Actions for Members' additional entitlements 2019

Members' additional entitlements 2019

Premier and Cabinet
Compliance

A report has been tabled on the findings and recommendations from the annual review of the additional entitlements claimed by the Members of the New South Wales Parliament (Members) under the Parliamentary Remuneration Tribunal’s Determination (the Determination).

Members claimed $21.5 million of additional entitlements in 2018–19, 2.7 per cent less than the previous year. The decrease is largely attributable to the period in the lead up to the New South Wales State Election, from 26 January to 23 March 2019, during which Members are not permitted to use their Communications Allowance.  In addition, Parliament did not sit from 23 November 2018 until 6 May 2019.

The review found one instance of material non‑compliance with the Determination relating to a Member who claimed the General Travel Allowance but did not provide evidence that the travel related to their parliamentary duties.

14 other departures from the administrative requirements of the Determination, mostly relating to the timing of Members’ claims were identified. The review also found two instances where it was unclear whether reimbursement of Members’ claims had been made strictly in accordance with the Determination.

The report makes three recommendations to the Department of Parliamentary Services to work with the Tribunal to clarify specific wording and requirements in the Determination.  

The Auditor-General has reviewed the compliance of the Members of the NSW Parliament (Members) with certain requirements outlined in the Parliamentary Remuneration Tribunal's Determination (the Determination) for the year ended 30 June 2019.

The Auditor-General's review is designed to provide parliament with limited assurance about Members' compliance with the Determination. We analysed all claims made by Members during the 2018–19 financial year and tested a sample of transactions that we identified as having a greater risk of non-compliance in more detail. Our sample included claims submitted by 59 of the 159 Members.

Results

Our review identified one instance of material non-compliance with the Determination for the year ended 30 June 2019 relating to a Member who claimed the General Travel Allowance but did not provide evidence that the travel related to their parliamentary duties.

Our audit procedures identified 14 other departures from the administrative requirements of the Determination:

  • 8 Members submitted their reconciliations for the Sydney Allowance after the due date
  • 1 Member who elected to receive their Sydney Allowance as an annual payment, returned their unspent Sydney Allowance to the Department after the 30 September 2019 due date
  • 5 Members' claims were not submitted to the Department for payment within 60 days of receipt or occurrence of the expense.

Our audit procedures identified two instances where it was unclear whether Members had been reimbursed for their costs in accordance with the Determination:

  • The Determination specifies the Electorate to Sydney Travel Allowance is for travel between Members’ electorates and Sydney. In administering the allowance, the Department permitted Members’ claims for travel to and from their residence, which may be outside of their electorate. The Tribunal confirmed that this accords with the intent of the Determination.
  • The Determination specifies the Communications Allowance reimburses Members for the cost of producing communications. One Member chartered flights to film materials used to produce communications and to perform parliamentary duties. The Member claimed the cost of flights under the General Travel Allowance, without apportioning any part to the Communications Allowance. The flights and the communication of the filmed material to constituents occurred during the blackout period, during which Members are not permitted to use their Communications Allowance. The Department determined that all travel costs can be claimed under the General Travel Allowance, even if the travel related to the production of communications during the blackout period.
 

Recommendation

The Department should work with the Tribunal to:

  • align the wording of the Determination in relation to the Electorate to Sydney Travel Allowance with the Tribunal’s intent
  • clarify whether Members can claim the cost of travel from their travel allowance when the travel was used to produce communications during the blackout period.

Our audit procedures identified 25 other departures from the Department's administrative guidelines, which support the Determination. Twenty-five Members submitted their annual loyalty scheme declarations after the 31 July 2019 due date specified in the Department's administrative requirements. Their declarations stated that loyalty scheme benefits accrued using their parliamentary allowance and entitlements were not used for private purposes.

Background

The Parliamentary Remuneration Tribunal (the Tribunal) determines the salary and additional entitlements of Members of NSW Parliament (Members), which are set out in the Tribunal's annual Determination.

Published

Actions for Members' Additional Entitlements 2018

Members' Additional Entitlements 2018

Premier and Cabinet
Compliance

The Auditor-General, Margaret Crawford, today released a report on the annual review of additional entitlements claimed by Members of the New South Wales Parliament under the Parliamentary Remuneration Tribunal’s Determination. The review analysed all claims made by Members and tested a sample of claims paid for the year ended 30 June 2018 in more detail.

The review found one Member of Parliament did not materially comply with the Determination. The Member made two unsupported claims for the Electorate to Sydney Travel allowance during the year ended 30 June 2018. The Department of Parliamentary Services has asked the Member to repay these amounts. 

A further 20 departures from the administrative requirements of the Determination were identified, all relating to the timing of Members’ claims. 

The Auditor-General recommended the Department work with the Tribunal to provide more detailed guidance on the activities that meet the definition of 'parliamentary duties' and the documents Members should retain to comply with the Determination.

The Auditor General has reviewed the compliance of the Members of the NSW Parliament (Members) with certain requirements outlined in the Parliamentary Remuneration Tribunal's Determination (the Determination) for the year ended 30 June 2018.

The Auditor General's review is designed to provide Parliament with limited assurance about Members' compliance with the Determination. We analysed all claims made by Members during the 2017-18 financial year and tested a sample of transactions that we identified as having a greater risk of non compliance in more detail. Our sample included claims submitted by 60 of the 140 Members.

Published

Actions for Members' Additional Entitlements 2017

Members' Additional Entitlements 2017

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Regulation
Service delivery

In a report released today, the Auditor-General for New South Wales, Margaret Crawford, identified two instances where Members of Parliament did not materially comply with the Parliamentary Remuneration Tribunal’s Determination relating to additional entitlements. The Department of Parliamentary Services has subsequently requested that the two Members concerned repay amounts that were incorrectly claimed. One claim was made under the Electorate to Sydney Travel allowance and the other from the Communication allowance.

Published

Actions for Procurement and reporting of consultancy services

Procurement and reporting of consultancy services

Finance
Education
Community Services
Industry
Justice
Planning
Premier and Cabinet
Health
Treasury
Transport
Environment
Information technology

Agencies need to improve their compliance with requirements governing the procurement of consultancy services. These requirements help agencies access procurement savings. Also, some agencies have under-reported consultancy fees in their annual reports for the 2016-17 financial year, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The report examined twelve agencies' compliance with procurement and reporting obligations for consultancy services. It notes that it is difficult to quantify total government expenditure on consultants as agencies define ‘consultants’ differently.

NSW Government agencies engage consultants to provide professional advice to inform their decision‑making. The spend on consultants is measured and reported in different ways for different purposes and the absence of a consistently applied definition makes quantification difficult.

The NSW Government’s procurement principles aim to help agencies obtain value for money and be fair, ethical and transparent in their procurement activities. All NSW Government agencies, with the exception of State Owned Corporations, must comply with the NSW Procurement Board’s Direction when engaging suppliers of business advisory services. Business advisory services include consultancy services. NSW Government agencies must disclose certain information about their use of consultants in their annual reports. The table below illustrates the detailed procurement and reporting requirements.

  Relevant guidance Requirements
Procurement of consultancy services PBD 2015 04 Engagement of major suppliers of consultancy and other services (the Direction) including the Standard Commercial Framework
(revised on 31 January 2018, shortly before it was superseded by 'PBD 2018 01')
 
Required agencies to seek the Agency Head or Chief Financial Officer's approval for engagements over $50,000 and report the engagements in the Major Suppliers' Portal (the Portal). 
  PBD 2018 01 Engagement of professional services suppliers
(replaced 'PBD 2015 04' in May 2018)
Requires agencies to seek the Agency Head or Chief Financial Officer's approval for engagements that depart from the Standard Commercial Framework and report the engagements in the Portal. Exhibit 3 in the report includes the key requirements of these three Directions.
 
Reporting of consultancy expenditure Annual Reports (Departments) Regulation 2015 and Annual Reports (Statutory Bodies) Regulation 2015 Requires agencies to disclose, in their annual reports, details of consultants engaged in a reporting year.
  Premier's Memorandum 
'M2002 07 Engagement and Use of Consultants'
 
Outlines additional reporting requirements for agencies to describe the nature and purpose of consultancies in their annual reports.

We examined how 12 agencies complied with their procurement and reporting obligations for consultancy services between 1 July 2016 and 31 March 2018. Participating agencies are listed in Appendix two. We also examined how NSW Procurement supports the functions of the NSW Procurement Board within the Department of Finance, Services and Innovation.

This audit assessed:

  • agency compliance with relevant procurement requirements for their use of consultants
  • agency compliance with disclosure requirements about consultancy expenditure in their annual reports 
  • the effectiveness of the NSW Procurement Board (the Board) in fulfilling its functions to oversee and support agency procurement of consultancy services. 
Conclusion
No participating agency materially complied with procurement requirements when engaging consultancy services. Eight participating agencies under reported consultant fees in their annual reports. The NSW Procurement Board is not fully effective in overseeing and supporting agencies' procurement of consultancy services.
All 12 agencies that we examined did not materially comply with the NSW Procurement Board Direction for the use of consultants between 1 July 2016 and 31 March 2018. 
Eight agencies did not comply with annual reporting requirements in the 2016–17 financial reporting year. Three agencies did not report expenditure on consultants that had been capitalised as part of asset costs, and one agency did not disclose consultancy fees incurred by its subsidiaries. Agencies also defined ‘consultants’ inconsistently.
The NSW Procurement Board's Direction was revised in January 2018, and mandates the use of the Standard Commercial Framework. The Direction aims to drive value for money, reduce administrative costs and simplify the procurement process. In practice, agencies found the Framework challenging to use. To better achieve the Direction’s intent, the Board needs to simplify procurement and compliance processes. 
The Board is yet to publish any statistics or analysis of agencies’ procurement of business advisory services due to issues with the quality of data and systems limitations. Also, the Board’s oversight of agency and supplier compliance with the Framework is limited as it relies on self reporting, and the information provided is insufficient to properly monitor compliance. NSW Procurement is yet to develop an effective procurement and business intelligence system for use by government agencies. Better procurement support, benefit realisation monitoring and reporting by NSW Procurement will help promote value for money in the engagement of consultants.

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.