Actions for Volume Eight 2013 focusing on Transport and Ports

Volume Eight 2013 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Procurement
Project management
Regulation
Workforce and capability

Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.

The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Volume Nine 2010 focus on Transport, Planning and Industry

Volume Nine 2010 focus on Transport, Planning and Industry

Transport
Planning
Industry
Asset valuation
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.

Published

Actions for Improving the Performance of Metropolitan Bus Services

Improving the Performance of Metropolitan Bus Services

Transport
Internal controls and governance
Management and administration
Procurement
Service delivery

The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.

 

Parliamentary reference - Report number #198 - released 10 March 2010

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006