Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Regulation of water pollution in drinking water catchments and illegal disposal of solid waste

Regulation of water pollution in drinking water catchments and illegal disposal of solid waste

Environment
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

There are important gaps in how the Environmental Protection Authority (EPA) implements its regulatory framework for water pollution in drinking water catchments and illegal solid waste disposal. This limits the effectiveness of its regulatory responses, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

The NSW Environment Protection Authority (the EPA) is the State’s primary environmental regulator. The EPA regulates waste and water pollution under the Protection of the Environment Operations Act 1997 (the Act) through its licensing, monitoring, regulation and enforcement activities. The community should be able to rely on the effectiveness of this regulation to protect the environment and human health. The EPA has regulatory responsibility for more significant and specific activities which can potentially harm the environment.

Activities regulated by the EPA include manufacturing, chemical production, electricity generation, mining, waste management, livestock processing, mineral processing, sewerage treatment, and road construction. For these activities, the operator must have an EPA issued environment protection licence (licence). Licences have conditions attached which may limit the amount and concentrations of substances the activity may produce and discharge into the environment. Conditions also require the licensee to report on its licensed activities.

This audit assessed the effectiveness of the EPA’s regulatory response to water pollution in drinking water catchments and illegal solid waste disposal. The findings and recommendations of this review can be reasonably applied to the EPA’s other regulatory functions, as the areas we examined were indicative of how the EPA regulates all pollution types and incidents.

 
Conclusion
There are important gaps in how the EPA implements its regulatory framework for water pollution in drinking water catchments and illegal solid waste disposal which limit the effectiveness of its regulatory response. The EPA uses a risk-based regulatory framework that has elements consistent with the NSW Government Guidance for regulators to implement outcomes and risk-based regulation. However, the EPA did not demonstrate that it has established reliable practices to accurately and consistently detect the risk of non compliances by licensees, and apply consistent regulatory actions. This may expose the risk of harm to the environment and human health.
The EPA also could not demonstrate that it has effective governance and oversight of its regulatory operations. The EPA operates in a complex regulatory environment where its regional offices have broad discretions for how they operate. The EPA has not balanced this devolved structure with an effective governance approach that includes appropriate internal controls to monitor the consistency or quality of its regulatory activities. It also does not have an effective performance framework that sets relevant performance expectations and outcome-based key performance indicators (KPIs) for its regional offices. 
These deficiencies mean that the EPA cannot be confident that it conducts compliance and enforcement activities consistently across the State and that licensees are complying with their licence conditions or the Act.
The EPA's reporting on environmental and regulatory outcomes is limited and most of the data it uses is self reported by industry. It has not set outcome-based key result areas to assess performance and trends over time. 
The EPA uses a risk-based regulatory framework for water pollution and illegal solid waste disposal but there are important gaps in implementation that reduce its effectiveness.
Elements of the EPA’s risk-based regulatory framework for water pollution and illegal solid waste disposal are consistent with the NSW Government Guidance for regulators to implement outcomes and risk-based regulation. There are important gaps in how the EPA implements its risk-based approach that limit the effectiveness of its regulatory response. The EPA could not demonstrate that it effectively regulates licensees because it has not established reliable practices that accurately and consistently detect licence non compliances or breaches of the Act and enforce regulatory actions.
The EPA lacks effective governance arrangements to support its devolved regional structure. The EPA's performance framework has limited and inconclusive reporting on regional performance to the EPA’s Chief Executive Officer or to the EPA Board. The EPA cannot assure that it is conducting its regulatory responsibilities effectively and efficiently. 
The EPA does not consistently evaluate its regulatory approach to ensure it is effective and efficient. For example, there are no set requirements for how EPA officers conduct mandatory site inspections, which means that there is a risk that officers are not detecting all breaches or non-compliances. The inconsistent approach also means that the EPA cannot rely on the data it collects from these site inspections to understand whether its regulatory response is effective and efficient. In addition, where the EPA identifies instances of non compliance or breaches, it does not apply all available regulatory actions to encourage compliance.
The EPA also does not have a systematic approach to validate self-reported information in licensees’ annual returns, despite the data being used to assess administrative fees payable to the EPA and its regulatory response to non-compliances. 
The EPA does not use performance frameworks to monitor the consistency or quality of work conducted across the State. The EPA has also failed to provide effective guidance for its staff. Many of its policies and procedures are out-dated, inconsistent, hard to access, or not mandated.
Recommendations
By 31 December 2018, to improve governance and oversight, the EPA should:
1. implement a more effective performance framework with regular reports to the Chief Executive Officer and to the EPA Board on outcomes-based key result areas that assess its environmental and regulatory performance and trends over time
By 30 June 2019, to improve consistency in its practices, the EPA should:
2. progressively update and make accessible its policies and procedures for regulatory operations, and mandate procedures where necessary to ensure consistent application
3. implement internal controls to monitor the consistency and quality of its regulatory operations. 
The EPA does not apply a consistent approach to setting licence conditions for discharges to water.
The requirements for setting licence conditions for water pollution are complex and require technical and scientific expertise. In August 2016, the EPA approved guidance developed by its technical experts in the Water Technical Advisory Unit to assist its regional staff. However, the EPA did not mandate the use of the guidance until mid-April 2018. Up until then, the EPA had left discretion to regional offices to decide what guidance their staff use. This meant that practices have differed across the organisation. The EPA is yet to conduct training for staff to ensure they consistently apply the 2016 guidance.
The EPA has not implemented any appropriate internal controls or quality assurance process to monitor the consistency or quality of licence conditions set by its officers across the State. This is not consistent with good regulatory practice.
The triennial 2016 audit of the Sydney drinking water catchment report highlighted that Lake Burragorang has experienced worsening water quality over the past 20 years from increased salinity levels. The salinity levels were nearly twice as high as in other storages in the Sydney drinking water catchment. The report recommended that the source and implication of the increased salinity levels be investigated. The report did not propose which public authority should carry out such an investigation. 
To date, no NSW Government agency has addressed the report's recommendation. There are three public authorities, the EPA, DPE and WaterNSW that are responsible for regulating activities that impact on water quality in the Sydney drinking water catchment, which includes Lake Burragorang. 
Recommendation
By 30 June 2019, to address worsening water quality in Lake Burragorang, the EPA should:
4. (a) review the impact of its licensed activities on water quality in Lake Burragorang, and
  (b) develop strategies relating to its licensed activities (in consultation with other relevant NSW Government agencies) to improve and maintain the lake's water quality.
The EPA’s risk-based approach to monitoring compliance of licensees has limited effectiveness. 
The EPA tailors its compliance monitoring approach based on the performance of licensees. This means that licensees that perform better have a lower administrative fee and fewer mandatory site inspections. 
However, this approach relies on information that is not complete or accurate. Sources of information include licensees’ annual returns, EPA site inspections and compliance audits, and pollution reports from the public. 
Licensees report annually to the EPA on their performance, including compliance against their licence conditions. The Act contains significant financial penalties if licensees provide false and misleading information in their annual returns. However, the EPA does not systematically or consistently validate information self-reported by licensees, or consistently apply regulatory actions if it discovers non-compliance. 
Self-reported compliance data is used in part to assess a licensed premises’ overall environmental risk level, which underpins the calculation of the administrative fee, the EPA’s site inspection frequency, and the licensee’s exposure to regulatory actions. It is also used to assess the load-based licence fee that the licensee pays.
The EPA has set minimum mandatory site inspection frequencies for licensed premises based on its assessed overall risk level. This is a key tool to detect non-compliance or breaches of the Act. However, the EPA has not issued a policy or procedures that define what these mandatory inspections should cover and how they are to be conducted. We found variations in how the EPA officers in the offices we visited conducted these inspections. The inconsistent approach means that the EPA does not have complete and accurate information of licensees’ compliance. The inconsistent approach also means that the EPA is not effectively identifying all non-compliances for it to consider applying appropriate regulatory actions.
The EPA also receives reports of pollution incidents from the public that may indicate non-compliance. However, the EPA has not set expected time frames within which it expects its officers to investigate pollution incidents. The EPA regional offices decide what to investigate and timeframes. The EPA does not measure regional performance regarding timeframes. 
The few compliance audits the EPA conducts annually are effective in identifying licence non-compliances and breaches of the Act. However, the EPA does not have a policy or required procedures for its regulatory officers to consistently apply appropriate regulatory actions in response to compliance audit findings. 
The EPA has not implemented any effective internal controls or quality assurance process to check the consistency or quality of how its regulatory officers monitor compliance across the State. This is not consistent with good regulatory practice.
Recommendations
To improve compliance monitoring, the EPA should implement procedures to:
5. by 30 June 2019, validate self-reported information, eliminate hardcopy submissions and require licensees to report on their breaches of the Act and associated regulations in their annual returns
6. by 31 December 2018, conduct mandatory site inspections under the risk-based licensing scheme to assess compliance with all regulatory requirements and licence conditions.
 
The EPA cannot assure that its regulatory enforcement approach is fully effective.
The EPA’s compliance policy and prosecution guidelines have a large number of available regulatory actions and factors which should be taken into account when selecting an appropriate regulatory response. The extensive legislation determining the EPA’s regulatory activities, and the devolved regional structure the EPA has adopted in delivering its compliance and regulatory functions, increases the risk of inconsistent compliance decisions and regulatory responses. A good regulatory framework needs a consistent approach to enforcement to incentivise compliance. 
The EPA has not balanced this devolved regional structure with appropriate governance arrangements to give it assurance that its regulatory officers apply a consistent approach to enforcement.
The EPA has not issued standard procedures to ensure consistent non-court enforcement action for breaches of the Act or non-compliance with licence conditions. Given our finding that the EPA does not effectively detect breaches and non-compliances, there is a risk that it is not applying appropriate regulatory actions for many breaches and non-compliances.
A recent EPA compliance audit identified significant non-compliances with incident management plan requirements. However, the EPA has not applied regulatory actions for making false statements on annual returns for those licensees that certified their plans complied with such requirements. The EPA also has not applied available regulatory actions for the non-compliances which led to the false or misleading statements.
Recommendation
By 31 December 2018 to improve enforcement, the EPA should:
7. Implement procedures to systematically assess non-compliances with licence conditions and breaches of the Act and to implement appropriate and consistent regulatory actions.
The EPA has implemented the actions listed in the NSW Illegal Dumping Strategy 2014–16. To date, the EPA has also implemented four of the six recommendations made by the ICAC on EPA's oversight of Regional Illegal Dumping Squads.
The EPA did not achieve the NSW Illegal Dumping Strategy 2014–16 target of a 30 per cent reduction in instances of large scale illegal dumping in Sydney, the Illawarra, Hunter and Central Coast from 2011 levels. 
In the reporting period, the incidences of large scale illegal dumping more than doubled. The EPA advised that this increase may be the result of greater public awareness and reporting rather than increased illegal dumping activity. 
By June 2018, the EPA is due to implement one outstanding recommendation made by the ICAC but has not set a time for the other outstanding recommendation.  

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.