Search filters applied: local government, premier and cabinet, transport AND 2020, 2006, 1997 AND asset valuation, infrastructure .

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW. The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal p

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years.  Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contribut

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits. The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public. The Auditor-General reports that the total cost of the pr

Published

Actions for Report on Local Government 2019

Report on Local Government 2019

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

I am pleased to present my third report to the Parliament on the 2019 audits of local government councils in New South Wales. This report notes that unqualified audit opinions were issued on the 2018–19 financial statements of 134 councils and 11 joint organisations. The opinion for one council was disclaimed and three audits are yet to complete. The report also highlights improvements I have seen in financial reporting and governance arrangements acro

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.  Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferre

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an

Published

Actions for Lease to Fox Studios Australia

Lease to Fox Studios Australia

Premier and Cabinet
Asset valuation
Infrastructure
Management and administration
Procurement
Project management

The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare sit

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the c

In progress

Actions for WestConnex: Changes since 2014

WestConnex: Changes since 2014

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether Transport for NSW and Infrastructure NSW effectively assessed and justified major scope changes to the WestConnex project since December

Planned

Actions for Road and rail freight strategy

Road and rail freight strategy

Transport
Asset valuation
Infrastructure
Management and administration
Procurement
Project management
Service delivery

Freight is a critical component of the New South Wales economy. It is currently estimated to be worth nearly $66.0 billion a year to the economy. The economic growth and prosperity of New South Wales depends on the safe, efficient and reliable movement of goods. The NSW Government Future Transport 2056 strategy estimates that by 2056, 12 million people will live in New South Wales, and freight volumes will double in the Greater Sydney area and increase b