Actions for Volume Six 2013 focusing on Law, Order and Emergency Services

Volume Six 2013 focusing on Law, Order and Emergency Services

Justice
Compliance
Fraud
Project management
Workforce and capability

We issued unqualified audit opinions on the above agencies’ 30 June 2013 financial statements. During the year, The Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. As a result, the law and order services agencies were required to perform early close procedures. All law and order service agencies were broadly successful in performing the procedures, which helped them submit financial statements by an earlier due date. This in turn enabled the financial statement audits to be finalised within an earlier timeframe of eight weeks (nine weeks in 2011-12).

As previously recommended, the Department of Attorney General and Justice should continue integrating policies, operations and systems between its divisions and, once complete, analyse the costs and benefits. The Department of Attorney-General and Justice should also ensure it has the necessary processes in place to enable it to regularly monitor and measure the performance and success of the Victims Support Scheme in providing a more accessible, streamlined and targeted service to victims of violent crime in New South Wales.

Published

Actions for Managing Drug Exhibits and other High Profile Goods

Managing Drug Exhibits and other High Profile Goods

Justice
Compliance
Information technology
Internal controls and governance
Management and administration
Risk

Some drug exhibits and other high profile goods, such as firearms, ammunition, vehicles and vessels, are held longer than necessary by NSW Police, increasing health and safety risks and storage costs.

 

Parliamentary reference - Report number #227 - released 28 February 2013

Published

Actions for Volume Eight 2010 focus on Law and Order and Emergency Services

Volume Eight 2010 focus on Law and Order and Emergency Services

Justice
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The report includes comments on his financial audits of NSW Government emergency services and law and order agencies for 2009-10. The audits of these agencies’ financial reports for the year ended 30 June 2010 each resulted in an unqualified Independent Auditor’s Report. Significant backlog in victims’ compensation claims The Department of Justice and Attorney General paid $63 million in compensation to victims of crimes but only received $4.2 million from offenders in 2009-10. Over $222 million worth of victims’ compensation claims are to be processed by the Department. The number of outstanding claims increased thirty-five per cent from 13,384 to 18,118 in 2009-10.

Published

Actions for Managing Forensic Analysis: Fingerprints and DNA

Managing Forensic Analysis: Fingerprints and DNA

Justice
Health
Internal controls and governance
Management and administration
Procurement
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Fingerprints and DNA play a critical role in solving crime and serving justice, but DNA evidence can result in more arrests, more prosecutions and more convictions. We found that while police effectively prioritise fingerprint evidence, it could better manage the screening and analysis of both fingerprint and DNA evidence to reduce delays.

 

Parliamentary reference - Report number #195 - released 10 February 2010

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Prisoner Rehabilitation

Prisoner Rehabilitation

Justice
Management and administration
Risk
Service delivery
Shared services and collaboration

In recent years the department has significantly changed its approach to rehabilitating prisoners. It has introduced programs to address offending behaviour based on evidence of what works. It has also formed partnerships with other agencies to help reintegrate prisoners into the community. We believe the department is on the right path and should continue building on these initiatives.

Despite these efforts, almost one in two prisoners return to prison or community supervision within two years of release, which is similar to other states. Most of these return to prison. In our opinion there is a risk that the department releases prisoners who have not addressed their rehabilitation needs. The department appears to address immediate health and welfare concerns. But it does not formally assess the education and work needs of all prisoners.

 

Parliamentary reference - Report number #151 - released 24 May 2006

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005