Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Eleven 2014 Focusing on Planning and Environment
Volume Eleven 2014 Focusing on Planning and Environment
The quality of financial reporting in the planning and environment cluster continues to improve with fewer reported misstatements over the last two years. The financial statements of all agencies within this cluster received unqualified audit opinions, except for one small agency where the audit is incomplete. Many cluster agencies’ actual revenues, expenses, assets and liabilities varied from budget by more than five per cent, suggesting financial management and budgetary controls could be improved.
Actions for Volume Six 2014 focusing on Premier and Cabinet
Volume Six 2014 focusing on Premier and Cabinet
All agencies in the NSW Premier and Cabinet cluster received unqualified audit opinions for the year ended 30 June 2014. Overall financial reporting has improved. Agencies submitted their financial statements earlier than last year and for the third year in a row there has been a reduction in the number of misstatements identified during audits.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Volume Three 2014 focusing on Parliamentarian Entitlements
Volume Three 2014 focusing on Parliamentarian Entitlements
New South Wales Members of Parliament, when spending their additional entitlements, substantially complied with the Parliamentary Remuneration Tribunal’s Determination for the year-ended 30 June 2013.
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Prequalification Scheme: Performance and Management Services
Prequalification Scheme: Performance and Management Services
There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.
Parliamentary reference - Report number #216 - released 28 September 2011
Actions for Two Ways Together - NSW Aboriginal Affairs Plan
Two Ways Together - NSW Aboriginal Affairs Plan
To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.
Parliamentary reference - Report number #213 - released 18 May 2011
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006