Reports
Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.
The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.
This audit had two objectives:
- To assess the economy of the approach chosen to achieve the objectives of the Program.
- To assess the effectiveness of the consultation and oversight of the Program.
We addressed the audit objectives by answering the following questions:
a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.
Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.
2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.
Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
- providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
- providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
- making business cases available to the public.
The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.
The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.
Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
- work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received.
There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.
There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public.
Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.
Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.
The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.
Recommendations
For future infrastructure programs, NSW Government agencies should:
- develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
- establish whole-of-government oversight early in the program to guide major decisions. This should include:
- agreeing on objectives and ensuring all agencies understand these
- clearly defining roles and responsibilities for all agencies
- establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.
By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:
- setting measurable targets for the desired benefits
- clearly allocating ownership for achieving the desired benefits
- monitoring progress toward achieving the desired benefits and reporting publicly on the results.
Appendix one - Response from agencies
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #310 - released 12 December 2018
Actions for Unsolicited proposal process for the lease of Ausgrid
Unsolicited proposal process for the lease of Ausgrid
In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.
A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.
Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.
In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.
On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal.
This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide).
The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money.
The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money.
It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.
The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance.
Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.
The reasons for accepting that the proposal and proponent were unique are not compelling.
The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated.
The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:
- it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
- the market would be unlikely to deliver a better result than offered by the proponent
- going to tender presented a material risk of a worse financial result.
The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category.
Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- recognise that when considering uniqueness they should:
- require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives
- give thorough consideration to any reasonable counter-arguments against uniqueness.
- rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
- do not use speed of transaction compared to a market process as justification for uniqueness.
The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction.
The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.
DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations.
The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
- do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal.
The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent.
DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous.
The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
• maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
• keep an auditable trail of documentation relating to the negotiation process
• maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.
Appendix one - Response from agency
Appendix two - NSW Government’s summary of assessment of the Ausgrid unsolicited proposal
Appendix three - The definition and nature of unsolicited proposals
Appendix four - Ausgrid unsolicited proposal process
Appendix five - About the audit
Appendix six - Performance auditing
Parliamentary reference - Report number #309 - released 11 December 2018
Actions for Mobile speed cameras
Mobile speed cameras
The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.
Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.
Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.
This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.
The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.
Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.
A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.
There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #308 - released 18 October 2018
Actions for Progress and measurement of the Premier's Priorities
Progress and measurement of the Premier's Priorities
The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.
The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.
The 12 Premier's Priorities | |
---|---|
|
|
|
|
|
|
|
|
|
|
|
|
Source: Department of Premier and Cabinet, Premier’s Priorities website.
Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.
The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.
This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.
The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.
The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.
The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.
Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.
The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.
Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.
Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.
We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.
The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.
By December 2018, the Department of Premier and Cabinet should:
- improve transparency of public reporting by:
- providing information about limitations of reported data and associated performance
- clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
- ensure that processes to check and verify data are in place for all agency data sources
- encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.
The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.
The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.
Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.
By June 2019, the Department of Premier and Cabinet should:
- establish routine collection of feedback about PIU performance including:
- independent assurance of PIU performance
- opportunity for agencies to provide confidential feedback.
Appendix one: Response from agency
Appendix three: About the audit
Appendix four: Performance auditing
Parliamentary reference - Report number #307 - released 13 September 2018
Actions for Government Advertising: Campaigns for 2015–16 and 2016–17
Government Advertising: Campaigns for 2015–16 and 2016–17
The 'Stronger Councils, Stronger Communities' and the 'Dogs deserve better' government advertising campaigns complied with the Government Advertising Act and most elements of the Government Advertising Guidelines.
However, some advertisements were designed to build support for government policy and used subjective or emotive messages. This is inconsistent with the requirement in the Government Advertising Guidelines for 'objective presentation in a fair and accessible manner'.
Advertisements in the 'Stronger Councils, Stronger Communities' campaign used subjective statements such as 'the system is broken' and 'brighter future'. While advertisements in the 'Dogs deserve better' campaign used confronting imagery such as gun targets, blood smears and gravestones.
The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit in relation to at least one government advertising campaign in each financial year. The performance audit assesses whether advertising campaigns were carried out effectively, economically and efficiently and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines). In this audit, we examined two campaigns:
- the ‘Stronger Councils, Stronger Communities’ campaign run by the Office of Local Government and the Department of Premier and Cabinet
- the ‘Dogs deserve better’ campaign run by the Department of Justice.
Section 6 of the Act details the specific prohibitions on political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed so as to influence (directly or indirectly) support for a political party.
The ‘Stronger Councils, Stronger Communities’ government advertising campaign was run by the Office of Local Government and the Department of Premier and Cabinet in four phases from August 2015 to May 2016. The total cost of the campaign was over $4.5 million. See Appendix 2 for more details on this campaign.
Two factors potentially compromised value for money for the campaign. The request for quotes for the design of the Phase 1 advertisement did not reflect the full scale of work to be undertaken, which was substantially greater than initially quoted. Further, the department did not meet all recommended timeframes to minimise media booking costs for all phases of the campaign.
The campaign did not comply with all administrative requirements in all phases. Advertising for Phase 1 commenced before the compliance certificate was signed. There was no evidence that a compliance certificate was signed for Phase 2 extension. The cost benefit analyses for Phase 2 and Phase 2 extension did not sufficiently consider alternatives to advertising, as is required by the Government Advertising Guidelines.
Advertisements adopted subjective messages designed to build public support for council mergers and directed audiences to websites for more detailed information. Campaign research identified statements that were most likely to reduce resistance to mergers. Some advertising content used subjective language, which we consider inconsistent with the requirement for ‘objective presentation’. Evaluations of advertising effectiveness also measured the success of the advertisements in increasing public support for council mergers.
No breach of specific prohibitions in the Act
Section 6 of the Act prohibits the use of government advertising for political advertising. A government advertising campaign must not:
- be designed to influence (directly or indirectly) support for a political party
- contain the name, voice or image of a minister, any other member of parliament or a candidate nominated for election to parliament
- contain the name, logo or any slogan of, or any other reference relating to, a political party.
We did not identify any breach of the specific prohibitions listed above in the advertising content of this campaign.
Request for quotes to design advertisement did not reflect the full scope required
The request for quotes for the design of the Phase 1 advertisement did not reflect the full scale of work that was to be undertaken, and this created a risk to achieving value for money. The Office of Local Government sought quotes for design of a television advertisement only. It did not request an estimate for radio, online advertisements, or translation for linguistically diverse audiences, which were ultimately required for the campaign.
A full and fair assessment of which supplier could provide the best value for money could not be made given that the quotes obtained did not reflect the full scope of work. The final amount paid for the design of Phase 1 was 2.7 times the original quote. It is possible that another supplier that provided a quote could have provided overall better value for money.
The Office of Local Government continued to use the Phase 1 supplier for Phase 2 and Phase 2 extension (Exhibit 4). Where there are other suppliers that could feasibly compete for a contract, direct negotiation increases the risk the agency has not obtained the best value for money. The department advised that it continued with the same agency to avoid costs involved in briefing a new agency on the campaign.
The ‘Dogs deserve better’ government advertising campaign was run by the Department of Justice from August 2016, after the government announced its decision to prohibit greyhound racing, and was terminated in October 2016 after a change of government policy. The campaign had a budget of $1.6 million, with an actual spend of $1.3 million. See Appendix 2 for more details on this campaign.
The Secretary of the department determined that urgent circumstances existed that required advertising to commence prior to completing a cost benefit analysis and peer review. There was a concern that industry participants may make impulse decisions to destroy greyhounds without further information on support services; there was also an identified need to promote public greyhound adoptions.
Phase 1 advertisements focused on explaining the reasons for the prohibition on greyhound racing with a reference to a website for further information. While industry participants were identified as the primary audience, media expenditure was not specifically targeted to this group. Phase 2 advertisements more effectively addressed the originally identified ‘urgent needs’ of providing information on support services for greyhound owners and information on how the public could adopt a greyhound.
The urgency to advertise potentially compromised value for money. The department did not use price competition when selecting a creative supplier due to a concern this would add to timeframes. Further, the department did not meet recommended timeframes to minimise media booking costs.
We identified three other areas in Phase 1 advertisements that were inconsistent with government advertising requirements. Advertisements used provocative language and confronting imagery, which we consider to be inconsistent with the requirement for ‘objective presentation’. Two statements presented as fact based on the Special Commission’s Inquiry report were inaccurate; one of these was due to a calculation error. Radio advertisements did not clearly identify that they were authorised by the New South Wales Government for the first few days of the campaign.
No breach of specific prohibitions in the Act
Section 6 of the Act prohibits the use of government advertising for political advertising. A government advertising campaign must not:
- be designed to influence (directly or indirectly) support for a political party
- contain the name, voice or image of a minister, any other member of parliament or a candidate nominated for election to parliament
- contain the name, logo or any slogan of, or any other reference relating to, a political party.
We did not identify any breach of the specific prohibitions listed above in the advertising content of this campaign.
Animal welfare concerns were identified as the reason for urgent advertising
A brief prepared by the department in July 2016 raised concerns about the welfare of greyhounds following the NSW Premier’s announcement that the government would prohibit greyhound racing. The brief raised the risk that industry members may make impulse decisions to destroy their greyhounds without information on support that was being offered.
The department used the provisions in Sections 7(4) and 8(3) of the Act to expedite the release of advertising due to ‘other urgent circumstances’. This provision allows advertising to commence prior to completing the peer review process and cost benefit analysis.
In introducing the Government Advertising Bill to parliament in 2011, the then Premier noted that exceptional circumstances would cover situations ‘such as a civil emergency or sudden health epidemic’. There is no other guidance on when it is appropriate to use this section. It is at the discretion of a government agency head to determine whether a campaign is urgent.
Phase 1 advertisements did not focus on the urgent needs
This advertising campaign had three overarching objectives:
- to increase public awareness of the animal welfare reasons for the closure of the greyhound racing industry
- to change the behaviour of dog owners from potentially harming their greyhounds to treating them humanely, by accessing the support options and packages available
- to promote greyhound adoptions by the public.
Alongside advertising, the department took other steps to engage with the greyhound racing industry. This included direct mail, face to face meetings around the State, setting up a call centre and community consultation through an online survey. Other government agencies and animal welfare agencies were also engaged to reach out to affected stakeholders.
Phase 1 advertising content focused on providing information about the reasons for the closure of the industry. The department’s radio and television advertisements did not refer to support packages or encourage the public to adopt a greyhound. While print advertisements did mention these things, this was only presented in fine print. In all advertisements, audiences were referred to a website for further information.
The focus of advertisements on the reasons for industry closure was not consistent with the identified needs to urgently commence advertising to influence the behaviour of dog owners and encourage the public to adopt a greyhound.
The content in Phase 2 advertisements, which began around four weeks after the first phase, was more explicit in highlighting the services and support for industry members such as offering business and retraining advice. These advertisements also referred audiences to a call centre number as well as the website.
Peer review process limited to influencing second phase of advertisements
In urgent circumstances, the Act allows for peer review to be completed after advertising has commenced. For this campaign, the peer review process was completed on 19 August 2016, two weeks after advertising had commenced. Where advertising commences before the peer review process is completed, the usefulness of peer reviewers’ recommendations is limited to informing subsequent phases of advertising and the post-campaign evaluation.
The peer review report found the messages in Phase 1 advertisements were not clearly defined, and the role of advertising was not clearly defined amongst other campaign activities. These recommendations informed the second phase of advertising, which ran from 27 August 2016 until the campaign was terminated in October 2016.
The department could not demonstrate value for money was achieved for creative work
The department provided a fixed budget for creative work when requesting quotes from creative agencies to develop advertising material. This is not consistent with the quotation requirements in the government’s Guidelines for Advertising and Digital Communication Services. This approach creates risks to achieving value for money as creative agencies are not required to compete on price for their services. The department advised that it had pre-set the creative costs based on a comparative government campaign of a similar size. This was done due to a concern that requiring agencies to compete on price would affect the short timeframe given to develop creative material.
Three creative agencies accepted the opportunity to present design ideas for the campaign. The department was unable to provide evidence of how it chose the preferred supplier out of these three agencies. Records are important for accountability and allow a procurement decision to be audited after an urgent decision.
Short notice did not allow for cost-efficient media booking for all phases
Placement of advertisements in various media channels was done through the State’s Media Agency Services contract. This contract achieves savings as the government can use its aggregated media spend to gain discounts from the media supplier.
The Department of Premier and Cabinet provides guidance to ensure cost efficient media booking. For example, media time for a television advertisement should be booked at least 6 to 12 weeks in advance. Radio advertisements should be booked at least 2 to 8 weeks in advance.
The peer review report noted that the department did not have adequate time to look for the most cost-efficient way to advertise. In its response to the peer reviewers, the department acknowledged this to be due to the urgency to start advertising. The media booking authority was signed by the department one day before the campaign commenced.
The department used a wide public campaign for a narrow target audience
The campaign identified greyhound industry participants as the primary target audience. In 201516 there were 1,342 greyhound trainers, 1,695 owner/trainers, 983 attendants and 1,247 breeders in New South Wales. The department’s advertising submission identified ‘concerns that industry members could make impulsive decisions, potentially jeopardising the welfare of a large number of dogs, prior to the shutdown of the industry’.
The submission’s evidence of advertising effectiveness focused on increasing the level of wider community support for the ban rather than stopping industry members from making impulse decisions. It used an early opinion poll to show that total support for the ban on greyhound racing rises by 17 points and opposition drops by four points following explanation of the findings of the Special Commission of Inquiry report.
The peer review report noted that the role of advertising was not clearly defined amongst the department’s range of other direct and targeted communications and consultations held with industry members.
No demonstrated basis for use of confronting imagery and provocative language
The Guidelines require ‘objective presentation in a fair and accessible manner’. Neither the Guidelines or Handbook further explain what objective presentation means. We have used an ordinary definition of this term as ‘not influenced by personal feelings or opinions in considering and representing facts’. This is synonymous with terms like ‘impartial’, ‘neutral’, and ‘dispassionate’ and opposite to ‘subjective’. We consider that to meet the current requirements in the Guidelines for objectivity, advertising content should contain accurate statements or facts, and avoid subjective language.
Phase 1 focussed on the ongoing consequences if no action was taken to close the industry. The advertisements used provocative language, for example ‘Up to 70 per cent of dogs are deemed wastage by their own industry. Wastage! Slaughtered just for being slow’. Advertisements used confronting imagery like gravestones, blood smears and gun targets.
Our literature review into this area highlighted mixed findings on the effectiveness of confrontational advertising materials. In some cases, shock campaigns may cause an audience to reject or ignore the message, and may even encourage people to do the opposite of the intended behaviour. In other cases, such as in road safety campaigns, this style of advertising can be successful. This shows the importance of conducting pre-campaign research before adopting a confrontational or emotive approach in advertising.
The Government Advertising Handbook recommends that an agency explain the rationale and the evidence for their chosen advertising approach. There was no evidence that the department researched the effectiveness of its advertising approach with its target audience. The department had planned to undertake creative concept testing as part of a strategy to ensure the creative material was understood by its audience. The department advised that due to the urgency of the campaign, it did not have time to conduct this testing.
Not all Phase 1 radio advertisements clearly identified that they were authorised by the New South Wales Government
For the first few days on air, Phase 1 radio advertisements ended by referring the audience to a government website, instead of clearly identifying that it had been authorised by the New South Wales Government. Government authorisations and logos ensure the work and the programs of the NSW Government are easily identifiable by the community.
The department’s cost benefit analysis did not consider alternatives to advertising
For government advertising campaigns that cost over $1.0 million, the Act requires the advertising agency to carry out a cost benefit analysis and obtain approval from the Cabinet Standing Committee on Communications, prior to commencing the campaign.
The department engaged with audiences through direct mail, face to face forums, and a telephone helpline in addition to advertising. However, the department’s cost benefit analysis did not meet the requirements in the Guidelines to specify the extent to which expected benefits could be achieved without advertising, and to compare costs of options other than advertising that could be used to successfully implement the program (see Exhibit 6).
The cost benefit analysis made optimistic assumptions about the impact of the campaign on greyhound adoptions. It estimated that 2,360 greyhounds would be adopted if the campaign was run. This is significantly higher than the ‘most optimistic outcome’ of re-homing in the Special Commission Inquiry report (we calculated this to be 1,467 greyhounds). There was insufficient evidence to support the higher number of adoptions in the cost benefit analysis.
The sensitivity analysis shows that using the Special Commission’s ‘most optimistic outcome’ figure of re-homing would reduce the net present value of advertising to be negative. Further, the cost benefit analysis also assumed that increased government funding would be made available to animal welfare and rehoming organisations to support more adoptions, but did not estimate or include this cost when calculating the net present value of advertising.
There were two factual inaccuracies in key messages used for Phase 1 advertisements
Section 8(2) of the Act requires the head of a government agency to certify that the proposed campaign ‘contains accurate information’. The Secretary of the Department of Justice signed the compliance certificate on 29 July 2016, before advertisements commenced.
We examined the accuracy of factual claims in this advertising campaign, by comparing the key statements to the report of Special Commission of Inquiry into the Greyhound Racing Industry (the Commissioner report). The Commissioner report was quoted by the NSW Government as the basis for its policy to transition the greyhound racing industry to closure.
We identified that two of the key statements used in Phase 1 advertisements to support the animal welfare reasons for industry closure were inaccurate (Exhibit 7).
Appendix one - Responses from agencies
Appendix two - About the campaigns
Appendix three - About the Audit
Appendix four - Performance Auditing
Parliamentary reference - Report number #294 - released 2 November 2017
Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.
WA | VIC | QLD | NSW | |
---|---|---|---|---|
Roads managed (lane kms) | 52,659 | 50,510 | 71,353 | 80,348 |
Estimated spend ($/lane km) | 5,000 | 4,500 | 6,000 | 7,000 |
Road quality measure (%) | 99 | 99 | 94 | 91 |
Parliamentary reference - Report number #288 - released 15 June 2017
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan.
Parliamentary reference - Report number #287 - released 8 June 2017
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.
Appendix one - Response from the agencies
Appendix two - Response from Audit Office
Appendix three - About the audit
Appendix four - Accuracy of punctuality measurement
Appendix five - Train and customer punctuality
Parliamentary reference - Report number #281 - released 11 April 2017
Actions for Signal failures on the metropolitan rail network
Signal failures on the metropolitan rail network
Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.
Parliamentary reference - Report number #170 - released 15 August 2007
Actions for Connecting with public transport
Connecting with public transport
We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.
Parliamentary reference - Report number #168 - released 6 June 2007