Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #336 - released 23 June 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Report on Local Government 2019

Report on Local Government 2019

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

I am pleased to present my third report to the Parliament on the 2019 audits of local government councils in New South Wales.

This report notes that unqualified audit opinions were issued on the 2018–19 financial statements of 134 councils and 11 joint organisations. The opinion for one council was disclaimed and three audits are yet to complete.

The report also highlights improvements I have seen in financial reporting and governance arrangements across councils. Fewer errors were identified. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices, including fraud control systems, have also improved.

These are very pleasing indicators of the gradual strengthening of governance and financial oversight of the sector. I want to acknowledge the investment councils have made in working with the Audit Office to improve consistency of practice and accountability generally.

Of course there is more work to do, particularly to prepare for new accounting standards and to strengthen controls over information technology and cyber security management. Asset management practices can also be improved. This report provides some guidance to council on these matters and we will continue to partner with the Office of Local Government in the Department of Planning, Industry and Environment to support good practice.

Margaret Crawford

Auditor-General
5 March 2020

This report focuses on key observations and findings from the 2018–19 financial audits of councils and joint organisations.

Unqualified audit opinions were issued on the financial statements for 134 councils and 11 joint organisations. The audit opinion for Bayside’s 2017–18 and 2018–19 financial statements were disclaimed. Three audits are still in progress and will be included in next year’s report.

The report highlights a number of areas where there has been improvement. There was a reduction in errors identified in council financial statements and high risk issues reported in audit management letters. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices and fraud control systems have also improved.

The report also found that councils could do more to be better prepared for the new accounting standards, asset management practices could be strengthened, and information technology controls and cyber security management could be improved.

The Auditor-General recommended that the Office of Local Government within the Department of Planning, Industry and Environment develop a cyber security policy by 30 June 2021 to ensure a consistent response to cyber security risks across councils.

Read the PDF Report

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision making is enhanced when financial reporting is accurate and timely. Strong financial performance provides the platform for councils to deliver services and respond to community needs.

This chapter outlines our audit observations on the financial reporting and performance of councils and joint organisations.

Section highlights
  • There was a reduction in the number and dollar value of errors identified in councils' financial statements.
  • We continue to identify prior period errors, which are predominantly asset-related.
  • Unqualified audit opinions were issued for 99 per cent of completed audits for councils and joint organisations.
  • Three audits remain outstanding, with the outcomes to be reported in next year's Report to Parliament.
  • Seventy-nine per cent of councils and joint organisations lodged their financial reports by 31 October 2019.
  • Councils that performed some early reporting procedures achieved better outcomes in terms of the quality and timeliness of financial reporting.
  • Councils are at various levels of preparedness to implement the new accounting standards for the 2019–20 financial year. Some have made the necessary modifications to systems and processes, but others are still assessing impacts.
  • Most councils met the prescribed benchmarks for the liquidity and working capital performance measures over the past three years.
  • More councils reported negative operating performance compared with the prior year, meaning their operating expenditure exceeded their operating revenue.

Strong governance systems and internal controls help councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations and support ethical government.

This chapter outlines the overall trends related to governance and internal control issues across councils and joint organisations for 2018–19.

Section highlights
  • While the total number of issues reported in our management letters increased compared with the prior year, the total number of high risk issues have decreased. Of the high-risk issues, 41 per cent were deficiencies in information technology controls.
  • More councils have established audit, risk and improvement committees and internal audit functions.
  • Councils have improved risk management practices, with over 75 per cent of councils now having a risk management policy and register.
  • While most councils have policies and processes to manage gifts and benefits, we identified some instances of non-compliance with the Model Code of Conduct.
  • Most councils have policies and processes to manage the use of credit cards.
  • Councils can strengthen policies and practices for managing fraud controls and legislative compliance.
  • There are further opportunities for councils to improve internal controls over revenue, purchasing, payroll, cash, financial accounting and governance processes.

Councils rely on information technology (IT) to deliver services and manage information. While IT delivers considerable benefits, it also presents risks that council needs to address.

In prior years, we reported that councils need to improve IT governance and controls to manage key financial systems. This chapter outlines the progress made by councils in the management of key IT risks and controls, with an added focus on cyber security.

Section highlights
  • We continue to report deficiencies in information technology controls, particularly around user access management. These controls are key to ensuring IT systems are protected from inappropriate access and misuse.
  • Many councils do not have IT policies and procedures and others do not identify, monitor or report on IT risks.
  • Cyber security management requires improvement, with some basic elements of governance not yet in place for many councils.

Councils are responsible for managing a significant range of assets to deliver services on behalf of the community.

This chapter outlines our asset management observations across councils and joint organisations.

Section highlights
  • There was an increase in the total number of issues reported in our management letters for asset management processes.
  • There were less high-risk issues reported compared to the previous year.
  • We continue to identify discrepancies between the council's Crown land asset records and the Crown Land Information Database (CLID) managed by the former Department of Industry (DOI).
  • Inconsistent practices remain across the Local Government sector in accounting for landfill sites.

Appendix one – Response from the Office of Local Government within the Department of Planning, Industry and Environment

Appendix two – Status of 2018 recommendations

Appendix three – Status of audits 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Sydney Road Maintenance Contracts

Sydney Road Maintenance Contracts

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.

RMS’ SMC contract management includes most elements of good practice, including governance and dispute resolution mechanisms. However, key elements are missing which reduces its effectiveness.

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. RMS divides the network into three geographical areas: south, west and north zones.

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. Prior to November 2013, RMS maintained roads in the south and west zones through its Road and Fleet Services unit. 

In November 2013, RMS outsourced road maintenance services for the south and west zones using Stewardship Maintenance Contracts (SMC). The contracts run for seven years with an option for a further three years at RMS’ discretion. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

The SMC model adopted stewardship principles to improve value for money. RMS defined stewardship principles as a broad set of values, attitudes and behaviours, required of the contractor to effectively manage the assets on behalf of RMS. The SMC also includes commercial principles, such as linking risk to reward, and a performance framework where outcomes drive performance.

This audit assessed whether RMS had effectively managed the outsourcing of road maintenance in the Sydney region south and west zones. In making this assessment, we answered the following questions:

  1. Did RMS justify the decision to adopt the SMC model?
  2. Do SMCs include key performance indicators (KPIs) and incentives which promote efficiency and effectiveness? 
  3. Does RMS collect high quality information on contractor performance and take action to correct performance deficiencies?
  4. Are the expected benefits being achieved?

Conclusion

RMS developed an innovative contracting approach with the SMC. RMS has realised some benefits in the first year, including savings, from outsourcing road maintenance in the Sydney region south and west zones using the SMC. However, RMS’ management of the SMC has key elements missing which reduces its effectiveness.

The SMC includes performance measures and incentives to drive efficiency and effectiveness improvements over time.  

RMS has established a contract management framework which includes most elements of good practice, including governance and dispute resolution mechanisms. However, it does not have procedures to guide its contract managers in managing specific provisions of the SMC. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractor account for an efficiency dividend in its pricing at the start of each three-year works period. It also has not done enough to assure itself that the contractor provided performance and financial data are correct. This is important because the data is used to measure performance and calculate contractor payments.  

RMS assessed that it had achieved around 80 per cent of the expected cost benefit in the initial year of the SMC. However, it has not tracked its achievement of benefits since then.

The Stewardship Maintenance Contract

RMS justified adopting the SMC model and included KPIs to drive efficiency and effectiveness

The SMC model includes features that RMS had not previously used for road maintenance contracts. These included adopting stewardship principles and transferring price risk to the contractor over time as the contractor becomes familiar with the assets being maintained.

The SMC model meets RMS’ requirements for flexibility in pricing models, the need for collaboration in asset maintenance planning, promoting innovation and effective performance management.

RMS used many good practices to develop the SMC model, including:

  • preparing a robust business case comparing the SMC model to RMS maintaining the road network itself, as well as assessing whether two other contracting models
    (traditional and alliance) would meet its requirements
  • assessing experiences with similar arrangements in other jurisdictions and identifying elements that worked to get the best outcomes
  • developing a robust performance framework, which included a mix of efficiency and effectiveness KPIs that reflected NSW Government policy and RMS priorities
  • incorporating risk and reward incentives delivered through cost sharing arrangements which change as the contract matures
  • using a contract duration that supports RMS priorities and provides an incentive for better quality outcomes.

RMS uses data provided by the contractor to measure performance and calculate payments to the contractor. The SMC includes a specific sanction if RMS finds that the contractor provided incorrect performance data, but no specific sanction if the contractor provides incorrect financial data. If RMS finds that the contactor provided incorrect performance or financial data, RMS can only recover over-payments which may have been made using the incorrect data.  

To provide a stronger incentive for the contractor to ensure data it provides is accurate, RMS should consider whether to incorporate stronger sanctions when negotiating the commercial reset due in mid-2018 for south and west zones. RMS should also consider this for the new contract for the north zone when the current PSMC contract expires in October 2018.

RMS' contract management approach and benefits realization

RMS can improve the effectiveness of its oversight and management of the SMC

RMS does not have SMC specific contract procedures to guide its contract managers. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractors account for an efficiency dividend in their pricing at the start of each three-year works period. Effective contract management should be supported by contract specific procedures, with explanations of, and allocation of responsibility for, the various interventions that RMS may be required to exercise in the SMC.

Performance and financial reporting under the SMC is based on a mix of RMS and contractor provided data. While there are a range of audits of contractor provided performance and financial data that RMS can conduct each year under the SMC, it does not have a schedule of audits it will conduct and when.  
During the first year of the SMC, RMS commissioned some limited audits of financial data. In the first three years of the SMC, RMS did not conduct any audits of performance data. Had there been SMC specific procedures in place, this would have reduced the risk of RMS not implementing a systematic audit program to give it reasonable assurance on the quality of the data that the contractor has provided. This is important because the data is used to measure performance and calculate contractor payments.

RMS has been aware of data quality issues since 2015. While RMS advised that it commenced addressing some data quality issues in response to a series of reviews conducted in 2015, a recent internal audit report indicates that RMS has not resolved the data quality issues.  

RMS achieved benefits in the first year, but has not tracked benefits since

As part of the business case, RMS agreed to implement a benefits realisation strategy, including a benefits tracking tool. RMS commenced tracking benefits, but did not establish a comparative baseline pre-SMC on non-financial benefits, and has not tracked benefits past year one.

In 2015, a benchmarking study commissioned by RMS found that it had achieved 80 per cent of the expected recurrent cost savings and other benefits, such as improved workplace safety, in the first full year of the SMC. However, there was no clear baseline to measure
non-financial performance. The study was qualified due to gaps in available data. The study also did not reconcile the actual one-off transition costs to the business case estimate.

During the course of the audit, RMS advised that it intends to repeat this type of study to determine whether it has achieved all expected benefits (and their value), and that it would use the results to inform its negotiation with the SMC contractors as part of the commercial reset due in mid-2018.

Roads and Maritime Services is responsible for the State Roads network in the Sydney region

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network. This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. The network is divided into three geographical areas: south, west and north zones. Prior to November 2013, RMS maintained roads in the Sydney region south and west zones through its Road and Fleet Services unit.  

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. This contract is worth around $35 million per annum.  

NSW Government priorities and road maintenance

Efficient and effective road maintenance contributes to the following NSW Government priorities:

  • improving road travel reliability
  • ensuring on-time running of public transport
  • reducing road fatalities
  • improving government services
  • keeping our environment clean.

The NSW Commission of Audit recommended outsourcing the maintenance of State roads

The NSW Commission of Audit in its Final Report on Government Expenditure (May 2012) recommended contestability as an appropriate strategy to consider for improving road maintenance service delivery for State roads.  

The Commission benchmarked RMS’ road surface quality and cost per lane kilometre against those of Western Australia, Victoria, and Queensland. This showed that New South Wales lagged the other states on both these measures.  

Exhibit 1: Interjurisdictional comparison of road maintenance outcomes 2009–10
  WA VIC QLD NSW
Roads managed (lane kms) 52,659 50,510 71,353 80,348
Estimated spend ($/lane km) 5,000 4,500 6,000 7,000
Road quality measure (%) 99 99 94 91

Source: NSW Commission of Audit Final Report May 2012.

The Commission noted that RMS had conducted two independent reviews to examine the potential for extending road maintenance contestability. The Commission found that there was inadequate and inconclusive benchmarking to establish the efficiency of RMS’ Road and Fleet Services unit when compared to outsourcing. It recommended that RMS bring forward a proposal to conduct a competitive tender for the road maintenance of the Sydney region south zone road network to inform the feasibility of a progressive rollout of road maintenance contestability across other areas of the State. In August 2012, the NSW Government adopted the Commission’s recommendation.

The NSW Government introduced road maintenance contestability through Stewardship Maintenance Contracts

In April 2013, the NSW Government announced that it would introduce road maintenance contestability across the Sydney region, using a Stewardship Maintenance Contract (SMC) model to improve value for money. In doing so, it excluded RMS’ Road and Fleet Services unit from tendering.  

The SMC model is based on the following key commercial and performance principles set by RMS:

  • performance driven by outcomes
  • flexible and adaptable
  • transparent and measurable
  • linking risk to reward
  • continuous improvement
  • criteria for selection of, and transition to, different payment models.

The following key stewardship principles underpin the SMC’s broad set of values, attitudes and behaviours, which are required of the contractor to effectively manage the assets on behalf of RMS:

  • putting RMS’ customers (road users and the general public) first and being responsive to them
  • being responsible and accountable for the outcomes resulting from the management of the assets
  • managing the assets diligently, efficiently and effectively with limited direction from RMS
  • working collaboratively with RMS to deliver services that are tailored to meet RMS’ evolving needs
  • acting with integrity and transparency in performing the services
  • performing the services in the best interests of RMS and asset users.

Other key features of the SMC include:

  • service requirements which describe the scope of the services, and the standards the contractor must meet
  • a commercial framework which defines how payments are structured, how performance assessment will impact on payments and outlines the key commercial principles. SMCs primarily divide payments into two main mechanisms, these being the priced component (or fixed price) and the target cost calculated as follows:
    • fixed price – the contractor is paid a pre-agreed amount for specific services being provided, regardless of the actual costs incurred
    • target cost – RMS and the contractor agree on a target cost for a project, and any cost overruns or underruns are shared between them
  • a performance framework which provides mechanisms for assessing contractor performance. This includes a comprehensive listing of the key result areas (KRAs) and key performance indicators (KPIs) against which RMS measures the contractor’s performance. The framework also outlines the scoring methodology that RMS uses to determine whether the contractor’s bid margin (profit and overheads) is reduced due to less than satisfactory performance or whether a bonus is paid if a threshold performance score is exceeded.

Road maintenance under SMCs for Sydney region south and west zones commenced in November 2013

In November 2013, RMS awarded SMCs to the Leighton Boral Amey consortium, now named Ventia Boral Amey (VBA), for the south zone and the DownerMouchel (DM) consortium for the west zone. The contracts run for seven years with an option for a further three years at RMS’ discretion. In April 2014, full services commenced following a four-month transition period. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

  1. Roads and Maritime Services should consider whether to incorporate stronger sanctions in the Stewardship Maintenance Contract if the contractor provides incorrect performance or financial data to RMS, when:
     
    1. negotiating the commercial reset for the next works period with the Sydney region south and west zone contractors due in July 2018.
    2. finalising a new SMC contract for the Sydney region north zone, due to commence in October 2018.

Roads and Maritime Services should, by September 2017:

2.  Review its contract management framework for SMCs to ensure that all authorities and accountabilities of
     contract managers are clearly defined, including:

a) accountability and procedures for exercising all operational clauses in the SMC where RMS may opt to, or be required to intervene, or make a decision

b) authority to approve or initiate the interventions RMS is required to, or may, exercise under the SMC

c) the audits that RMS will conduct to systematically validate the performance and financial data that the SMC contractors provide

d) the accountabilities of RMS contract managers to systematically review audits and quality reviews that the SMC contractors must conduct to demonstrate compliance with their service plans

e) the accountabilities of RMS contract managers to check that the monthly and annual reports provided by SMC contractors do not contain errors, omissions or inaccuracies.

3.  Improve its management of benefits realisation by:

a) initiating a further benefits realisation review and record the benefits delivered against those
    estimated following the tender process, including the one-off transition costs

b) identify any benefits, including savings, not yet attained and develop strategies to address any short-falls

c) establish a tool to track the ongoing realisation of benefits.

Published

Actions for NorthConnex

NorthConnex

Premier and Cabinet
Treasury
Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement

The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan.

NorthConnex is a nine-kilometre tolled motorway tunnel between the M1 Pacific motorway at Wahroonga and the M2 Hills motorway at West Pennant Hills. The total cost for the project is $3.1 billion. NorthConnex will be funded through toll charges, and contributions from the NSW and Australian Governments of up to $405 million each. In January 2015, the NSW Roads Minister signed the final contracts for NorthConnex.

By December 2017, the Department of Premier and Cabinet should:

1. publish an updated ‘Unsolicited Proposals – Guide for Submission and Assessment’ which clarifies obligations with requirements in other NSW Government policies such as the NSW PPP guideline and Infrastructure Investor Assurance Framework. The update should require:

a) a business case to be prepared, and a business case gateway review completed, as part of the assessment of the detailed proposal (currently stage 2)

b) probity reports must be completed and considered before the decision to proceed to the next stage.
 

The Department of Premier and Cabinet and NSW Treasury should immediately:

2. improve record keeping to ensure compliance with the State Records Act 1998 and the NSW Government Standard on Records Management.

 

Published

Actions for Mining Rehabilitation Security Deposits

Mining Rehabilitation Security Deposits

Planning
Industry
Environment
Infrastructure
Management and administration
Project management

The Department of Planning and Environment requires mining companies to rehabilitate sites according to conditions set in the mining development approval. The Department holds mining rehabilitation security deposits that are meant to cover the full cost of rehabilitation if a mining company defaults on its rehabilitation obligations.

The total value of security deposits held has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites in New South Wales.

While there have been substantial increases in total deposits held, mine rehabilitation security deposits are still not likely to be sufficient to cover the full costs of each mine's rehabilitation in the event of a default.

This audit was undertaken when the Department of Industry, Skills and Regional Development was responsible for ensuring land disturbed by mining activities is rehabilitated in accordance with the relevant development approval, including the administration of mining rehabilitation security deposits. On 1 April 2017, this responsibility was transferred to the Department of Planning and Environment (the Department).  

This audit assessed whether the Department maintains adequate security deposits to cover the liabilities associated with mine closures, including rehabilitation. Companies authorised by the Department to undertake mining activities must provide a security deposit to cover the full costs of rehabilitation in the event of default by the company. Rehabilitation is the treatment of disturbed land or water to establish a safe, stable, non-polluting and sustainable environment.

Mining companies must provide an estimate of rehabilitation costs for each site. The Department provides a Rehabilitation Cost Calculation tool to assist companies calculate the deposit amount. Companies are also required to ensure that the cost estimate is in accordance with the approved Mining Operations Plan (MOP). The MOP is intended to be a mine rehabilitation and closure plan, and forms the basis for the estimation of the security deposit. The Department reviews the estimates and determines the deposit for each site.  

Security deposits are an option of last resort. The Department has other legislative and regulatory tools which it normally uses to promote compliance with rehabilitation requirements before accessing a security deposit. It can direct action by the mining company, issue fines and even have the Minister revoke a mining lease. To date, the Department has never had to access a security deposit for a state significant development mine site.

Conclusion

The Department holds security deposits for mining rehabilitation consistent with the amounts it has requested from mining companies, and it should be able to claim on a deposit if a mining company defaults on its rehabilitation obligations. The total value of deposits has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites. The Department’s management of the security deposit process has improved in recent years, and it has well advanced plans for further improvement, including a revised cost calculation tool.

The Department’s policy is that each mine’s security deposit should cover the full costs of rehabilitation for that mine. The security deposits the Department holds are not likely to be sufficient to cover the full costs of each mine’s rehabilitation in the event of a default. The rates and allowances in the current cost calculation tool have not been updated since 2013 and some activities required for effective rehabilitation are not covered, or not covered adequately.

Security deposits also do not include sufficient contingency given the substantial risks and uncertainties associated with mine rehabilitation and closure, particularly in the absence of a detailed closure plan. This risk is exacerbated by the limited independent verification of mining company claims about the size of the outstanding rehabilitation task, which remains the case despite recent improvements to monitoring and review procedures and practices.  

There is also no financial assurance held over the risk of significant unexpected environmental degradation in the long-term after a mine is deemed to be rehabilitated and the security deposit is returned. A security deposit is not an appropriate vehicle for covering this risk.

Security deposits are close to calculated value and should be accessible if needed

The value of securities held by the Department aligns with the latest approved rehabilitation cost estimates. This contrasts with the situation found by investigations in Victoria and Queensland, where deposit amounts held fell below the calculated costs.

The security deposits are usually in the form of a bank guarantee or cash. The Department has obtained legal advice indicating that it should be able to claim on these bank guarantees if the need arises. As the guarantee is between the financial institution and the Department, if a mining company goes into liquidation the Department should still be able to access the funds.  

When the latest estimate of rehabilitation costs is higher than the existing deposit, the Department will request additional security. It has experienced extensive delays in obtaining additional security for some sites, increasing the risk that available funds will be insufficient if needed.

Rehabilitation cost estimates are not yet adequate, but improvements are planned

The Department’s policy is for security deposits to cover the full cost of rehabilitation. No discounts are provided to mining companies for past good behaviour or low likelihood of default, unlike in some other states. Discounting could undermine the policy position.  

Current security deposits are unlikely to cover the full cost of rehabilitation on each mine site. The Department provides a rehabilitation cost calculation tool to help mining companies calculate the cost of rehabilitation and the required deposit amount, but:

  • several activities required to effect closure are not included and others underestimated
  • it does not make provision for industry cost changes over time
  • the rates used in the tool have not been updated since 2013
  • it was not able to provide the basis for the rates and allowances in the tool.

The Department reviews cost estimates provided by mining companies, but its verification of the extent of rehabilitation work on which these estimates are based is limited. It relies instead on section 387C of the Mining Act 1992 which makes it an offence for mining companies to provide false or misleading information. It is not evident how the Department would establish that information provided was false or misleading without more verification work, and six of the 14 cost estimates we reviewed were not signed by the mine manager, making enforcement more difficult.  

The Department has developed a new calculation tool, and recently released it for industry consultation. The new tool should improve rehabilitation estimates. It updates rates and allowances, and includes additional items to better cover required rehabilitation tasks. While a substantial improvement, the new tool could be further improved by providing additional coverage for stakeholder engagement, additional planning approvals, insurance costs, and any additional design, research and verification work required for successful closure.

There is no financial assurance over long-term environmental risks

The Department does not hold any financial assurance to cover the costs associated with mitigating any future environmental degradation once a mine closes and the security deposit is relinquished to the mining company. Security deposits are probably not the appropriate mechanism to cover these long-term risks but the risk of potential post-closure environmental degradation still needs to be costed and covered. A fund to cover the state-wide risk, to which all mines would contribute, is a possible mechanism.

Rehabilitation and closure outcomes are vague, particularly for unplanned closure

Rehabilitation outcomes in the MOPs we reviewed were generally not specific. Any lack of specificity in MOPs translates into uncertainty about rehabilitation work required if a mining company defaults. Part of the problem is that rehabilitation outcomes established in planning approvals are usually not specific and may not address all closure requirements. The Department has recognised there is scope to improve the clarity and specificity of rehabilitation requirements in planning approvals, and has started a review focusing on open-cut mines.

Rehabilitation outcomes are even less specific in the event of an unexpected early closure because they will probably be different from that achievable from a planned closure.  

MOP guidelines do not cover management of some key closure matters, such as the requirements of environment protection licences issued by the Environment Protection Authority and the management of heritage sites during closure.

There were significant variations in quality of MOPs we reviewed and the way closure risks and uncertainties were identified and addressed. The Department plans to improve the quality of rehabilitation programs through enhanced guidance and oversight.

Monitoring is not adequate to effectively gauge rehabilitation progress

The Department was not able to show it has been monitoring operational mine sites effectively to gauge the progress of ongoing site rehabilitation and the management of closure risks. There was no protocol for site inspections and limited evidence of inspections for the sites we reviewed.

The Department receives annual environmental management reports from mining companies, with most describing the areas of disturbance and rehabilitation occurring at each mine site. The Department recently established procedures for reviewing these annual reports, and has developed a risk-based process for prioritising reviews.

Most annual reports we reviewed did not explain environmental changes over time, nor the risks to mine closure and the measures required to mitigate them. For example, analysis of changes to surface water and groundwater quality was limited despite its relevance for assessing future contamination risks.

The Department does not currently have adequate processes in place to effectively verify the reported areas of disturbance and rehabilitation. It is developing geographic information system-based tools to better measure areas of disturbance and rehabilitation, new rehabilitation guidelines, and a procedure for determining whether rehabilitation has been successful. These initiatives should improve the monitoring and reporting of rehabilitation progress at mine sites.

There is no mechanism to prevent a mine being in ‘care and maintenance’ indefinitely

The Department does not have a clear policy on the length of time and circumstances under which a mine can remain in ‘care and maintenance’. Indefinite postponement of rehabilitation and closure is therefore possible. 'Care and maintenance' is the period following temporary cessation of operations when infrastructure remains largely intact and the site continues to be managed. There are a range of valid reasons for a mining company to put a mine in ‘care and maintenance’, but it is also reasonable for the community to expect a limit to how long it has to wait for proper rehabilitation.

Mining operations make a significant contribution to the NSW economy, including over $1.3 billion in royalties each year. Around 400 mine sites throughout NSW provide over 40,000 jobs and are a major source of economic activity for many communities. Despite these benefits, it is important to ensure that mining companies fulfil their obligations to rehabilitate land disturbed as a result of mining activity.

We recommend that the Department should, by January 2018:

1. Improve the quality of rehabilitation and closure plans by:

  • ensuring plans submitted by mining companies include robust mine rehabilitation and closure risk assessments
  • clarifying the level of detail required in plans at each stage of a mine’s operation
  • specifying how requirements set under other legislative instruments (e.g. environment protection licences, heritage assets) should be addressed.

2. Improve assurance that security deposits are sufficient by:

  • ensuring its new cost calculation tool adequately covers all works needed for rehabilitation and closure
  • increasing the contingency for uncertainties associated with mine rehabilitation and closure, at least until the mining company provides a detailed closure plan
  • verifying the cost estimates for a sample of high risk sites annually
  • ensuring that when mining companies are required to provide increased security deposits, they do so with minimal delay.

3. Enhance oversight of mine rehabilitation by:

  • developing a protocol to ensure sufficient and adequate site inspections
  • ensuring mining companies report performance against rehabilitation targets and environmental changes clearly, including an analysis of long-term surface water and groundwater trends in terms of levels, flow and quality
  • improving how it determines the progress and success of mine rehabilitation
  • developing clear policy and procedures for ensuring a mine cannot be put into ‘care and maintenance’ indefinitely.

4. Collaborate with relevant agencies to establish a financial assurance mechanism, such as a sinking fund, to cover the risk of long-term environmental degradation after mines are closed and security deposits returned.

Appendix One - Response from the Department

Appendix Two - About the audit

 

Parliamentary reference - Report number #285 - released 11 May 2017

Published

Actions for Passenger Rail Punctuality

Passenger Rail Punctuality

Transport
Information technology
Infrastructure
Service delivery

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

A NSW Government priority is to ‘maintain or improve reliability of public transport services over the next four years’. Punctuality is a key element of reliability, and the level of patronage is a critical factor in the ability to maintain punctuality. Increasing patronage places pressure on the length of time trains need to wait at stations to load and offload passengers which can lead to delays. The NSW Long Term Transport Master Plan forecasts that rail patronage could increase by 26 per cent between 2012 and 2031.  

Passenger rail services in NSW are provided under a purchaser-provider model. Transport for NSW enters contracts with:

  • Sydney Trains for Sydney suburban passenger rail services
  • NSW Trains for services that commence or terminate outside Sydney, including intercity services that operate between Central station and the South Coast, Southern Highlands, Blue Mountains and Central Coast and Newcastle.

Transport for NSW sets performance targets and standards for these services, develops the timetables, procures trains for the service providers, and is responsible for long term planning.

This audit assessed whether these rail agencies have plans and strategies to maintain or improve performance in getting the growing number of suburban and intercity rail passengers to their destinations on time.

Conclusion:

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

Transport for NSW has undertaken considerable work on developing strategies to increase capacity and maintain punctuality after 2019, but remains some way from putting a costed plan to the government. There is a significant risk that investments will not be made soon enough to handle future patronage levels. Ideally, planning and investment decisions should have been made already.

Punctuality measurement is satisfactory, but agencies could publish more information

Passenger rail punctuality indicators adopted in NSW are good practice. The key train punctuality indicator is better than indicators used by many other rail operators. It is also better than the on-time-running indicator that it replaced. Unlike the on-time-running indicator, the punctuality indicator classifies trains that have been cancelled or skipped stations as late and results are not adjusted to take account of delays caused by factors such as extreme weather or police operations.

NSW also has a customer delay measure which represents good practice. Work has started on refining and embedding customer delay as a key performance measure for the planned new Rail Operations Centre.

As train frequency approaches a ‘turn up and go’ level of service, rather than running to a timetable, more emphasis will need to be placed on excess waiting time and customer delay when assessing performance.

Measurement of punctuality is reasonably precise. There are some measurement inaccuracies which should be addressed, such as the estimated arrival time of a train being incorrect at some destination stations, but these do not affect punctuality results materially.  

Train punctuality is reported publicly, but not to the detail of the indicators in the contracts between Transport for NSW and Sydney Trains and NSW Trains. There is very limited public reporting of customer delay.

Overall punctuality is good, but some services are relatively poor

System-wide train punctuality has usually exceeded target since 2005, but some services suffer from poor punctuality compared to the rest of the network.  

The part of the network around North Sydney is creating problems for the punctuality of afternoon peak services heading through it and out to Western Sydney and to Hornsby via Strathfield. Transport for NSW and Sydney Trains are well advanced with strategies to address this up to 2019.  

The East Hills express trains in the afternoon peak also performed well below target. The rail agencies recently analysed this issue and believe it relates to the train timetable and signalling which restricts how close trains can run behind each other into Campbelltown. It further advises that this will be corrected over the next three years.  

Intercity train punctuality is below that of suburban trains and there was an extended period of declining punctuality between 2011 and 2014. Transport for NSW suggested that the old age of trains is a factor, and the recently announced intercity fleet acquisition may help address this. Apart from ensuring that train crew and station staff are available and perform their duties adequately, NSW Trains can do little to impact the punctuality of its intercity services directly. Train maintenance, track and signal maintenance, and management of trains on the rail network are performed by Sydney Trains. NSW Trains’ ability to influence improvement is hampered by key indicators in some contracts being undefined. Transport for NSW, Sydney Trains and NSW Trains are now working collaboratively to make improvements to the contracts.

Initiatives are in place or are planned to deliver good punctuality until 2019

Patronage increases, which can lead to overcrowding and trains having to wait longer at stations, are likely to present a significant challenge to maintaining punctuality into the future.

Based on patronage projections, the rail agencies have strategies to maintain punctuality up to and including joining the Sydney Metro Northwest to the network at Chatswood in 2019. These include improving infrastructure at particular parts of the network, increasing staff training, reducing the number of speed restrictions, and a new Rail Operations Centre. The projects are being managed by experienced staff, with good governance arrangements, quality assurance processes and planning systems in place. New timetables should provide more services and cater for more passengers, including off peak. They should increase network efficiency through better utilisation of capacity, but some passengers may face longer journey times and more may need to change trains mid-journey.  

The planned Rail Operations Centre has the potential to make operational decision-making more customer-focussed, by placing more emphasis on minimising customer delay during disruptions. If implemented well, it will also generate information to help agencies better identify the root cause of incidents that delay trains and improve communication with passengers so they can make better real-time travel decisions.

Predicted passenger growth presents a risk to punctuality after 2019

The rail system will struggle to maintain punctuality much beyond 2019 based on current patronage forecasts and system limitations.

From 2024, the Sydney Metro City and Southwest will help by extending the metro network from Chatswood under Sydney Harbour, through the city and out to Bankstown. Announced fleet upgrades will also help. Transport for NSW advises that it is also working with the Greater Sydney Commission to ensure network capacity constraints are considered in future urban planning.

In addition to investment in new metro networks, sustained and substantial investment needs to be made into the existing heavy rail network to meet demand and ensure its ongoing reliability. Transport for NSW has been developing strategies for this purpose, including an Advanced Train Control system. Its aim is to put a costed plan to the government by the third quarter of this (2017) calendar year. Given the likely lead times involved with major infrastructure projects, there remains a significant risk of poor punctuality after 2019.

Punctuality could be at risk sooner if recent patronage growth continues

If patronage continues to increase at a faster rate than forecast, particularly during the morning peak, the network will struggle to cope before 2019. Transport for NSW forecast that between 2011 and 2026 morning peak rail patronage would increase each year by approximately 3.3 per cent. Between 2011 and 2016 the number of passengers travelling to the city during the morning peak grew by an average of 4.4 per cent each year, including annual growth of 6.6 per cent since May 2014.

A good understanding of patronage levels, trends and drivers is critical to effective planning. The audit identified some shortcomings in measurement of peak passenger loads. Transport for NSW advised that measurement approaches have been improved recently, and this will soon flow into improved data quality.  

Given the increasing flexibility in work practices available to many city workers, the relatively new field of behavioural insights may offer opportunities to ‘nudge’ some passengers away from travelling at the height of the peak with benefits for them and the network.

  1. Transport for NSW should ensure that programs to address rail patronage growth over the next five to ten years are provided to the government for Cabinet consideration as soon as possible.
     
  2. Sydney Trains and Transport for NSW should:
    a) maintain effective oversight and resourcing for all strategies designed to address rail patronage growth
    b) adjust strategies for any patronage growth above projection.
     
  3. Sydney Trains, NSW Trains and Transport for NSW should publish Customer Delay results by June 2018.
     
  4. Transport for NSW, Sydney Trains and NSW Trains should agree by December 2017:
    a) specific performance requirements for intercity train, track and signal availability and reliability
    b) guidelines for train priorities during disruptions and indicators of control centre performance in implementing these guidelines.
     
  5. Sydney Trains, NSW Trains and Transport for NSW should by June 2018:
    a) improve the accuracy of patronage measurement and develop a better understanding of patronage growth trends
    b) address small errors in the adjustment factors used for determining a train’s punctuality status
    c) improve their understanding of the factors impacting on intercity punctuality.
     
  6. Transport for NSW should, commencing June 2017, explore the potential to use behavioural insights to encourage more passengers to travel outside the height of the morning peak (8 am to 9 am).