Actions for Building Energy Use in NSW Public Hospitals

Building Energy Use in NSW Public Hospitals

Health
Treasury
Planning
Environment
Internal controls and governance
Management and administration

NSW Health has reduced its energy use and greenhouse gas emissions by two per cent over the last four years. It is pleasing that annual emissions are now 15,000 tonnes less than they were four years ago. However, this was not sufficient to meet its target of an 11 per cent drop in emissions. 

Despite a reduction in energy use, energy cost in NSW Health has increased by nearly 50 per cent over the last four years to $120 million per annum. This is expected to increase by another 50 per cent in the next five years.

 

Parliamentary reference - Report number #231 - released 4 June 2013

Published

Actions for Managing Gifts and Benefits

Managing Gifts and Benefits

Planning
Finance
Transport
Environment
Compliance
Fraud
Internal controls and governance
Management and administration

Overall, the audited entities are managing some aspects of gifts and benefits effectively but other aspects require improvement. We found that all five entities had gifts and benefits policies that addressed some but not all of the attributes of a sound policy. All five have communicated their gifts and benefits policies to staff and external stakeholders, although in each case we identified opportunities to better communicate their policies.

 

Parliamentary reference - Report number #228 - released 27 March 2013

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006

Published

Actions for Management of road passenger transport regulation

Management of road passenger transport regulation

Transport
Management and administration
Regulation
Service delivery
Shared services and collaboration

The Audit Office is of the opinion that the Department’s levels of regulatory activity in respect of road passenger transport regulation may have exceeded optimum levels. The Department’s current focus on processing activity limits the Department in achieving all of its desired outcomes. The Audit Office considers that a change in the approach to undertaking and managing road passenger transport regulatory activities would achieve better outcomes for the community and a better use of resources within the Department.

The Audit Office believes that while there is scope to make some improvements from procedural changes, such changes would not be sufficient to generate significant improvements.

 

Parliamentary reference - Report number #75 - released 6 September 2000