1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for The New Schools Privately Financed Project

The New Schools Privately Financed Project

Education
Treasury
Infrastructure
Management and administration
Procurement
Project management

In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.

 

Parliamentary reference - Report number #148 - released 8 March 2006