Actions for Albert 'Tibby' Cotter Walkway
Albert 'Tibby' Cotter Walkway
On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.
Parliamentary reference - Report number #260 - released 17 September 2015
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014