Actions for Development applications: assessment and determination stages

Development applications: assessment and determination stages

Planning
Local Government
Internal controls and governance
Management and administration
Service delivery

What the report is about

Local councils in New South Wales are responsible for assessing local and regional development applications.

Most development applications are assessed and determined by council staff under delegated authority. However, some development applications must be referred to independent local planning panels or Sydney and regional planning panels for determination.

Councils provide support to local planning panels. The Department of Planning and Environment provides support to Sydney and regional planning panels.

This audit assessed whether Byron Shire Council, Northern Beaches Council and The Hills Shire Council had effectively assessed and determined development applications in compliance with legislative and other requirements.

It also assessed whether The Hills Shire Council, Northern Beaches Council and the Department of Planning and Environment had provided effective support to relevant independent planning panels.

What we found

All councils had established clear roles, responsibilities and delegations for assessment and determination of development applications and had also established processes to ensure quality of assessment reports.

Northern Beaches Council and The Hills Shire Council have established comprehensive approaches to considering and managing risks related to development assessment.

Northern Beaches Council's approach to publishing its assessment reports promotes transparency.

Across a sample of development applications assessed and determined between 2020–22:

  • Northern Beaches Council and The Hills Shire Council had assessed and determined applications in compliance with legislative and other requirements. However, The Hills Shire Council could do more to transparently document any conflicts of interest within assessment reports.
  • Byron Shire Council had assessed most applications in compliance with legislative and other requirements. However, we found opportunities for the Council to:
    • ensure determinations were made in line with delegations
    • strengthen its approach to transparent management of conflicts of interest and quality review of assessments.

The Hills Shire Council and Northern Beaches Council had effectively supported their respective local planning panels.

The Department of Planning and Environment had processes that meet requirements for supporting regional planning panels but could do more to promote consistency in approach, share information across panels and measure the effectiveness of its support.

What we recommended

We made recommendations to Byron Shire Council, The Hills Shire Council and the Department of Planning and Environment to address the gaps identified and improve the transparency of processes.

Local councils in New South Wales are responsible for assessing local and regional development applications under the Environmental Planning and Assessment Act 1979 (EP&A Act).

In assessing development applications, councils consider:

  • whether the proposed development application is compliant with legislation and environmental planning instruments
  • whether the proposed development meets local planning controls and objectives
  • any environmental, social and economic impacts
  • any submissions from impacted properties, neighbours and interested parties
  • the public interest.

Once assessed, a development application will be determined by council staff under delegated authority, the elected council, or an independent planning panel.1 

The involvement of a particular independent planning panel is established under legislative and policy instruments, and depends on the type and value of the proposed development. Most development applications are assessed and determined by council staff under delegated authority.

In determining development applications, independent planning panels must manage any potential, real or perceived conflicts of interest of panel members for a given development application, meet and vote on development applications, and publish their decisions and reasons.

Under the EP&A Act, and as required by statutory instruments and procedures, councils and the Department of Planning and Environment (DPE) must provide secretariat and other support functions to independent planning panels.

Previous reviews and inquiries have identified several significant risks that are present within the processes involved in the assessment and determination of development applications. These risks include possible non-compliance with complex legal and policy requirements, potential improper influence from developers and other stakeholders, and a perceived lack of transparency within the planning system and planning outcomes.

There are several planning pathways for development in New South Wales. This audit focuses on local and regional development that requires assessment and determination by a local council and/or an independent local planning panel or Sydney or regional planning panel in three Local Government Areas (LGAs): Byron Shire Council, Northern Beaches Council, The Hills Shire Council.

Audited councils were selected from a range of criteria, including:

  • the number, value and types of development applications determined in 2018–19
  • average determination timeframes
  • appeals against determinations and Land and Environment Court outcomes
  • LGA demographics.

The audit also avoided councils that had previously been subject to a performance audit.

The objective of this audit was to assess whether:

  • selected councils have effectively assessed and determined development applications in compliance with relevant legislation, regulations and government guidance
  • selected councils and DPE effectively support independent planning panels to determine development applications in compliance with relevant legislation, regulations and government guidance.

Conclusion – Byron Shire Council

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the effectiveness of the Council's approach is limited by gaps in governance, risk management and internal controls.

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the Council does not have a consolidated policy and procedure for development assessment, has not adequately followed up on the outcomes of internal reviews that identified opportunities to strengthen its assessment and determination procedures and approach, and has not demonstrated that it has managed relevant risks effectively.

The Council has not ensured that delegations have been consistently followed in the assessment of development applications.

Byron Shire Council's approach to managing conflicts of interest in development assessments does not provide transparency over potential conflicts of interest.

Byron Shire Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has also implemented a separate policy that details additional requirements for managing conflicts of interest relevant to the development assessment process, but has not regularly updated this policy and requirements between it and the Code of Conduct have not been aligned. This creates a risk that planning staff may be following inconsistent or outdated advice in managing conflicts of interest.

Across the period of review, the Council did not require staff to provide a disclosure of interest for individual development applications to be contained within assessment reports. Including these disclosures would increase transparency and ensure that staff are sufficiently considering any conflicts of interest relevant to each separate assessment process.

Byron Shire Council has processes that promote compliance with legislation, regulation and government policy, but can improve how it undertakes some aspects of these that would ensure transparency, quality and consistency.

Our review of a sample of completed development applications from the Council indicated that most assessments were completed in compliance with relevant legislation, regulations and government guidance, but that there were some opportunities to improve elements of the assessment process, including: transparency of any conflicts of interest involved in the assessment process, ensuring compliance with delegated authority limits, and consideration of modification application provisions.

The Council has established templates to guide planners through relevant assessment considerations required by legislation, regulations and other guidance. However, it could do more to strengthen its approach to peer or manager review, monitoring legislative changes, and how it monitors the completion of relevant training by planning staff. 

 

Conclusion – Northern Beaches Council

Northern Beaches Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has a clear governance and risk management framework for development assessment that sets out roles, responsibilities and delegations.

Northern Beaches Council has established clear roles, responsibilities and delegations for development application assessment and determination. The Council has identified development assessment related risks, and has put in place controls and mitigating actions to manage the risks to within risk tolerances.

Northern Beaches Council's approach to managing conflicts of interest promotes transparency.

Northern Beaches Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has implemented an additional framework for planning staff to respond to the risk of conflicts of interest in development assessment processes. This framework requires its staff to disclose any conflicts of interest as a formal step in assessing development applications and includes declarations of any interests within assessment reports or planning panel minutes.

Our review of a sample of completed development applications indicated that the assessment reports had been compliant with the Council's approach to transparently documenting conflicts of interest.

Northern Beaches Council has established processes to deliver consistent, quality assessment of development applications.

Northern Beaches Council staff use an electronic development assessment tool that provides guidance, links to legislative and policy instruments and other applications that support assessment and drive consistency in approach. The Council applies a peer review process in which a manager or team member in a more senior position reviews an assessment report prior to determination to ensure that expected standards of quality and consistency have been met.

Our review of a sample of completed development applications indicated that assessments were undertaken in compliance with relevant legislation, regulations and government guidance.

Northern Beaches Council transparently documents assessment reports, supporting information and determination outcomes.

Northern Beaches Council has implemented a transparent approach to how it assesses and determines development applications. The Council publishes assessment reports, supporting technical reports, plans and submissions for all development applications. Notices of determination and final plans are also published alongside the assessment reports, allowing for greater transparency to the public.

Northern Beaches Council has established processes to effectively support the Northern Beaches Local Planning Panel.

Northern Beaches Council has established processes to support the Northern Beaches Local Planning Panel as required under legislative and policy instruments. The Council has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – The Hills Shire Council

The Hills Shire Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has established a comprehensive governance and risk management framework for development assessment that sets out clear roles, responsibilities and delegations.

The Hills Shire Council has established a comprehensive framework for managing risks related to development assessment. Such risks are clearly identified and associated controls are in place to reduce or mitigate the risks. The Council has undertaken regular internal audits of development assessments, including reviewing completed applications to ensure compliance with relevant legislative and policy requirements.

The Council has established clear roles, responsibilities and delegations, and its staff assessing and determining development applications are supported by a standard set of policies and procedures for undertaking assessment and determination of applications.

The Hills Shire Council is managing conflicts of interest in line with Code of Conduct requirements but could more transparently document these.

The Hills Shire Council manages conflicts of interest for those involved in development application processes through provisions under its Code of Conduct. Under this Code of Conduct, staff must declare any conflicts of interest to their manager. However, the Council does not require staff to disclose any conflicts of interest in development application assessment reports which limits transparency to reviewing managers or any other determination bodies.

The Hills Shire Council has established processes to deliver consistent, quality assessment of development applications.

The Hills Shire Council has established templates to guide planners through relevant development assessment and determination considerations required by legislation, regulations and other guidance. The Council requires a peer review to occur prior to any determination which ensures a check on the compliance and quality of the assessment report prepared.

Our review of a sample of completed development applications from the Council indicated that assessments were performed in compliance with relevant legislation, regulations and government guidance.

The Hills Shire Council has established processes to effectively support The Hills Shire Local Planning Panel.

The Hills Shire Council has met requirements to provide secretariat and other support to The Hills Shire Local Planning Panel as required under legislative and policy instruments. It has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – Department of Planning and Environment

The Department of Planning and Environment (DPE) has established processes that meet its statutory and policy requirements to support Sydney and regional planning panels.

DPE has established processes to provide secretariat and other support to planning panels. It has met requirements to provide administrative support to the panels through its planning panels secretariat including undertaking administrative functions, supporting recruitment of panel members, and addressing complaints about the panel processes.

DPE has not ensured collection of annual pecuniary interest declarations for all panel members for the three Sydney and regional planning panels in scope for this audit. DPE could not provide annual pecuniary interest declarations for part of the audit period for three of the 47 members of these panels, as is required by DPE's Code of Conduct for Regional Planning Panels.

DPE does not formally measure its effectiveness in providing support to panels, but panel chairs consulted as part of this audit advised that they had no concerns with the level of secretariat support provided by DPE.

DPE could do more to facilitate information sharing between panels and could formalise how it provides comparative information to panels to improve consistency and standardisation in approach and share good practice. DPE has identified these gaps in reviews of its services and functions and has a plan in place to address them.

DPE has effectively documented planning panel decisions and made them available to all stakeholders. It also effectively documented interests declared as part of consideration of development applications for in-scope panels. 


1 Prescribed councils within designated Sydney districts are required to refer contentious development applications to local planning panels for determination. If the proposed development is above a threshold for estimated cost of works, or meets other prescribed criteria, the EP&A Act may require it to be referred to a Sydney or regional planning panel.

This audit continues a series of audits examining the development assessment process in NSW local councils and is focused on the assessment and determination stages.

The Audit Office of New South Wales previously considered local government development assessments in our 2019 performance audit: 'Development assessment: pre-lodgement and lodgement in Camden Council and Randwick City Council'.

Appendix one – Response from agencies

Appendix two – Council profile: Byron Shire Council

Appendix three – Council profile: Northern Beaches Council

Appendix four – Council profile: The Hills Shire Council

Appendix five – About the audit 

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #370 - released 12 December 2022

 

Published

Actions for Effectiveness of the Biodiversity Offsets Scheme

Effectiveness of the Biodiversity Offsets Scheme

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Regulation

What the report is about

This audit examined whether the Department of Planning and Environment (DPE) and the Biodiversity Conservation Trust (BCT) have effectively designed and implemented the Biodiversity Offsets Scheme (‘the Scheme’) to compensate for the loss of biodiversity due to development.

Under the Biodiversity Conservation Act 2016, the Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements on sites to generate credits for the unique biodiversity on that land. These credits can be sold to offset the negative impact of development on biodiversity.

What we found

DPE has not effectively designed core elements of the Scheme. DPE did not establish a clear strategic plan to guide the implementation of the Scheme.

The BCT has various roles in the Scheme but lacked safeguards against potential conflicts, creating risks to credit supply.

The effectiveness of its implementation has also been limited. Key concerns around the Scheme’s transparency, sustainability and integrity are yet to be fully resolved.

A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand. DPE has not established a clear, resourced plan to manage the shortage in credit supply. Data about the market, published by the DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to readily support market participation.

These factors create a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from development, and that the DPE will not be able to assess the Scheme’s overall effectiveness.

DPE is leading work with the BCT to improve the Scheme, but this is not yet guided by a long-term strategy with clear goals.

What we recommended

The audit made 11 recommendations to DPE and the BCT, focusing on:

  • a long-term strategic plan for the Scheme
  • improvements to the operation and transparency of the market and credit supply
  • frameworks to ensure the financial and ecological sustainability of biodiversity stewardship sites
  • enhanced public reporting and data management
  • resolving issues in conflicting governance and oversight.

 

 Fast facts

  • 96% –  proportion of developer demand for species credits not met by current supply
  • 97% – proportion of species credits that have never been traded on the biodiversity market
  • 60% – proportion of the 226 Biodiversity Stewardship sites under active land management
  • $90m – value of developers’ obligations paid directly into the Biodiversity Conservation Fund
  • 20% – proportion of developer obligations transferred to the BCT that have been acquitted.

The NSW Government's Biodiversity Outlook Report 2020 estimates that, without effective management, only 50% of species and 59% of ecological communities that are listed as threatened in New South Wales will still exist in 100 years. The NSW State of the Environment 2021 report identifies habitat destruction and native vegetation clearing as presenting the single greatest threat to biodiversity in the State.

According to the Organisation for Economic Co-operation and Development (OECD), biodiversity offsets are 'measurable conservation outcomes that result from actions designed to compensate for significant, residual biodiversity loss from development projects'. The OECD states that a feature of such schemes is that biodiversity offsets are intended to be implemented as the 'final step of a mitigation hierarchy' whereby reasonable first steps are taken to avoid and minimise the negative impacts.

The NSW Biodiversity Offsets Scheme was established in 2017 under the Biodiversity Conservation Act 2016 (the Act). The purpose of the Act is to 'maintain a healthy, productive and resilient environment for the greatest well-being of the community, now and into the future, consistent with the principles of ecologically sustainable development'.

The Department of Planning and Environment (DPE) designed and manages this Scheme. Under the Act, a feature of the Scheme is a 'market-based conservation mechanism through which the impacts to biodiversity can be offset.' The Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements (BSAs) on sites to generate biodiversity credits, which can be sold to offset the negative impact of development on biodiversity. BSA sites are intended to be managed over the long term to generate the biodiversity gains required to offset the impact.

The Biodiversity Conservation Trust (BCT) monitors and supports landholders to manage BSA sites under the Scheme. This includes making payments to landholders from funds held in the Biodiversity Stewardship Payments Fund for undertaking the required biodiversity management actions.

This Scheme was preceded by several other offsetting schemes in New South Wales, including the BioBanking scheme that started in 2008. DPE has arrangements to transition sites, credits, and offset obligations from this and other previous schemes.

The current biodiversity credit market in New South Wales consists of 1394 different types of ecosystem credits, which are approved to be traded in 364 different offset trading groups, and 867 different species credits. Trading rules, set out in the Biodiversity Conservation Regulation 2017 (the Regulation), prioritise offsetting the obligations of a development with like-for-like ecosystem or species credits.

The Scheme is implemented through the planning system in New South Wales. Proposed development that involves the clearing of native vegetation, and meets certain thresholds, is required to undertake a Biodiversity Development Assessment Report. These reports determine an offset obligation, in biodiversity credits, to compensate for the biodiversity loss proposed. These reports are considered by consent authorities (such as a council, for local development, or by the Minister for Planning for major projects). An offset obligation is then included in the conditions of development approval.

In addition to establishing a market for trading between developers, with offset obligations, and landholders, who sell credits from their BSA sites, the Scheme allows developers to pay into the Biodiversity Conservation Fund and transfer their obligations to the BCT. This allows the developer to proceed with their project. The BCT must then meet these acquired obligations by buying the required credits, or by undertaking other approved activities set out in the Regulation. The BCT has more options than developers on how and when it acquits its obligations.

This audit examined whether DPE and the BCT have effectively designed and implemented the Biodiversity Offsets Scheme to compensate for the loss of biodiversity due to development.

Conclusion

The Department of Planning and Environment (DPE) has not effectively designed core elements of the NSW Biodiversity Offsets Scheme. DPE did not establish a clear strategy to develop the biodiversity credit market or determine whether the Scheme’s operation and outcomes are consistent with the purposes of the Biodiversity Conservation Act 2016.

The effectiveness of the Scheme's implementation by DPE and the BCT has been limited. A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand: this includes a potential undersupply of in-demand credits for numerous endangered species. Key concerns around the Scheme’s integrity, transparency, and sustainability are also yet to be fully resolved. As such, there is a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from the impacts of development, and that DPE will not be able to assess the Scheme’s overall effectiveness.

DPE developed the Scheme following a 2014 review of the State's biodiversity legislation and building on previous offsetting arrangements in New South Wales. At the time the Scheme commenced in 2017, DPE lacked a strategic plan to guide its implementation, set clear outcomes and performance measures, and respond effectively to risks. DPE did establish a detailed scientific method for assessing biodiversity impacts under the Scheme and a system for accrediting assessors to undertake this technical work. These are important foundations for the robustness of the Scheme.

The Scheme has been in place for five years, but the biodiversity credit market is not well developed. Most credit types have never been traded. Also, according to DPE data, around 90% of demand cannot be matched to credit supply – and there is likely to be a substantial credit undersupply for at least seven endangered flora species, three endangered fauna species, and eight threatened ecological communities. Credit demand is projected to grow – especially in relation to the NSW Government’s $112.7 billion four-year infrastructure pipeline.

As with any market, potential participants need information about demand and price in order to understand risks and opportunities. But information about the biodiversity credit market, published by DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to support market participation. This can create uncertainty for landholders who may be weighing the costs and benefits of establishing Biodiversity Stewardship Agreement (BSA) sites, and for development proponents who need to know whether they can purchase sufficient credits and at what price. Development proponents who lack market information are being incentivised to meet their offset obligations by paying into the Biodiversity Conservation Fund, which is managed by the BCT. This option provides developers with more certainty that enables them to progress their projects, but does not result in the development being offset until the BCT later acquits the obligation.

The BCT has multiple roles in the Scheme. These include setting-up and administering BSAs which generate credits, acquiring offset obligations from developers who pay into the Biodiversity Conservation Fund, and purchasing credits to meet its acquired obligations. There have been inadequate safeguards to mitigate the potential for conflicts between these roles. As the BCT directs its efforts towards facilitating BSA sites and purchasing credits to meet its obligations, there is a risk that government is insufficiently focused on supporting overall credit supply.

DPE has begun developing a credit supply strategy. Its absence, and a lack of clarity around responsibility for credit supply under the Scheme, has contributed to the significant risk of insufficient and poorly matched credits to meet the growing demand. The BCT's acquired obligations from developers have been increasing year-on-year, and are likely to continue to grow. 

There is a risk that the BCT will not have sufficient funds to acquit its growing obligations with like-for-like credits, which could result in sub-optimal biodiversity outcomes. The Scheme rules allow the BCT to acquit its obligations with measures other than like-for-like credits. DPE has not provided clear guidance to the BCT on when or how to do so, or how this would fulfil the 'no net loss' of biodiversity standard.

There are transparency and integrity risks to the Scheme. DPE does not maintain a public register of biodiversity credits with complete information, including credits' transaction histories, consistent with the legislative intent for a single register. DPE also does not have ready access to information to check that developments have been acquitted with the required credits.

Risks to the sustainability of the Scheme and its outcomes remain. DPE and the BCT have not yet implemented a decision-making and intervention framework to ensure adequate initial and ongoing funding for the long-term management of new and existing BSA sites. DPE also did not collect ecological data from sites under previous schemes before they were transitioned, and BCT only introduced ecological monitoring requirements for new BSA sites in March 2021. The lack of monitoring requirements creates a risk that the biodiversity gains, which BSA sites are required to generate to offset biodiversity losses, will not be measured and achieved under the Scheme.

This section presents an overview of the status of the biodiversity credit market in New South Wales. It describes development of the market under the Scheme in the context of transitional arrangements from previous schemes, and the extent of market participation and transactions to date. It also presents information about emerging trends in credit demand and supply.

Background

A purpose of the Biodiversity Conservation Act 2016 (the Act) is to establish a market-based conservation mechanism through which impacts on biodiversity can be offset. Sufficient credits of appropriate types, which are well matched to demand, are necessary for enough transactions to inform prices and enable efficient like-for-like offsetting. For transactions to occur efficiently in the market, participants require reliable and easy-to-access information about supply, demand and price.

The Scheme was established in 2017 with an existing credit supply and offset obligations (credit demand) as regulations had been introduced to preserve and transition credits and obligations from previous schemes including the BioBanking Scheme, which started in 2008.

Credits under the BioBanking scheme are referred to as 'BBAM credits', and credits under the current Scheme are referred to as 'BAM credits'. BBAM credits are still available, and the transitional arrangements enable DPE to determine the 'reasonable equivalence' of these to the current Scheme's credit numbers and classes. DPE has stated that reasonable equivalence of credits is based on ecological not financial equivalence. 

This section assesses the clarity and alignment of the goals of the Scheme to key features of its design and operations. It also examines structural elements of the Scheme that aim to maintain integrity within administering agencies, and the status of actions to address risks or issues.

Background

The Biodiversity Conservation Act 2016 (the Act) sets out the legal framework for the Scheme. Given the complexities, financial interests, and range of stakeholders associated with the Scheme, it requires strong safeguards. Transparency and assurances around the Scheme's integrity are also relevant to participants' confidence in it, which in turn is important for market development.

Core components of the Scheme, identified in section 1.3 of the Act, are to be consistent with the ‘principles of ecologically sustainable development’.

The Act and other administrative arrangements of government allocate responsibility to DPE and the Minister for Environment and Heritage for the Scheme’s design and elements of its implementation. This includes responsibility for the Scheme’s policy, legislative and regulatory framework.

Responsibility is allocated to the BCT for implementing and operating certain elements of the Scheme. This includes administering Biodiversity Stewardship Agreements (which generate credits) and securing offsets on behalf of development proponents who pay into the Biodiversity Conservation Fund to meet their offset obligations.

This broad legislative framework is not intended to detail responsibilities for the full range of roles and activities that agencies need to take to implement and regulate the Scheme effectively, and ensure its good governance. Agencies should do this as part of sound and transparent public administration. 

This section assesses how effectively components of the Scheme have been designed and are being implemented to provide assurance that the impacts of development are being avoided and minimised such that only ‘unavoidable’ impacts remain to be offset. The section also assesses whether the Scheme and its market embeds the necessary controls to ensure that obligations are offset as required.

Background

The Biodiversity Assessment Method, and the quality of its application by DPE-Accredited Assessors, is critical to the robustness the Scheme. The method is designed to be applied to avoid and minimise impacts at proposed development sites before identifying offset obligations. The effectiveness of Scheme outcomes requires that obligations are offset with the retirement of the necessary and appropriate credits.

The Biodiversity Conservation Act 2016 (the Act) requires the relevant Minister (the current Minister for Environment and Heritage) to establish a method for the purpose of assessing the impacts of actions on threatened species and ecological communities.

The Act also specifies that this method must be applied by an accredited person. DPE is responsible for the design and implementation of this accreditation system, arrangements for which are set out in an instrument under the Act.

A Biodiversity Development Assessment Report is a report by a DPE-Accredited Assessor using the Biodiversity Assessment Method. These reports assess the biodiversity impacts of the proposed development and establish offset obligations as part of the development approval process. It is important that local councils and other development consent authorities understand and can assess the quality of these reports.

DPE manages the process of ‘retiring’ credits against the identified offset obligations. Once a credit is retired it cannot be reused to acquit another obligation, which is critical to Scheme outcomes. DPE is also responsible for maintaining records of credit transactions, which results in a legally binding transfer of credit ownership from seller to buyer. 

This section assesses how effectively the supply of biodiversity credits has been supported by encouraging and enabling landholders to participate in the Scheme. It also assesses whether sufficient action is underway to address issues and risks to the establishment of BSA sites, especially in the context of known credit supply issues (section 2).

Background

Credit supply is generated when a landholder establishes a Biodiversity Stewardship Agreement (BSA) on their land. Establishing a BSA site requires landholders agree to an in-perpetuity management plan, so it is important that they have sufficient support and access to relevant information about risks and opportunities when deciding to do so. Ensuring adequate credits supply underpins the Scheme's ability to deliver the intended biodiversity outcomes.

A landholder establishes an offset site through a BSA, which is a legal agreement with the Minister of Environment and Heritage (delegated to the Biodiversity Conservation Trust). The BSA is registered on the title of the land.

DPE-Accredited Assessors develop Biodiversity Stewardship Site Assessment Reports, which are submitted by landholders to the BCT as part of the BSA application. These reports apply the Biodiversity Assessment Method to detail the number and types of credits that a BSA site is expected to generate by implementing a 20-year management plan. The BCT issues credits to landholders on registration of the BSA.

Ensuring an adequate and appropriate supply of credits is important so that like-for-like matches between credits and obligations can be efficiently secured in a timely way. This minimises the use of offset variation rules, and can avoid potential delays in developers securing appropriate offsets to meet their offset obligations. It also makes it easier for the BCT to locate the necessary credits to acquit the obligations it acquires from developers. 

This section assesses how effectively BSA sites, which need to be managed by landholders to generate the biodiversity gains represented by credits, are regulated and supported by the Biodiversity Conservation Trust. It also assesses whether actions have been taken to address identified risks to the suitability of funds required to ensure long-term BSA site management.

Background

For Biodiversity Stewardship Agreement (BSA) sites to achieve the expected biodiversity gains to offset losses from development impact, they need sufficient funding for the required management actions, and to be effectively regulated and supported over the long-term. Funding for these sites is generated through the returns on landholders' initial investment (Total Fund Deposit). The BCT is required to monitor landholders' compliance with BSAs and should also ensure ecological outcomes on sites are measured.

DPE and the BCT are responsible for developing and implementing a system of oversight to ensure the implementation of management actions at BSA sites is delivering the intended outcomes in a financially and environmentally sustainable way. The agencies' key mechanisms for delivering this are:

  • calculating the costs of the required land management actions in perpetuity
  • annual reporting systems for monitoring compliance with land management requirements
  • reporting systems for monitoring ecological outcomes arising from land management actions.

Landholders are required to pay the required Total Fund Deposit amount for their BSA accounts into the Biodiversity Stewardship Payments Fund, which is held in trust and managed by the BCT. A costing tool is used by landholders to calculate the value of the deposit, based on the required management payments (in perpetuity), administrative fees, and the discount rate applied.

The Total Fund Deposit can be paid upfront but is usually paid from the proceeds of the sale of credits. Once this occurs the BSA site becomes 'active' and management payments commence to enable the landholder to undertake the required management actions. BSA sites that have not yet sold enough credits to make the deposit are 'passive' sites that do not require active land management.

Sites in passive management for an extended duration present risks to biodiversity outcomes, and potentially to Scheme integrity, if the quality of credits is undermined due to an absence of active site management. 

Appendix one – Response from agencies 

Appendix two – Like-for-like, variation and ancillary rules

Appendix three – Detail on progress of the IIAP

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #367 - released 30 August 2022

Published

Actions for NSW planning portal

NSW planning portal

Planning
Industry
Environment
Local Government
Information technology
Project management
Risk

What the report is about

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal).

Using the portal, relevant planning activities can be carried out online, including all stages of development applications.

The portal has been developed under three separate business cases in 2013, 2014 and 2020.

In late 2019, the government mandated the use of the portal for all development applications. This decision took effect across 2020–21.

This audit assessed the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. 

What we found

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information, and allow them to prepare and submit development applications online.

Shortcomings in the department's initial planning and management of the program led to a significant time overrun. It has taken the department longer and cost significantly more to implement the portal than first anticipated. 

In recent years the department has improved the planning, implementation and governance of the ePlanning program, resulting in improved delivery of the portal’s core functions.

The department now has a clear view of the scope necessary to finalise the program, but has not yet published the services it plans to implement in 2022 and 2023.

Mandating the use of the portal for all development applications changed the program's strategic risk environment and required the department to work more closely with a cohort of stakeholders, many of whom did not want to adopt the portal.

Despite this change, the department kept its overall delivery approach the same.

While implementation of the portal has delivered financial benefits, the department has overestimated their value.

The Department has only reported benefits since 2019 and has not independently assured the calculation of benefits.

What we recommended

By December 2022, the department should:

  • publish a roadmap of the services it expects to release on the portal across 2022 and 2023
  • update its ePlanning program assumptions, benefits targets and change management approach to reflect the government's decision to mandate the use of the portal for all stages of a development application
  • independently assure and report publicly the correct calculation of ePlanning program benefits.

Fast facts

  • 10 years taken to implement the portal when completed
  • 3 years longer than initially planned to implement the portal
  • $146m capital expenditure on the portal when completed
  • $38.5m more spent than planned in the business cases.

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal, or the planning portal). The department defines the portal as an online environment where community, industry and government can work together to better understand and meet their obligations under the Environmental Planning and Assessment Act 1979 (NSW). Using the portal, relevant planning activities can be carried out online throughout New South Wales. This includes, but is not limited to:

  • applying for and gaining planning approval
  • applying for and gaining approval for building works, sub-dividing land and similar activities
  • issuing occupancy and other certificates.

The portal has been developed under three separate business cases. The first business case in 2013 led to the creation of a central portal, which made planning information available to view by planning applicants and allowed some planning applications to be lodged and tracked online.

Under a second business case prepared in 2014, the department set out to improve and widen the functions available via the portal. The department prepared a third business case in 2020 to fund further improvements to the portal over the period July 2020 to June 2023. The third business case also extended the portal's functions to support the building and occupation stages of the planning cycle.

In late 2019, the government mandated the use of the portal for all stages of development applications. This decision took effect across 2020–21 and applied to all councils as well as certifiers and others involved in the planning process.

The objective of this performance audit was to assess the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. We investigated whether:

  • delivery of the NSW planning portal was planned effectively
  • sound governance arrangements are in place to ensure effective implementation of the program
  • users of the NSW planning portal are supported effectively to adopt and use the system.
Conclusion

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information and allow them to prepare and submit development applications online. Implementation was initially hindered by deficiencies in planning and it has taken the department significantly longer and cost significantly more to implement the portal than first anticipated. While the portal's implementation has delivered financial benefits, the department has overestimated their value. As a result, the department cannot yet demonstrate that the portal has achieved overall financial benefits, relative to its costs.

In the first two years of the ePlanning program, the department delivered a portal that allowed planners, developers, certifiers and the public to view important planning information. However, the department found the delivery of a second, transactional version of the portal in 2017 to be much more challenging. This version was intended to offer more integrated information and allow development applications to be submitted and managed online. The department did not rollout this version after a pilot showed significant weaknesses with the portal's performance. A subsequent review found that this was partly because the department did not have a clear view of the portal’s role or the best way to implement it. In recent years the department has improved the planning, implementation and governance of the ePlanning program resulting in improved delivery of the portal’s core functions.

By the time the program reaches its scheduled completion in 2023, it will have taken the department ten years and around $146 million in capital expenditure to implement the portal. This will be significantly longer and more expensive than the department originally expected. This overrun is partly due to an increased scope of services delivered through the portal and an initial under-appreciation of what is involved in creating a standard, central resource such as the portal. The department also experienced some significant implementation difficulties – which saw the transactional portal discontinued after it was found to be not fit for purpose. Following this, the department re-set the program in 2017–18 and re-planned much of the portal's subsequent development.

In November 2019, the New South Wales Government decided to mandate the use of the portal for all stages of development applications by the end of 2020–21. The department had previously planned that the portal would be progressively adopted by all councils and other stakeholders over the five years to 2025. The decision to mandate the portal's use for all development applications brought forward many of the portal's benefits as well as the challenges of its implementation. The department did not change its overall delivery approach in response to the changed risks associated with the government's decision to mandate use of the portal.

The current version of the portal has given the department more timely and comprehensive planning information and has helped New South Wales to provide continuous planning services during COVID-19 lockdowns, which interrupted many other public functions. The portal has also delivered financial benefits, however the department has not independently assured benefits calculations carried out by its consultant, and the reported benefits are overstated. In addition, some stakeholders report that the portal is a net cost to their organisation. This has included some certifiers and some councils which had implemented or had started to implement their own ePlanning reforms when use of the portal was mandated in 2019. The department now needs to address the issues faced by these stakeholders while continuing to deliver the remaining improvements and enhancements to the portal. Over the remaining year of the program, it will be critical that the department focuses on the agreed program scope and carefully evaluates any opportunities to further develop the portal to support future planning reforms.

This part of the report sets out how:

  • the ePlanning program has been planned and delivered
  • users of the portal have been supported
  • the program has been governed.

This part of the report sets out the ePlanning program's:

  • expected and reported financial benefits
  • calculation of financial benefits.

In 2019, the department increased its expectations for net financial benefits

The department's three ePlanning business cases each forecast substantial financial benefits from the implementation of the planning portal. The department expected that most financial benefits would flow to planning applicants due to a quicker and more consistent planning process. It also expected that government agencies and councils would benefit from the portal.

Exhibit 6: Summary of the financial benefits originally expected
  Business case 1
($ million)
Business case 2
($ million)
Business case 3
($ million)
Total
($ million)
Benefits 90.0 44.3 270.9 405.2
Costs 43.3 29.4 89.8 162.5
Net benefits 46.7 15.0 181.1 242.7

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for business case 1, 2 and 3 amounts are expressed in 2013, 2015 and 2019 dollars respectively. All amounts are discounted at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

In 2019 the department commissioned a review to explore opportunities to better identify, monitor and realise the benefits of the ePlanning program. Using this work, the department updated the expected benefits for business cases 1 and 2 to take account of:

  • errors and miscalculations in the original benefits calculations
  • slower delivery of the portal and changes to the take-up of portal services by councils
  • changes to the services supported by the portal.
Exhibit 7: Summary of the financial benefits expected for business case 1 and 2 after the 2019 update
  Original business case 1 and 2 (combined)
($ million)
New business case 1 and 2 (combined)
($ million)
Benefits 134.3 210.6
Costs 72.7 96.3
Net benefits 61.7 114.3

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for the original business case 1 and 2 are expressed in 2013 and 2015 dollars respectively. The new combined amount is expressed in 2019 dollars. All amounts are discounted or inflated at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

Reported benefits significantly exceed the current targets

In September 2021, the department reported that the program had achieved $334 million of benefits over the three financial years up to June 2021 plus the first two months of 2021–22. These reported benefits were significantly higher than expected. 

Exhibit 8: Reported financial benefits from the ePlanning program
  2018–19
($ million)
2019–20
($ million)
2020–21
($ million)
July to August 2021
($ million)
Total
($ million)
Benefits 5.2 68.8 214.7 45.1 333.8
Target 2.5 14.4 56.7 19.2 92.8
Amount and per cent above target 2.7
108%
54.4
378%
158
279%
25.9
135%
241
260%

Source: Audit Office analysis of data provided by the Department of Planning and Environment.

The department attributes the higher-than-expected financial benefits to the following:

  • benefit targets have not been updated to reflect the impact of the 2019 decision to mandate the use of the portal for all development applications. This decision brought forward the expected benefits as well as potential costs of the program. However, the department did not update its third business case which was draft at the time. The business case was subsequently approved in July 2020
  • one-off cost savings for agencies not having to develop their own systems
  • public exhibitions of planning proposals continuing to be available online during 2020 when some newspapers stopping printing due to COVID-19.

The calculation of benefits is overstated

The department reported $334 million of benefits in September 2021 due to the ePlanning program. This calculation is overstated because:

  • a proportion of reported benefits is likely to be due to other planning reforms
  • the calculation of the largest single benefit is incorrect
  • the reported benefits may not fully account for dis-benefits reported by some stakeholders.

The program’s benefits are calculated primarily from changes in planning performance data, such as the time it takes to determine a planning development application. The department currently attributes the benefits from shorter planning cycles entirely to the effect of the ePlanning program. However, planning cycles are impacted by many other factors such as the complexity of planning regulations and the availability of planning professionals. Planning cycles may also be impacted by other departmental initiatives which are designed to improve the time that it takes for a planning application to be evaluated. The Introduction describes some of these initiatives.

The largest contribution to the department’s September 2021 benefit report was an estimated saving of $151 million for developers due to lower costs associated with holding their investment for a shorter time. However, the department’s calculation of this benefit assumes a high baseline for the time to determine a development application. It also assumes that all development applications except for additions or alterations to existing properties will incur financing costs. However, a small but material number of these applications will be self-financed. The calculation also includes several data errors in spreadsheets.

The calculation of some benefits relies upon an extrapolation of the benefits experienced by a small number of early-adopter councils, including lower printing and scanning costs, fewer forms and quicker processing times. However, some councils report that their costs have increased following the introduction of the portal, primarily because aspects of the portal duplicate work that they carry out in their own systems. The portal has also required some councils to re-engineer aspects of their own systems, such as the integration of their planning systems with other council systems such as finance or property and rating systems. It has also required councils to create new ways of integrating council information systems with the planning portal.

The department has published information to help councils and certifiers to automatically integrate their systems with the planning portal. This approach uses application programming interfaces (or APIs) which are an industry-standard way for systems to share information. In April and May 2021, the government granted $4.8 million to 96 regional councils to assist with the cost of developing, implementing and maintaining APIs. The maximum amount of funding for each council was $50,000. The department is closely monitoring the implementation of APIs by councils and other portal users. Once they are fully implemented the department expects APIs to reduce costs incurred by stakeholders.

The department has not yet measured stakeholder costs. It was beyond the scope of this audit to validate these costs.

The department has not independently assured the calculation of reported benefits

In 2020 the department appointed an external provider to calculate the benefits achieved by the ePlanning program. The department advised that it chose to outsource the calculation of benefits because the provider had the required expertise and because it wanted an independent calculation of the benefits. The process involves:

  • extraction and verification of planning performance data by the department
  • population of data input sheets by the department
  • calculation of benefits by the external provider using the data input
  • confirmation by the department that the calculation includes all expected benefit sources.

The department does not have access to the benefits calculation model which is owned and operated by the external provider. The department trusts that the provider correctly calculates the benefits and does not verify the reported benefit numbers. However, as the benefits model involves many linked spreadsheets and approximately 300 individual data points, there is a risk that the calculation model contains errors beyond those discussed in this audit.

The reported benefits have only been calculated since 2019

The department originally intended to track benefits from October 2014. However, it only started to track benefits in 2019 when it appointed an external provider to calculate the benefits achieved by the portal. Any benefits or dis-benefits between the introduction of the portal and 2019 are unknown and not included in the department’s calculation of benefits.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #366 - released 21 June 2022

Published

Actions for Facilitating and administering Aboriginal land claim processes

Facilitating and administering Aboriginal land claim processes

Planning
Environment
Industry
Local Government
Premier and Cabinet
Whole of Government
Cross-agency collaboration
Compliance
Management and administration

What the report is about

The Aboriginal Land Rights Act 1983 (NSW) (the Act) provides land rights over certain Crown land for Aboriginal Land Councils in NSW.

If a claim is made over Crown land (land owned and managed by government) and meets other criteria under the Act, ownership of that land is to be transferred to the Aboriginal Land Council.

This process is intended to provide compensation for the dispossession of land from Aboriginal people in NSW. It is a different process to the recognition of native title rights under Commonwealth law.

We examined whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. The relevant agencies are:

  • Department of Premier and Cabinet (DPC)
  • Department of Planning and Environment (DPE)
  • NSW Aboriginal Land Council (NSWALC).

We consulted with Local Aboriginal Land Councils (LALCs) and other Aboriginal community representative groups to hear about their experiences.

What we found

Neither DPC nor DPE have established the resources required for the NSW Government to deliver Aboriginal land claim processes in a coordinated way, and which transparently commits to the requirements and intent of the Act.

Delays in determining land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land. Delays also create risks due to uncertainty around the ownership, use and development of Crown land.

DPC has not established governance arrangements to ensure accountability for outcomes under the Act, and effective risk management.

DPE lacks clear performance measures for the timely and transparent delivery of its claim assessment functions. DPE also lacks a well-defined framework for prioritising assessments.

LALCs have concerns about delays, and lack of transparency in the process.

Reviews since at least 2014 have recommended actions to address numerous issues and improve outcomes, but limited progress has been made.

The database used by DPC (Office of the Registrar) for the statutory register of land claims has not been upgraded or fully validated since the 1990s.

In 2020, DPE identified the transfer of claimable Crown land to LALCs to enable economic and cultural outcomes as a strategic priority. DPE has some activities underway to do this, and to improve how it engages with Aboriginal Land Councils – but DPE still lacks a clear, resourced strategy to process over 38,000 undetermined claims within a reasonable time.

What we recommended

In summary:

  • DPC should lead strategic governance to oversee a resourced, coordinated program that is accountable for delivering Aboriginal land claim processes
  • DPE should implement a resourced, ten-year plan that increases the rate of claim processing, and includes an initial focus on land grants
  • DPE and DPC should jointly establish operational arrangements to deliver a coordinated interagency program for land claim processes
  • DPC should plan an interagency, land claim spatial information system, and the Office of the Registrar should remediate and upgrade the statutory land claims register
  • DPC and NSWALC should implement an education program (for state agencies and the local government sector) about the Act and its operations
  • DPE should implement a five-year workforce development strategy for its land claim assessment function
  • DPE should finalise updates to its land claim assessment procedures
  • DPE should enhance information sharing with Aboriginal Land Councils to inform their claim making
  • NSWALC should enhance information sharing and other supports to LALCs to inform their claim making and build capacity.

Fast facts

  • 53,800 the number of claims lodged since the Act was introduced in 1983
  • 38,200 the number of claims awaiting DPE assessment and determination (about 70 per cent of all claims lodged)
  • 207 the number of claims granted by DPE in six months to December 2021
  • 120 LALCs, and the NSWALC, have the right to make a claim and have it determined
  • +5 years around 60 per cent of claims have been awaiting determination for more than five years
  • 22 years the time it will take DPE to determine existing claims, based on current targets

The return of land under the Aboriginal Land Rights Act 1983 (NSW) (the Act) is intended to provide compensation for the dispossession of land from Aboriginal people in New South Wales. A claim on Crown land1 made by an Aboriginal Land Council that meets criteria under the Act is to be transferred to the claimant council as freehold title. The 2021 statutory review of the Act recognises the spiritual, social, cultural and economic importance of land to Aboriginal people.

The Minister for Aboriginal Affairs administers the Act, with support from Aboriginal Affairs NSW (AANSW) in the Department of Premier and Cabinet (DPC). AANSW also leads the delivery of Opportunity, Choice, Healing, Responsibility and Empowerment (OCHRE), the NSW Government's plan for Aboriginal affairs, and assists the Minister to implement the National Agreement on Closing the Gap – which includes a target for increasing the area of land covered by Aboriginal and Torres Strait Islander people's legal rights or interests.

The Act gives responsibility for registering land claims to an independent statutory officer, the Registrar of the Aboriginal Land Rights Act (the Registrar), whose functions are supported by the Office of the Registrar (ORALRA) which is resourced by AANSW.2

The Land and Environment Court of New South Wales has stated that there is an implied obligation for land claims to be determined within a reasonable time. The Minister administering the Crown Land Management Act 2016 (NSW) is responsible for determining land claims. This function is supported by the Department of Planning and Environment (DPE),3 whose staff assess and recommend claims for determination based on the criteria under section 36(1) of the Act. There is also a mechanism under the Act for land claims to be negotiated in good faith through an Aboriginal Land Agreement.

The NSW Aboriginal Land Council (NSWALC) is a statutory corporation constituted under the Act with a mandate to provide for the development of land rights for Aboriginal people in NSW, in conjunction with the network of 120 Local Aboriginal Land Councils (LALCs). LALCs are constituted over specific areas to represent Aboriginal communities across NSW. Both NSWALC and LALCs can make land claims.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities that are required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties need to be engaged so that these processes are coordinated effectively and managed in a way that is consistent with the intent of the Act, and other legislative requirements.

The first land claim was lodged in 1983. The number of undetermined land claims has increased over time, and at 31 December 2021 DPE data shows 38,257 undetermined claims.

The issue of undetermined land claims has been publicly reported by the Audit Office since 2007. Recommendations to agencies to better facilitate processes and improve how functions are administered have been made in multiple reviews, including two Parliamentary inquiries in 2016.

The objective of this audit was to assess whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. In making this assessment, we considered whether:

  • agencies (DPE, DPC (AANSW and ORALRA) and NSWALC) coordinate information and activities to effectively facilitate Aboriginal land claim processes
  • agencies (DPE and DPC (ORALRA)) are effectively administering their roles in the Aboriginal land claim process.

We consulted with LALCs to hear about their experiences and priorities with respect to Aboriginal land claim processes and related outcomes. We have aimed to incorporate their insights into our understanding of their expectations of government with respect to delivering requirements, facilitating processes, and identifying opportunities for improved outcomes. 

Conclusion

The Department of Premier and Cabinet (DPC) and the Department of Planning and Environment (DPE) are not effectively facilitating or administering Aboriginal land claim processes. Neither agency has established the resources required for the NSW Government to operate a coordinated program of activities to deliver land claim processes in a way that transparently commits to the requirements and intent of the Aboriginal Land Rights Act 1983 (NSW) (the Act). Arrangements to engage the NSW Aboriginal Land Council (NSWALC) in these activities have not been clearly defined.

There are more than 38,000 undetermined land claims that cover approximately 1.12 million hectares of Crown land. As such, DPE has not been meeting its statutory requirement to determine land claims nor its obligation to do so within a reasonable time. Over 60 per cent of these claims were lodged with the Registrar of the Aboriginal Land Rights Act, for DPE to determine, more than five years ago.

DPE’s Aboriginal Outcomes Strategy 2020–23 identifies transferring claimable Crown land to Local Aboriginal Land Councils (LALCs) as a priority to enable economic and cultural outcomes. Since mid-2020 DPE has largely focused on supporting LALCs to identify priority land claims for assessment and on negotiating Aboriginal Land Agreements. This work may support the compensatory intent of the Act but is in its early stages and is unlikely to increase the pace at which land claims are determined. Based on current targets, it will take DPE around 22 years to process existing undetermined land claims.

Delays in processing land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land in NSW. The intent of the Act to provide compensation to Aboriginal people for the dispossession of land has been significantly constrained over time.

Since 2014, numerous reviews have made recommendations to agencies to address systemic issues, improve processes, and enhance outcomes: but DPC and DPE have made limited progress with implementing these. Awareness of the intent and operations of the Act was often poor among staff from some State government agencies and local government representatives we interviewed for the audit.

DPC has not established culturally informed, interagency governance to effectively oversee Aboriginal land claim processes – and ensure accountability for outcomes consistent with the intent of the Act, informed by the expectations of the NSWALC and LALCs. Such governance has not existed since at least 2017 (the audited period) and we have not seen evidence earlier. DPE still does not have performance indicators for its land claim assessment function that are based on a clear analysis of resources, that demonstrate alignment to defined outcomes, and which are reported routinely to key stakeholders, including NSWALC and LALCs.

LALCs have raised strong concerns during our consultations, describing delays in the land claim process and the number of undetermined land claims as disrespectful. LALCs have also noted a lack of transparency in, and opportunity to engage with, Aboriginal land claim processes. DPE’s role in assessing Aboriginal land claims, and identifying opportunities for Aboriginal Land Agreements, requires specific expertise, evidence gathering and an understanding of the complex interaction between the Act and other legislative frameworks, including the Native Title Act 1993 (Cth) and the Crown Land Management Act 2016 (NSW). In mid-2020, DPE created an Aboriginal Land Strategy Directorate within its Crown lands division, increased staffing in land claim assessment functions, and set a target to increase the number of land claims to be granted in 2021–22. In the six months to December 2021, DPE granted more land claims (207 claims) than in most years prior. DPE has also assisted some LALCs to identify priority land claims for assessment.

But the overall number of claims processed per year remains well below the historical (five-year) average number of claims lodged (2,506 claims). As such, DPE has not yet established an appropriately resourced workforce to assess the large number of undetermined land claims and engage effectively with Aboriginal Land Councils and other parties in the process. There also are notable gaps in DPE’s procedures that impact the transparency of the process, especially with respect to timeframes and the prioritisation of land claims for assessment.

DPC (the Office of the Registrar of the Aboriginal Land Rights Act, ORALRA) has not secured or applied resources that would assist the Registrar to use discretionary powers, introduced in 2015, not to refer certain land claims to DPE for assessment (those not on Crown land). This could have improved the efficiency and coordination of end-to-end land claim processes.

DPC (ORALRA) is also not effectively managing data and ensuring the functionality of the statutory Register of Aboriginal land claims. This contributes to inefficient coordination with DPE and NSWALC, and creates a risk of inconsistent information sharing with LALCs, government agencies, local councils and other parties. More broadly, responsibilities for sharing information about the location and status of land under claim are not well defined across agencies. These factors contribute to risks to Crown land with an undetermined land claim, which case law has found to establish inchoate property rights for the claimant Aboriginal Land Council.4 It can also lead to uncertainty around the ownership, use and development of Crown land, with financial implications for various parties.


1 Crown land is land that is owned and managed by the NSW Government.
 AANSW and ORALRA were previously part of the Department of Education, before the 1 July 2019 Machinery of Government changes.
 Previously, these functions were undertaken by the Department of Industry (2017–June 2019) and the Department of Planning, Industry and Environment (July 2019 to December 2021). 
 The lodgement of a land claim creates an unformed property interest for the claimant Aboriginal Land Council over the claimed land. This interest will be realised if the Crown Lands Minister determines that the land is claimable.

Since 1983, 53,861 Aboriginal land claims have been lodged with the Registrar.25

The Land and Environment Court of New South Wales has stated there is an implied obligation on the Crown Lands Minister to determine land claims within a reasonable time.26

As at 31 December 2021, DPE has processed less than a third (31 per cent) of these land claims: 14,273 were determined by the Crown Lands Minister (that is, granted or refused, in whole or part) and 2,562 were withdrawn. This amounts to 16,835 claims processed, including the negotiated settlement of 15 claims through three Aboriginal Land Agreements. As a result, DPE reports that approximately 163,900 hectares of Crown land has been granted to Aboriginal Land Councils since 1983 up to 31 December 2021.

There are 38,257 land claims awaiting determination, which cover about 1.12 million hectares of Crown land.

The 2017 report on the statutory review of the Act noted that the land claims ‘backlog’ was one of the ‘Top 5’ priorities identified by LALCs during consultations. The importance of this issue is consistent with findings from our consultations with LALCs in 2021 (see Exhibit 7).

Exhibit 7: LALCs report that delays undermine the compensatory intent of the Act

LALCs raised concerns about delays in the Aboriginal land claim process, including waiting decades for claims to be assessed and years for land to be transferred once granted.

The large number of undetermined claims has been described by LALCs as disrespectful, and as reflecting under-resourcing by governments.

LALCs reported that these delays undermine the compensatory intent of the Act, including by creating uncertainty for their plans to support the social and economic aspirations of their communities.

Source: NSW Audit Office consultation with LALCs.

Delays in delivering on the statutory requirement to determine land claims, and limited use of other mechanisms to process claims in consultation or agreement with NSWALC and LALCs, undermines the beneficial and remedial intent of Aboriginal land rights under the Act. It also:

  • impacts negatively on DPE’s ability to comply with the statutory requirement to determine land claims, because often the older a claim becomes the more difficult it can be to gather the evidence required to assess it
  • creates uncertainty around the ownership, use and development of Crown land, which can have financial impacts on Aboriginal Land Councils, government agencies, local councils and developers.

Risks that arise in the context of undetermined claims are discussed further in section 3.3.


25 According to DPC (ORALRA) data in the ALC Register up to 31 December 2021. DPC (ORALRA) data indicates that the Registrar has refused to refer claims to DPE for assessment under section 36(4A) of the Act in a small number of cases – for example, seven times in 2017 and none since that time.
26 Jerrinja Local Aboriginal Land Council v Minister Administering the Crown Lands Act [2007] NSWLEC 577 at 125. The Court stated, ‘While a reasonable time may vary on a case-by-case basis, a delay of 15 to 20 years in determining claims does not accord with any idea of reasonableness’.

NSW Treasury describes public sector governance as providing strategic direction, ensuring objectives are achieved, and managing risks and the use of resources responsibly with accountability.

Consistent with the NSW Treasury’s Risk Management Toolkit (TPP-12-03b), governance arrangements for Aboriginal land claim processes should ensure their effective facilitation and administration. That is, arrangements are expected to contribute to and oversee the performance of administrative processes and service delivery towards outcomes, and ensure that legal and policy compliance obligations are met consistent with community expectations of accountability and transparency.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties (such as native title groups and those with an interest in development on Crown land) need to be engaged so that these processes are coordinated effectively with risks managed – consistent with the intent of the Act, and other legislative requirements.

Policy commitments to Aboriginal people and communities made by the NSW Government in the OCHRE Plan and Closing the Gap priority reforms establish an expectation for culturally informed governance.

Exhibit 12: LALCs want their voices to be heard and responded to by government

LALCs expressed a strong desire to have their voices heard so that outcomes in the Aboriginal land claim process are informed by LALC aspirations and consistent with the intent of the Act. The importance of respect and transparency were consistently raised.

The following quotes are from our consultations with LALCs during this audit which illustrate the inherent cultural value of land being returned, as well as the importance of its social and economic value and potential.

There’s batches of land in and around town. This land is significant…We want to get the land activated to encourage economic development, and promote the community…our job is to step up to create infrastructure, employment, maintenance and services and lead by example.

One of the best things we were able to do is develop a long term 20-year plan and where Crown Land could directly see where land was transferred to us and it was going to things like education, housing, health and other social programs…

There has been a claim lodged on a parcel of land that has long lasting cultural significance, a place that is very special to the Aboriginal community members and holds a lot of history. If the claim lodged was successful this land would be used to strengthen the cultural knowledge of the local youth, through placing signage that depicts stories that have been passed down by the Elders, cultural talks and tours and school group visits. This land, although not large in size, has a significant number of cultural trees and artefacts. Aboriginal families and members of the LALC that have lived in our town are very protective of the site and others surrounding it, respecting the importance of the cultural history of the site. There is one, which is a cultural one. We received a land claim that contained a cultural site. This is the high point: we were given back lands that contained rock engravings, carvings. A real diamond for us, especially as an urban based land council.

At the heart of the ALRA is the ability to claim Crown Land…The slow determination of claims gets in the way of us doing what we want to do, which is focus on our communities and address our real needs which are about health, wellbeing and culture. If we could realise these rights, we can address all sorts of socio-economic needs. We would become an economic benefit to the state…If it was operating well there could be more caring for Country too.

Note: Permission has been granted by LALC interviewees to use these quotes in this context.
Source: Excerpts from NSW Audit Office interviews with LALC representatives, facilitated by Indigenous consultants.

The Crown Lands Minister, supported by DPE, is required to determine whether Aboriginal land claims meet the criteria to be ‘claimable Crown lands’ under section 36(1) of the Act. DPE staff within its Crown Lands division are responsible for assessing land claims and preparing recommendation briefs to the Crown Lands Minister, or their delegate, on determination outcomes. That is, on whether to grant or refuse the claim.38 DPE staff also make decisions about which land claims within the large number of undetermined claims should be processed first.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Banner image used with permission.
Title: Forces of Nature
Artist: Lee Hampton – Koori Kicks Art
Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #365 - released 28 April 2022.

Published

Actions for Building regulation: combustible external cladding

Building regulation: combustible external cladding

Finance
Local Government
Planning
Compliance
Infrastructure
Regulation
Risk

What the report is about

The report focuses on how effectively the Department of Customer Service (DCS) and Department of Planning and Environment (DPE) led reforms addressing the unsafe use of combustible external cladding on existing residential and public buildings.

Nine local councils were included in the audit because they have responsibilities and powers needed to implement the NSW Government’s reforms.

What we found

After the June 2017 Grenfell Tower fire in London, the NSW Government committed to a ten-point action plan, which included establishing the NSW Cladding Taskforce, chaired by DCS, and with DPE as a key member. The Taskforce co-ordinates and oversees the implementation of the plan.

Depending on the original source of development approval, either individual local councils or DPE are responsible for ensuring that buildings are identified, assessed, and remediated. NSW Government-owned buildings are the responsibility of each department.

Identifying buildings potentially at risk was complex and resource intensive. However, on balance, it is likely that most affected buildings have now been identified.

By October 2021, around 40 per cent of assessed high-risk buildings that are the responsibility of local councils had either been remediated or found not to pose an unacceptable fire risk.

By February 2022, almost 50 per cent of affected NSW Government-owned buildings, and 90 per cent of buildings that are the responsibility of DPE, have either been cleared or are in the process of being remediated.

Earlier guidance on some key issues could have been provided by DCS and DPE in the two years after the Grenfell Tower fire. This may have reduced confusion and inconsistency across local councils we audited, and in some NSW Government departments. This especially relates to the application of the Fair Trading Commissioner's product use ban.

Given the inherent risks posed by combustible external cladding, buildings initially assessed as low-risk may also still warrant further action.

While most high-risk buildings have likely been identified, poor information handling makes it difficult to keep track of all buildings from identification, through to risk assessment and remediation.

What we recommended

DCS and DPE should:

  1. address the confusion surrounding the application of the Commissioner for Fair Trading's product use ban for aluminium composite panels with polyethylene content greater than 30 per cent
  2. develop an action plan to address buildings assessed as low-risk
  3. improve information systems to track all buildings from identification through to remediation.

Fast facts

Authority responsible for
ensuring that owners make
their buildings safe
Approximate number of
buildings referred for further
investigation*
Approximate percentage of
buildings remediated or
assessed to be safe
Local councils 1,200 40%
NSW Government owned 66 50%
DPE under delegation from
the Minister for Planning
137 90%
*After initial inspection by Fire and Rescue NSW, and/or preliminary inquiries by the consent authority, it was identified that the building may be at high-risk of
fire from combustible external cladding.

 

NSW Government's response to the risks posed by combustible external cladding

The NSW Government first became aware of the potential heightened risks posed by combustible external cladding on building exteriors after the 2014 Lacrosse Tower fire in Melbourne. However, it was the tragic loss of life from the Grenfell Tower fire in London, in June 2017, that gave added urgency to the need to address these risks.

Within six weeks of the London fire, the NSW Government committed to a ten-point plan of action for NSW to:

  • identify and remediate any buildings with combustible external cladding
  • ensure that regulation prevented the unsafe use of such cladding
  • ensure that experts involved in providing advice and certifying fire safety measures had the necessary skills and experience.

One of the actions in the ten-point plan was the creation of the NSW Government's Fire Safety and External Wall Cladding Taskforce (the Cladding Taskforce) chaired by the Department of Customer Service (DCS) and with the Department of Planning and Environment (DPE) as a key member.

The ten-point plan also specified that NSW Government departments would be responsible, in regard to buildings they owned to '…audit their buildings and determine if they have aluminium cladding'.

Local councils play a key role in implementing the Government's reforms, given their responsibilities and powers under the Environmental Planning and Assessment Act 1979 (EPA Act) and Local Government Act 1993 (Local Government Act) to approve building works (as 'consent authorities'), as well as to ensure fire safety standards are met. DPE plays an equivalent role for a smaller number of 'State Significant Developments' for which it is the consent authority under delegation from the Minister for Planning.

Commissioner for Fair Trading's building product use ban

On 18 December 2017, the Building Products (Safety) Act 2017 (BPS Act) came into effect in NSW, introducing new laws to prevent the use of unsafe building products. Notably, the BPS Act gave the Secretary of DCS and the Commissioner for Fair Trading the power to ban unsafe uses of building products.

After an extensive consultative process, the Commissioner for Fair Trading used these powers to issue a product use ban on 15 August 2018. This banned the use of external wall cladding of aluminium composite panels with a core comprised of more than 30 per cent polyethylene by mass on new buildings, unless the proposed use was subject to independent fire propagation testing of the specific product and method of application to a building in accordance with relevant Australian Standards.

Buildings occupied before the product use ban came into force are not automatically required to have the banned product removed. Under the BPS Act, consent authorities may determine necessary actions to eliminate or minimise the risk posed by the banned material on existing buildings.

Project Remediate

Project Remediate is a three-year NSW Government program announced in November 2020. The program was designed by the NSW Government to assist building owners of multi-storey apartments (two storeys or more) with high-risk combustible cladding to remediate their building to a high standard and for a fair price.

The scheme is voluntary and includes government paying for the interest on ten-year loans, as well as incorporating assurance and project management services to provide technical and practical support to owners’ corporations and strata managing agents. Building remediations under the program are expected to commence in 2022.

About this audit

This audit assessed whether DCS and DPE effectively led reforms to manage the fire safety risk of combustible external cladding on existing residential and public buildings.

In making this assessment, we considered whether the expressed policy intent of the NSW Government's ten-point plan for fire safety reform had been achieved by asking:

  • are the fire safety risks of combustible external cladding on existing buildings identified and remediated?
  • is there a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products on existing buildings?
  • is fire safety certification for combustible external cladding on existing buildings carried out impartially, ethically and in the public interest by qualified experts?

Consistent with the focus of the Cladding Taskforce on multi-storey residential buildings and public buildings, the scope of our audit is limited to buildings categorised under the Building Code of Australia (BCA) as class 2, 3 and 9. These classes are defined in detail in section 1.2, but include: multi-unit residential apartments, hotels, motels, hostels, back-packers, and buildings of a public nature, including health care buildings, schools, and aged care buildings. The scope was also limited to existing buildings, which is defined as buildings occupied by 22 October 2018.

Auditees

The Department of Customer Service chairs the NSW Government's Cladding Taskforce, which is responsible for coordinating the combustible external cladding reforms. The Commissioner of Fair Trading sits within DCS and DCS regulates the industry accreditation scheme for fire safety practitioners, as well as administering the BPS Act.

The Department of Planning and Environment administers the EPA Act and the Environmental Planning and Assessment Regulation 2000 (EPA Regulation), which regulate the building development process. As well as being the delegated consent authority for State Significant Developments, DPE is also responsible for maintaining the mandatory cladding register requiring building owners of multi-storey (BCA class 2, 3 or 9) buildings to register buildings with combustible external cladding on an online portal.

Functions and responsibilities between DCS and DPE varied over time. For example, in October 2019, the DPE building policy team responsible for co-ordinating the DPE response to the combustible cladding issue was transferred to DCS, following changes to agency responsibilities resulting from machinery of government changes. DPE advised this resulted in a lessening of DPE's subsequent policy work on combustible cladding and its involvement in the Cladding Taskforce.

While the focus of the audit was on the oversight and coordination provided by DCS and DPE, nine councils were also auditees for this performance audit. Councils play an essential part as consent authorities for building development approvals in NSW, as well as having responsibilities and powers to ensure fire safety standards. To fully understand how well their activities were overseen and coordinated, a sample of councils was included as auditees.

Nine councils were selected to represent both metropolitan and regional areas, noting that there are very few in-scope buildings in rural areas. The audited councils were:

  • Bayside Council
  • City of Canterbury Bankstown Council
  • Cumberland City Council
  • Liverpool City Council
  • City of Newcastle Council
  • City of Parramatta Council
  • City of Ryde Council
  • City of Sydney Council
  • Wollongong City Council.

Terminology

The two NSW Government department auditees have, over time, been subject to machinery of government changes, which have changed some of their functions and what the departments are called.

Relevant to this audit, the effect of these changes has been:

  • the Department of Finance, Services, and Innovation (DFSI) became the Department of Customer Services (DCS) on 1 July 2019
  • on 1 July 2019, the Department of Planning and Environment became the Department of Planning, Industry, and Environment (DPIE)
  • on 21 December 2021, DPIE became the Department of Planning and Environment (DPE).

To avoid confusion, we use the titles by which these departments are known at the date of this report: the Department of Customer Service and the Department of Planning and Environment.

Conclusion

At July 2017, immediately after the Grenfell Tower fire, there was no reliable source to identify buildings that may have had combustible external cladding. However, it is now likely that most high-risk buildings have been identified.

Following the 2014 Lacrosse Tower fire in Melbourne, the NSW Government recognised that there was a need to be able to identify buildings in NSW that could have combustible external cladding.

The process of identifying buildings that could have combustible external cladding has been complex, resource-intensive, and inefficient principally due to the lack of centralised and coordinated building records in NSW. In total, approximately 1,200 BCA class 2, 3 and 9 buildings have been brought to the attention of councils by either Fire and Rescue NSW (FRNSW), the Cladding Taskforce, or through councils' own inspection for possible further action. In addition, approximately 2,000 more buildings were inspected by FRNSW but not referred to local councils because they either had no combustible external cladding or had combustible external cladding not assessed as being high-risk.

A multi-pronged approach to identifying buildings has been used by the DCS and DPE, through the Cladding Taskforce. While it is impossible to know the full scope of potentially affected buildings, the approach appears thorough in having identified most relevant buildings.

The process of clearing buildings with combustible external cladding has been inconsistent.

In the more than four years since the NSW Government's ten-point plan was announced, around 40 per cent of the buildings brought to the attention of councils have been cleared by either rectification or being found not to pose an unacceptable fire risk. Also, around 50 per cent of NSW Government-owned buildings identified with combustible external cladding and almost 90 per cent of identified buildings for which DPE is consent authority have been cleared or remediation is underway.

While DCS and DPE did seek to work cooperatively with councils and provided high-level guidance on the NSW Government’s fire safety reforms, it took until September 2019 before a model process and other detailed advice was provided to councils to encourage consistent processes. DCS and DPE advice to councils and NSW Government-building owners should have been more timely on two key issues:

  • the use of experts in the process of assessing and remediating existing buildings, and
  • the implementation of the product use ban on aluminium composite panels with polyethylene content 30 per cent or greater.

Clarifying the application of the product use ban may require consent authorities and building owners to revisit how some buildings have been cleared.

The management of buildings assessed as low-risk by FRNSW, estimated to be over 500, has not been a priority of the Cladding Taskforce to date, despite those buildings potentially posing unacceptable fire risks.

Information management by the Cladding Taskforce is inadequate to provide a high-level of assurance that all known affected buildings have been given proper attention.

While most high-risk buildings have likely been identified, information management is not sufficiently robust to reliably track all buildings through the process from identification, through to risk assessment and, where necessary, remediation.

Reforms to certifier registration schemes are limited to new buildings and do not apply to the existing buildings covered by this audit.

While reforms are limited in application to new buildings, some consent authorities took steps to obtain greater assurance on the quality of the work done by fire safety experts regarding combustible external cladding on existing buildings. For example, by requiring fire safety experts to be appropriately qualified and requiring peer review of cladding risk assessments and proposed remediation plans.

 

This chapter considers the part played by DCS and DPE as key members of the Cladding Taskforce in ensuring that buildings with combustible external cladding were effectively identified and remediated through processes implemented by:

  • local councils or DPE, where those bodies were consent authorities under the EPA Act for the relevant buildings
  • in the case of NSW Government buildings, the departments that owned those buildings.

This chapter considers what has been done to deliver a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products.

 

This chapter considers whether reforms have ensured that only people with the necessary skills and experience are certifying buildings and signing off on fire-safety.

Inspections of existing buildings and development of any subsequent action plans to address combustible external cladding are not activities covered by accreditation or registration schemes for building certifiers

Almost all the risk assessment and remediation work done on buildings in the scope of this audit have been undertaken under fire safety orders issued by consent authorities using their powers under the EPA Act. This has been the recommended approach by DPE and DCS since at least 2016 (that is, before the Grenfell Tower fire in London).

While there have been reforms to certifier registrations scheme, these were not intended to ensure that combustible cladding-remediation on existing buildings is supported by people with the necessary skills and experience in fire safety under the fire safety order process. Instead, they are focused on offering better assurance for work done in respect to new building projects where accredited experts certify that building work is carried out in accordance with BCA under the DCS managed certifier registration schemes.

No steps have been taken to ensure the quality of the work done by experts inspecting, assessing the fire risk and developing action plans to address combustible external cladding on existing buildings, other than where consent authorities have chosen to exercise their discretion. This includes requiring fire safety experts to be appropriately qualified and requiring peer review of some cladding risk assessments and remediation plans.

Consent authorities determine whether individuals with accreditation are required for combustible cladding inspection, risk assessments and remediation on existing buildings

Whether an individual with certifier accreditation participates in a cladding inspection, risk assessment, or remediation for an existing building will be determined by what councils as consent authorities specify in their fire safety orders unless building owners opt to use such experts without being directed to do so by the consent authority.

As discussed earlier, councils acting as consent authorities vary in whether they require building owners to engage individuals with certifier accreditation. In most of the councils we audited, A1 or C10 accredited experts were either required, or recommended, to perform functions such as auditing suspected combustible cladding, or conducting fire safety risk assessments and developing plans to rectify combustible cladding.

However, these types of work are not functions covered by the accreditation or registration schemes that apply to building and development certifiers.

Certifier accreditation schemes do not cover cladding remediation work done under fire safety orders

While councils may require or recommend that independent accredited A1 or C10 certifiers be engaged by building owners for cladding risk assessment and remediation, they are not performing those functions as certifiers — they are, in effect, more akin to expert consultants. Accordingly, how they perform their functions and duties is not covered by the legislation supporting the accreditation scheme for certifiers that was operated until July 2020 by the Building Professional Board.

Instead, their use in this process is a convenient and practical way for consent authorities to ensure that building owners use appropriate experts who have the qualifications, skills and experience needed to investigate and identify combustible cladding, and then to formulate appropriate action to deal with such cladding. However, these individuals are not performing regulated or accredited work, are not subject to regulatory oversight, and are not accountable to any accreditation body for the quality of the work they perform.

While councils could (and sometimes do) choose to decline poor quality or incomplete cladding-related work prepared by A1 or C10 certifiers, the burden of resolving poor quality would fall on the building owner, who would have to seek amended or additional risk assessments or rectification plans.

In the absence of regulatory oversight, disincentives for poor quality cladding-related work, may include litigation being commenced by the property owner, harm to the expert's reputation in a small and competitive market, and the potential impact on whether the individual could retain their professional indemnity insurance at a reasonable cost (especially in an environment when many insurance providers withdrew coverage for cladding related work).

Reforms impact on regulated experts doing work on new buildings

The reforms that commenced on 1 July 2020, replaced categories of accreditation with classes of registration, and varied the classes such that:

  • accredited building surveyor category A1 became registered building surveyor-unrestricted
  • accredited certifier—fire safety engineer category C10 became registered certifiers-fire safety.

The legislation that introduced these reforms, the Building and Development Certifiers Act 2018, also repealed the pre-existing Building Professionals Act 2005 and abolished the Building Professionals Board. The new Act was accompanied by the Building and Development Certifiers Regulation 2020.

While the scope of this audit is limited to existing buildings, we note that there are buildings with combustible external cladding that are yet to be remediated. Just as these processes previously drew on the expertise of A1 and C10 category certifiers, it seems inevitable that the remediation of existing buildings will continue to draw on the expertise of the equivalent new classes of registered building surveyor-unrestricted and registered certifier-fire safety.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #364 - released 13 April 2022.

Published

Actions for Local government business and service continuity arrangements for natural disasters

Local government business and service continuity arrangements for natural disasters

Local Government
Internal controls and governance
Management and administration
Project management
Risk
Service delivery

What the report is about

Natural disaster events, including bushfires and floods, have directly impacted some local councils in New South Wales over recent years. It is important for local councils to effectively plan so that they can continue operations through natural disasters and other disruptions.

This audit assessed the effectiveness of Bega Valley Shire Council and Snowy Valleys Council’s approaches to business and service continuity arrangements for natural disasters.

What we found

Bega Valley Shire Council has a documented approach to planning for business and service continuity that provides for clear decision making processes and accountability.

Bega Valley Shire Council has prepared for identified natural disaster risks to business and service continuity but can do more to monitor how it has implemented controls responding to these risks.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires.

Bega Valley Shire Council can do more to ensure its business continuity management approach is regularly reviewed and updated, and that staff are regularly trained in its implementation.

Snowy Valleys Council did not have a finalised approach to ensure business and service continuity until October 2020. Now in place, this approach identifies governance, assigns roles and responsibilities, and includes procedures to retain or resume services. That said, the Council has not adequately documented key elements of its business continuity management approach.

Snowy Valleys Council's strategic risk register identifies that natural disasters may impact its ability to deliver services, but the Council has not identified controls to respond to these risks.

During the 2019–20 bushfires, in the absence of a business continuity plan, Snowy Valleys Council relied on the local knowledge of its staff to manage service continuity in line with directions from the Local Emergency Operations Controller and the combat agency (the Rural Fire Service).

Both councils advised that, during the 2019–20 bushfires, services were maintained, sometimes with adaptation and sometimes with support from other councils, NSW Government and Australian Government agencies.

What we recommended

Bega Valley Shire Council should update and regularly review its business continuity plans, provide business continuity training, and improve its monitoring of risk controls and actions, including for natural disaster impacts.

Snowy Valleys Council should document and monitor all disruption-related risks and controls, regularly review and update its business continuity plans, and progress planned actions to increase staff awareness of business continuity plans.

Across both councils, we recommended that recordkeeping relating to service delivery during natural disasters should be adequate to inform post incident reviews and future updates to business continuity.

Fast facts

  • Multiple natural disasters affected the audited councils in 2019–20:
    • bushfires in 2019–20
    • storms and floods in January 2020
    • storms and floods in July and August 2020
    • storms and floods in October 2020.
  • 6,279kmSize of Bega Valley Shire Council (area)
  • 2,203kmArea burnt within Bega Valley Shire Council in 2019–20 bushfires
  • 8,959kmSize of Snowy Valleys Council (area)
  • 3,339kmArea burnt within Snowy Valleys Council in 2019–20 bushfires.

Natural disaster events, including bushfires and floods, have directly impacted some local councils in New South Wales over recent years. Given their important role in delivering essential services to their communities, it is important for local councils to effectively plan so that they can continue operations through natural disasters and other disruptions.

Business continuity plans are a widespread mechanism used by governments and private sector organisations to ensure they are prepared to respond effectively to disruptions. In New South Wales, business continuity plans are widely used by local councils to help ensure continuity of service delivery, safety and availability of staff, availability of information technology systems and other systems, financial management and governance. There are no current sector-wide requirements or policies for business continuity management issued by the Department of Planning and Environment (DPE)1 for NSW councils. As such, councils can develop their own business continuity management frameworks.

Our 'Report on Local Government 2020' considered the financial and governance impacts from recent natural disaster events on local councils in New South Wales. It also considered sector-wide trends in business continuity planning, including how many councils enacted or updated their business continuity plans in 2019–20.

The report found that all councils were impacted by emergency events, and that some councils changed their governance, policies, systems, and processes to respond to the emergency events. Sixty-five per cent of councils updated their business continuity plan as a response to recent emergency events, and 43 per cent of councils updated their disaster recovery plan.

This audit follows on from the 'Report on Local Government 2020' with a detailed examination of the effectiveness of business and service continuity arrangements for natural disasters in two councils.

The selected councils for this audit were Bega Valley Shire Council and Snowy Valleys Council. They were selected because they had been heavily impacted by the 2019–20 bushfires and other natural disaster events, such as storms and floods between December 2018 to December 2020.

The objective of this performance audit was to assess the effectiveness of the councils' approaches to business and service continuity arrangements for natural disasters. In making this assessment, we considered whether the selected councils:

  • had documented approaches for identifying, mitigating, and responding to disaster-related risks to business and service continuity
  • effectively implemented strategies to prepare for identified disaster-related impacts
  • responses during selected disasters were effective in managing business and service continuity.

Conclusion - Bega Valley Shire Council

Bega Valley Shire Council has a documented approach to planning for business and service continuity that provides for clear decision-making processes and accountability.

Since 2018, the council has prepared for identified natural disaster risks to business and service continuity, but can do more to monitor how it has implemented controls responding to these risks.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires.

The council can do more to ensure its business continuity management approach is regularly reviewed and updated, and that staff are regularly trained in its implementation.

Bega Valley Shire Council has a documented approach to business continuity management that is integrated with its broader approach to enterprise risk management and is supported by clear decision-making processes and accountability. This includes a business continuity plan (BCP), BCP subplans, and a business impact analysis (BIA). The council made changes to its BIA in 2019 following the 2018 Tathra bushfires within its local government area (LGA), but its BCP and BCP subplans have not been updated since 2016 and key information is out of date.

Bega Valley Shire Council has identified high-level controls and strategies to mitigate disaster-related risks and undertakes post incident reviews to capture lessons following a disaster, but many high-risk actions resulting from those reviews remain outstanding.

Bega Valley Shire Council identified risks, controls, and actions to prepare for natural disaster impacts between 2018 to 2020. However, the council has not effectively monitored implementation of the identified controls. Bega Valley Shire Council has only partially implemented the actions and recommendations from internal reviews that identified gaps in its business continuity management approach.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires, instead relying on the local knowledge of its staff. The council has not provided BCP scenario training since 2015 and has not monitored completion rates of its online business continuity management training for staff.

Bega Valley Shire Council did not keep records of its decision of whether to enact its BCP during the 2019–20 bushfires, but advised its ability to follow the BCP was not possible due to the scale and impact of the bushfires surpassing the expectations included in its BCP and BCP subplans.

The council advised that essential council-led services were largely maintained during the disaster, sometimes with adaptation of services, and sometimes with support from other councils, NSW Government and Australian Government agencies.

As Bega Valley Shire Council did not maintain formal records of service disruptions for most services, did not follow all aspects of its BCP during the 2019–20 bushfires, and because it requested and received support from other agencies, we are unable to assess the impact of its planning and preparation activities on the continuity of services.

Bega Valley Shire Council took actions during the 2019–20 bushfires to communicate key service changes to staff, residents, and stakeholders, and regularly sought feedback on residents' experiences.

Bega Valley Shire Council could improve the effectiveness of its business continuity management approach by undertaking regular staff training (including scenario training) and ensuring that its business continuity management framework is routinely updated to reflect current practice and current staff. 

 

Conclusion - Snowy Valleys Council

Snowy Valleys Council did not have a finalised approach to ensure business and service continuity until October 2020. Now in place, this approach identifies governance, assigns roles and responsibilities and includes procedures to retain or resume services. That said, the council has not adequately documented key elements of its business continuity management approach.

Snowy Valleys Council's risk register identifies that natural disasters may impact its ability to deliver services, but the council has not identified controls to respond to these risks.

During the 2019–20 bushfires, in the absence of a business continuity plan (BCP) or BCP subplans, the council relied on the local knowledge of its staff to manage service continuity in line with directions from the Local Emergency Operations Controller and the combat agency (the Rural Fire Service).

Snowy Valleys Council did not have a finalised BCP, BCP subplans, or BIA until after the 2019–20 bushfires. The council finalised most of its business continuity management framework in late 2020 and this framework now establishes governance, including assigning roles and responsibilities, and identifies contingencies and procedures to retain or resume critical services.

There are gaps in how Snowy Valleys Council has documented key elements of its business continuity management approach. The council advised it has completed a BIA, but has not retained the completed version of this document as it was not managed under Snowy Valleys Council's record management procedures. Some of the council's BCP subplans have gaps in process information and contact details which means BCP subplan owners and other potential users may not have access to accurate, up to date information when responding to a disruption event.

The council advised it provided BCP scenario training in 2016, 2018, and 2021, but was unable to provide any evidence of the 2018 training. As the current BCP and BCP subplans were only finalised in 2021, the 2016 and 2018 training were based on the previous BCP framework, developed under the former Tumut Shire Council. Additionally, the council advised it has developed BCP awareness training for staff as part of induction training, but has not provided a clear timeframe for implementing this training.

The council undertakes post incident reviews after most service disruption events, but has not undertaken a post incident review of the 2019–20 bushfires, despite its significant impact within the Snowy Valleys Council LGA.

Snowy Valleys Council advised that it identifies and mitigates or controls for disaster related risks within broader enterprise-wide risk assessments. Snowy Valleys Council’s strategic risk register identifies the risk of natural disasters to service delivery, but does not identify preventative controls or resilience strategies to mitigate these risks. The council monitors and improves the resilience of some assets as part of its regular operations of maintaining assets but does not clearly link such actions to how they contribute to reducing the risk of natural disaster related impacts. Snowy Valleys Council advises it works with other agencies, such as the Rural Fire Service and the local Bush Fire Management Committee, to plan for bushfire risks.

In the absence of a BCP or BCP subplans, Snowy Valleys Council relied on individual team members to manage service continuity during the 2019–20 bushfires based on directions by the local Emergency Operations Controller, and the Rural Fire Service. The council advised that the delivery of essential council-led services was largely maintained during the 2019–20 bushfires, sometimes with adaptation and support from other NSW Government and Australian Government agencies. Snowy Valleys Council took actions during the 2019–20 bushfires to communicate key service changes to staff, residents, and stakeholders, and regularly sought feedback on residents' experiences.

As Snowy Valleys Council did not maintain formal records of any service disruptions and did not have a finalised business continuity management approach in place to guide its response during the 2019–20 bushfires, we are unable to assess the impact of its planning and preparation activities on the continuity of services.

 

 1 At the time of this audit, the Department of Planning and Environment is responsible for supporting and regulating local councils in New South Wales through the Office of Local Government. Prior to 21 December 2021, the Department of Planning and Environment was named the Department of Planning, Industry and Environment.

Appendix one – Responses from councils and the Department of Planning and Environment 

Appendix two – Emergency management arrangements for local councils 

Appendix three – About the audit 

Appendix four – Performance auditing 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #362 - released 17 February 2022.

Published

Actions for Integrity of grant program administration

Integrity of grant program administration

Local Government
Premier and Cabinet
Internal controls and governance
Management and administration

What the report is about

This report assessed the integrity of the assessment and approval processes for two grant programs:

  • Stronger Communities Fund Round 2 (tied grants round), which was administered by the former Office of Local Government (OLG) and provided $252 million to newly amalgamated councils and other councils that had been subject to a merger proposal during 2017–18 and 2018–19.
  • Regional Cultural Fund, which was administered by Create NSW (now within the Department of Premier and Cabinet) and awarded $100 million for cultural projects in regional NSW.

What we found

The assessment and approval process for Round 2 of the Stronger Communities Fund lacked integrity. The government decided to prioritise funds for councils that had worked constructively with the government through the 2016 merger process. 

However, this information was not included in the program guidelines. The program guidelines were not published and did not contain details of selection and assessment processes. Councils and projects were instead identified by the former Premier, Deputy Premier and Minister for Local Government and communicated to OLG with little or no information about the basis for the council or project selection. There was no merit assessment of identified projects. This process resulted in 96 per cent of funds allocated to coalition state seats.

The assessment process that Create NSW used for the Regional Cultural Fund was robust and produced transparent and defensible recommendations to the minister. However, the former Minister for the Arts, in consultation with the former Deputy Premier, did not follow the recommendations of the independent assessment panel in 22 per cent of cases. Reasons for these changes were not documented by Create NSW.

What we recommended

The Department of Premier and Cabinet should develop a model for grant administration that must be used for all grant programs administered in NSW that:

  • is based on ethical principles such as impartiality, equity and transparency 
  • ensures assessments and decisions can be made against clear eligibility criteria
  • ensures accountability for decisions and actions of all those who are involved in the program 
  • includes minimum mandatory administration and documentation standards
  • requires any ministerial override of recommendations to be documented. 

The Department of Planning and Environment should ensure that guidelines prepared for all grant programs are published and include a governance framework that includes accountabilities and key assessment steps.

Fast facts    

Stronger Communities Fund Round 2

  • $252m allocated to 24 councils    
  • 96% allocated to council projects in coalition state seats
  • 36% of the funding ($90m) was allocated to a single council
  • $8m in projects identified before the program guidelines were finalised

Regional Cultural Fund

  • 405 applications received across three funding rounds
  • $99m awarded for 147 cultural projects in regional NSW 
  • 22% panel recommendations not followed by ministers  
  • $9.3m awarded to projects not recommended by panel

Grants are frequently used by the state government to deliver funds to councils and community organisations to provide infrastructure and services important to their local communities. Grant programs are administered by NSW Government agencies in line with priorities and objectives set by the government.

Guidance for agencies administering grant programs is available in the Good Practice Guide to Grants Administration (the 'DPC Guide') which is maintained by the Department of Premier and Cabinet (DPC). In addition to this guide, some agencies maintain their own grant program policies and guidelines. More broadly, public servants are required to comply with financial legislation and the Government Sector Employment Act 2013 which include requirements to be transparent, fiscally responsible and focus on the efficient, effective and prudent use of resources.

The objective of this performance audit is to assess the integrity of the assessment and approval processes for NSW Government grant programs.

The audit focuses on two grant programs, both administered during the 2017–18 and 2018–19 financial years. The Stronger Communities Fund (round two tied grants round) was administered by the former Office of Local Government (OLG), now referred to as the Local Government Group within the Department of Planning and Environment (DPE). The fund awarded $252 million to 24 councils that had amalgamated in 2016 or which had been the subject of a merger proposal. The Regional Cultural Fund was administered by Create NSW, now within the Department of Premier and Cabinet (DPC). The fund awarded $100 million to organisations in regional New South Wales to support the development of cultural infrastructure in regional areas.

The audit comments upon the role played by the then Premier, Deputy Premier, ministers and their staff in the audited grant programs to provide context. The Audit Office of NSW cannot compel those individuals to participate in the audit or provide documents. In all cases, reference to the Premier, Deputy Premier, ministers, MPs and their staff refers to the individuals who were in those roles at the time the grant programs were administered unless otherwise noted.

Conclusion

Stronger Communities Fund

The assessment and approval processes for round two of the Stronger Communities Fund (SCF) lacked integrity. The program guidelines developed by the Office of Local Government (OLG) were deficient in a number of aspects and were not used to guide the selection of councils or projects for funding. Of the 55 councils that met the eligibility criteria in the guidelines, 24 received funding. Ninety-six per cent of available SCF funding was allocated to projects in coalition-held state government electorates. Funding for councils was determined by the then Premier, Deputy Premier and Minister for Local Government and communicated by their staff through emails to OLG with little or no information about the basis for the council or project selection. OLG administered payment of these funds without questioning or recording the basis for selection. For the 22 councils where funding allocations were determined by the former Premier and Deputy Premier, the only record of their approval is a series of emails from their staff. The exclusion of key information from the program guidelines and the lack of formality in approving 22 of the 24 funding allocations prevent accountability and transparency over the government's approach to selecting councils for funding.

In July 2017, the NSW Government established priorities for how the remaining SCF funds should be used. The funds were to be used to cover costs associated with councils' legal action relating to amalgamation, to reimburse costs incurred by councils that were unable to merge but had participated constructively in the merger process, and to fund community initiatives in council areas that had amalgamated in 2016.

OLG developed the initial grant program guidelines between July 2017 and September 2017 in consultation with the then Premier, Deputy Premier and Minister for Local Government and their staff. These were then revised in June 2018. Neither version of the guidelines made reference to the type of projects that were to be prioritised and did not set out how the funds should be administered in accordance with these priorities. The guidelines also did not include information about how councils and projects would be selected and made no provision for an assessment of identified projects against the criteria for eligible projects in the guidelines. OLG did not publish the guidelines and the process adopted by the Premier, Deputy Premier and Minister for Local Government to select projects did not reference the criteria for eligible projects in the guidelines. The selection of councils and funded projects resulted in 96 per cent of available funding being allocated to projects in coalition-held state government electorates.

The Minister for Local Government was responsible for distributing the SCF funds but only approved funding for projects at two of 24 councils, both paid in November 2017. Projects at the other 22 councils were identified by the former Premier and Deputy Premier between June 2018 and June 2019 in consultation with other coalition Members of Parliament and communicated to OLG through emails from Premier and Deputy Premier's staff. When making payments in response to email instructions from staff in the offices of the Premier, Deputy Premier and Minister for Local Government, OLG did not seek to ensure that identified projects were consistent with the guidelines and made payments to selected councils with little or no information to justify them. With the exception of the two funding allocations approved by the then Minister for Local Government, OLG also did not ensure that formal records were in place to document approval for the remaining 22 funding allocations.

Regional Cultural Fund

The assessment process that Create NSW used for the Regional Cultural Fund was robust and produced transparent and defensible recommendations to the then Minister for the Arts. However, the integrity of the approval process for funding allocations was compromised because the minister, in consultation with the then Deputy Premier, did not follow the recommendations of the independent assessment panel in multiple cases and the reasons for making changes were not documented by the minister's office or Create NSW.

All projects that received funding were assessed by Create NSW as eligible for funding under the program. An independent assessment panel assessed applications against the program objective and criteria. This process was designed in line with good practice in grants administration and was implemented consistently. The then Minister for the Arts, in consultation with the former Deputy Premier, did not follow the panel's recommendations for 22 per cent, or more than one in five, of the applications assessed for funding. Thirty-four applications that were recommended by the independent panel did not receive any funding. In the second funding round, seven of the top ten ranked applications were not funded.

The Minister for the Arts approved funding for 22 applications that were not recommended by the independent panel. This resulted in around $9.3 million being awarded to applicants that were not rated highest by the independent panel, including six applicants that received grants of $500,000 or more. Most did not meet one or more assessment criteria and received low ratings.

The then minister did not provide reasons for not approving funding in line with the recommendations of the panel. This did not breach any legislation or guidelines in New South Wales, but it compromised Create NSW's ability to demonstrate integrity and value for money in the RCF approval process. It creates a clear perception that factors other than the merits of the projects influenced funding decisions.

Create NSW's administration of the Regional Cultural Fund was based on relevant legislative requirements and good practice guidance. The objectives of the program were defined clearly and the guidelines and criteria were consistent with the program objectives. The governance and probity framework was appropriate for the size and nature of the program.

Appendix one – Response from agencies

Appendix two – List of funded projects - Stronger Communities Fund Round 2

Appendix three – List of funded projects - Regional Cultural Fund

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #361 - released 8 February 2022.