Actions for CBD and South East Light Rail: follow-up performance audit

CBD and South East Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street. Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW ent

Published

Actions for Universities 2019 audits

Universities 2019 audits

Universities
Cyber security
Financial reporting
Internal controls and governance
Procurement

This report analyses the results of our audits of the financial statements of the ten NSW universities for the year ended 31 December 2019. The table below summarises our key observations. 1. Financial reporting Financial reporting The 2019 financial statements of all ten NSW universities received unmodified audit opinions. One controlled entity of the Western Sydney University received a qualified audit opinion. Five NSW universities fi

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of prog

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.  Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferre

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.   Parliamentary referen

Published

Actions for Relocating Agencies to Regional Areas

Relocating Agencies to Regional Areas

Premier and Cabinet
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

Decisions to relocate government agencies to non-metropolitan areas are not made purely for cost reasons. They can also serve government policy objectives, such as promoting regional economic development. Regardless of the policy objectives that may exist, I would expect that decisions on individual agency relocations would be based on sound business cases. Those business cases would show how the relocation achieves any relevant government objectives, w

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made. In this follow-up audit, we examine changes following our May 2002 report on how well the: State Transit Authority maintained its buses Ministry of Transport administered contracts for the provision of regular passenger bus services.   Parliament

In progress

Actions for WestConnex: Changes since 2014

WestConnex: Changes since 2014

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether Transport for NSW and Infrastructure NSW effectively assessed and justified major scope changes to the WestConnex project since December

Planned

Actions for Road and rail freight strategy

Road and rail freight strategy

Transport
Asset valuation
Infrastructure
Management and administration
Procurement
Project management
Service delivery

Freight is a critical component of the New South Wales economy. It is currently estimated to be worth nearly $66.0 billion a year to the economy. The economic growth and prosperity of New South Wales depends on the safe, efficient and reliable movement of goods. The NSW Government Future Transport 2056 strategy estimates that by 2056, 12 million people will live in New South Wales, and freight volumes will double in the Greater Sydney area and increase b