Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Prequalification Scheme: Performance and Management Services
Prequalification Scheme: Performance and Management Services
There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.
Parliamentary reference - Report number #216 - released 28 September 2011
Actions for Government expenditure and transport planning in relation to implementing Barangaroo
Government expenditure and transport planning in relation to implementing Barangaroo
Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project.
Parliamentary reference - Report number #214 - released 15 June 2011
Actions for Two Ways Together - NSW Aboriginal Affairs Plan
Two Ways Together - NSW Aboriginal Affairs Plan
To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.
Parliamentary reference - Report number #213 - released 18 May 2011
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for Agency use of performance information to manage services
Agency use of performance information to manage services
Overall the results were mixed. There is some good news but this is such a basic and vital issue that we must conclude that a good deal more needs to be done. Three agencies did not have sufficient information to provide a balanced view of services. And two of these agencies could not tell us whether their services actually made a difference to customers. Across the ten programs we found many examples of good practice, but some variation in the quality and coverage of performance measures. Agencies that we identified as not having sufficient information to judge services were either unaware of its importance, collected data on activities but not results or reported system limitations.
Parliamentary reference - Report number #153 - released 21 June 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Fare evasion on public transport: Follow-up audit
Fare evasion on public transport: Follow-up audit
The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.
However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.
Parliamentary reference - Report number #150 - released 26 April 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006
Actions for The New Schools Privately Financed Project
The New Schools Privately Financed Project
In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.
Parliamentary reference - Report number #148 - released 8 March 2006