Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what serv

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a d

In progress

Actions for CBD and South East Light Rail – follow up audit

CBD and South East Light Rail – follow up audit

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The CBD and South East Light Rail (CSELR) project is a light rail service that connects the Sydney CBD to Kingsford and Randwick. First passenger services commenced in December 2019. We conducted a performance audit of the CSELR project in 2016. This audit will assess whether Transport for NSW has effectively updated and consolidated information about project costs and benefits, and whether Transport for NSW has implemented the recommendations of the pre

Open for contribution

Actions for WestConnex

WestConnex

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether the responsible agencies effectively assessed and justified major scope changes to the WestConnex project. Contributions close 30 June

Planned

Actions for Government Advertising 2018-19

Government Advertising 2018-19

Premier and Cabinet
Compliance
Regulation
Service delivery

Under the NSW Government Advertising Act 2011, the Auditor-General is required to undertake a performance audit on government advertising activities annually. The performance audit assesses whether a government agency or agencies has carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guideli

Planned

Actions for Advice on major decisions

Advice on major decisions

Premier and Cabinet
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Risk

The public service is responsible for providing accurate, evidence-based, and impartial advice to government, and implementing government’s commitments in a responsive and professional manner. Quality advice from the public service is required to support good decision making. This audit may examine 2-3 major decisions to determine whether the advice provided meets good practice standards. It will also assess the effectiveness of the whole of government