that may exist, I would expect that decisions on individual agency relocations would be based on sound business cases. Those business cases would show how the relocation achieves any relevant government objectives, what costs (or savings) would be involved, logistical considerations such as obtaining appropriate accommodation and staff, and any impacts on levels service to the public.

In my view, the existence of government policy objectives does not remove the need for individual decisions to be made in a transparent, rational and accountable manner. Responsible public servants should provide the appropriate information to government to allow it to judge how best to implement its policies.

 

Parliamentary reference - Report number #147 - released 14 December 2005

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005