Refine search Expand filter

Reports

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.