Actions for Transport 2020
Transport 2020
1. Financial Reporting Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities. Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements. Transport cluster agencies continued to experience some challenges with accounting for land and infrastructur
Actions for CBD South East Sydney Light Rail: follow-up performance audit
CBD South East Sydney Light Rail: follow-up performance audit
This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits. The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public. The Auditor-General reports that the total cost
Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time. RMS’ SMC contract management includes most elements of good practice, including governance and dispute re
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan. NorthConnex is a nine-kilometre tolled motorway tunnel be
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound. Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased s
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017. The quality and timeliness of financial reporting continued to improve across the NSW public sector in 2016. Only one qualified audit opinion was issued and most agencies signed their financial statements on time. We found the Government’s cluster governance arrangements were unclear and inconsisten
Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effect
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced