Reports
Actions for Monitoring Local Government
Monitoring Local Government
The Division of Local Government (DLG) has helped many NSW councils improve their long-term financial planning and asset management practice. Many councils are serving their communities well. However, because DLG lacks the power, it finds it difficult to respond effectively when things go wrong.
Parliamentary reference - Report number #225 - released 26 September 2012
Actions for Managing Overtime: RailCorp and Roads and Maritime Services
Managing Overtime: RailCorp and Roads and Maritime Services
Overtime is a significant cost for RailCorp and Roads and Maritime Services, adding about ten per cent to the cost of regular salaries. RailCorp’s overtime cost was $133.7 million in 2010–11, and at Roads and Maritime Services it cost $49.3 million.
Parliamentary reference - Report number #223 - released 20 June 2012
Actions for Settling Humanitarian Entrants in New South Wales - Services to permanent residents who come to New South Wales through the humanitarian migration scheme
Settling Humanitarian Entrants in New South Wales - Services to permanent residents who come to New South Wales through the humanitarian migration scheme
Support for humanitarian entrants living in New South Wales is poorly coordinated. Humanitarian entrants in New South Wales are doing less well than in other states on the key indicators of health, housing and employment. Unlike some States, New South Wales does not have a single point of contact that humanitarian entrants can go to assist them with settling in a new country.
Parliamentary reference - Report number #221 - released 23 May 2012
Actions for Volume One 2012 focusing on themes from 2011
Volume One 2012 focusing on themes from 2011
The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for Agency use of performance information to manage services
Agency use of performance information to manage services
Overall the results were mixed. There is some good news but this is such a basic and vital issue that we must conclude that a good deal more needs to be done. Three agencies did not have sufficient information to provide a balanced view of services. And two of these agencies could not tell us whether their services actually made a difference to customers. Across the ten programs we found many examples of good practice, but some variation in the quality and coverage of performance measures. Agencies that we identified as not having sufficient information to judge services were either unaware of its importance, collected data on activities but not results or reported system limitations.
Parliamentary reference - Report number #153 - released 21 June 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Fare evasion on public transport: Follow-up audit
Fare evasion on public transport: Follow-up audit
The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.
However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.
Parliamentary reference - Report number #150 - released 26 April 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006
Actions for The New Schools Privately Financed Project
The New Schools Privately Financed Project
In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.
Parliamentary reference - Report number #148 - released 8 March 2006