Refine search Expand filter

Reports

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.

Some of the findings of the report include:

  • government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)

  • passenger services revenue only covered 20 per cent of RailCorp's operating costs

  • Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

  • At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually

  • Transport patronage continued to grow with 510 million journeys on train, bus and ferry services

  • CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time

  • On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12

  • Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes

  • Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.

 

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Improving road safety: Young drivers

Improving road safety: Young drivers

Transport
Finance
Project management
Regulation
Service delivery

The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effective in reducing crashes and saving lives. Despite these improvements, young drivers are more likely to be involved in fatal crashes than other drivers.

 

Parliamentary reference - Report number #217 - released 19 October 2011

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Volume Five 2010 focus on Public Financing Enterprises

Volume Five 2010 focus on Public Financing Enterprises

Industry
Transport
Finance
Treasury
Planning
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
 

Published

Actions for Improving the Performance of Metropolitan Bus Services

Improving the Performance of Metropolitan Bus Services

Transport
Internal controls and governance
Management and administration
Procurement
Service delivery

The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.

 

Parliamentary reference - Report number #198 - released 10 March 2010

Published

Actions for Improving Road Safety: School Zones

Improving Road Safety: School Zones

Transport
Management and administration
Service delivery

Overall, speed cameras change driver behaviour and improve road safety. Fixed speed cameras reduce crashes and speeding. While the overall impact of speed cameras has been positive, 38 of the 141 fixed speed cameras need to be closely examined as they appear to have no significant road safety benefit. Other road safety measures may be needed for these sites.

 

Parliamentary reference - Report number #197 - released 10 March 2010

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007