Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)

Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)

Treasury
Finance
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

The quality of financial reporting in the Finance and Treasury cluster continues to improve with fewer reported misstatements over the last three years. The financial statements of all cluster agencies received unqualified audit opinions, except for the New South Wales Self Insurance Corporation.

Published

Actions for Volume Six 2014 focusing on Premier and Cabinet

Volume Six 2014 focusing on Premier and Cabinet

Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

All agencies in the NSW Premier and Cabinet cluster received unqualified audit opinions for the year ended 30 June 2014. Overall financial reporting has improved. Agencies submitted their financial statements earlier than last year and for the third year in a row there has been a reduction in the number of misstatements identified during audits.

Published

Actions for Use of Purchasing Cards and Electronic Payment Methods

Use of Purchasing Cards and Electronic Payment Methods

Treasury
Compliance
Fraud
Procurement

NSW government agencies are not making sufficient use of purchasing cards and EFTs to pay for goods and services. There are potential savings in processing costs of around $22 per transaction from purchasing cards and over $7 when using EFTs instead of cheques.

 

Parliamentary reference - Report number #243 - released 5 June 2014

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006

Published

Actions for The New Schools Privately Financed Project

The New Schools Privately Financed Project

Education
Treasury
Infrastructure
Management and administration
Procurement
Project management

In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.

 

Parliamentary reference - Report number #148 - released 8 March 2006

Published

Actions for Government office accommodation

Government office accommodation

Treasury
Finance
Asset valuation
Management and administration
Procurement

The Audit Office has undertaken an audit on Government Office Accommodation. The audit examined the cost effectiveness of long-term leasing versus ownership and the housing of agencies involved with the delivery of core government activities.  Core activities are those intrinsically linked to basic and ongoing functions of Government and Parliament.

It recommends that:

  • the Government consider owning office accommodation, as opposed to leasing, for its long-term core needs, subject to a case by case analysis of the relevant financial and nonfinancial factors

  • the Government undertake an analysis of the costs/savings from proposed asset sales of office accommodation in light of the demonstrated need for long-term office accommodation (for core needs) New, Expired and Expiring Leases

  • given the findings of the own versus lease case studies presented in this report, it is recommended that the Government require agencies to undertake, in collaboration with the Department of Public Works and Services (DPWS) a cost/benefit analysis of available accommodation options prior to committing to any proposed major new leases

  • the Government direct the DPWS, in collaboration with all agencies, to negotiate the renewal of all major expired/expiring leases (where continued occupancy is warranted) in order to reduce the financial risk of above-market rent increases and the risk of cancellation of leases (Major leases are defined, for the purposes of these recommendations, to be those over $500,000 rental per annum or a net lettable area over 1,000 square metres) Management of Property Information

  •  in order to improve the integrity of the Government Office Accommodation Database, agencies be required to respond to the annual data request from DPWS by a predetermined date

  • a senior officer within each agency be required to certify to the accuracy of information provided by an agency as input to the database maintained by DPWS

  • DPWS verify, on a sample basis, information provided by agencies as input to the Government Office Accommodation Database Premier’s Memorandum No 97-2

  • the compliance by agencies with Premier’s Memorandum No 97-2 Government Office Accommodation and Property Disposal be established by DPWS.

 

Parliamentary reference - Report number #45 - released 11 December 1997