Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Making the Most of Government Purchasing Power - Telecommunications

Making the Most of Government Purchasing Power - Telecommunications

Whole of Government
Compliance
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General has found that agencies have consistently failed to negotiate the best price for their telecommunication contracts and are not getting value for money because of inadequate contract and expense management processes.

The audit examined six agencies to assess whether the government was getting value for money from its telecommunications contracts. It again raised problems with the way NSW government agencies manage contracts.

 

Parliamentary reference - Report number #244 - released 26 June 2014

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Building Energy Use in NSW Public Hospitals

Building Energy Use in NSW Public Hospitals

Health
Treasury
Planning
Environment
Internal controls and governance
Management and administration

NSW Health has reduced its energy use and greenhouse gas emissions by two per cent over the last four years. It is pleasing that annual emissions are now 15,000 tonnes less than they were four years ago. However, this was not sufficient to meet its target of an 11 per cent drop in emissions. 

Despite a reduction in energy use, energy cost in NSW Health has increased by nearly 50 per cent over the last four years to $120 million per annum. This is expected to increase by another 50 per cent in the next five years.

 

Parliamentary reference - Report number #231 - released 4 June 2013

Published

Actions for Managing Gifts and Benefits

Managing Gifts and Benefits

Planning
Finance
Transport
Environment
Compliance
Fraud
Internal controls and governance
Management and administration

Overall, the audited entities are managing some aspects of gifts and benefits effectively but other aspects require improvement. We found that all five entities had gifts and benefits policies that addressed some but not all of the attributes of a sound policy. All five have communicated their gifts and benefits policies to staff and external stakeholders, although in each case we identified opportunities to better communicate their policies.

 

Parliamentary reference - Report number #228 - released 27 March 2013

Published

Actions for Government Advertising 2009

Government Advertising 2009

Premier and Cabinet
Finance
Treasury
Compliance
Management and administration
Procurement
Regulation

We found that the two NSW Health campaigns had followed the required approval processes and were appropriate. We had some concerns with the two Department of Premier and Cabinet (DPC) campaigns. The revised Guidelines, which incorporate recommendations from earlier audit reports, are a positive step towards reducing the risk that publicly funded advertising could be used inappropriately. But there are still parts of the Guidelines that require a subjective judgement and therefore do little to help manage this risk. While we did not have any concerns with the two NSW Health campaigns, the two DPC campaigns highlighted these risks.

 

Parliamentary reference - Report number #194 - released 9 December 2009

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Environmental Grants Administration

Environmental Grants Administration

Planning
Environment
Internal controls and governance
Management and administration
Procurement
Shared services and collaboration

We found many aspects of good grants management, particularly in the Trust. All of the programs we looked at are clearly aligned to the Government’s objective to improve environmental outcomes. The Trust also has good practices for allocating grants. Performance in respect of results was mixed although many grants delivered tangible benefits - homes were protected from floods, degraded waterways restored and endangered habitats protected.

Generally we found that while both Department of Environment, Climate Change and Water and the NSW Environmental Trust had a range of strategies to monitor grants these were not always applied consistently or effectively. Grant programs need to be regularly evaluated to see what is working and what can be done better.

 

Parliamentary reference - Report number #190 - released 26 August 2009