Actions for Transport 2016

Transport 2016

Transport
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Premier and Cabinet 2016

Premier and Cabinet 2016

Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

There are opportunities for agencies in the Premier and Cabinet cluster to improve financial controls and governance of outsourced service providers. These are the key findings of a report released by the New South Wales Auditor-General, Margaret Crawford.

Published

Actions for Justice 2016

Justice 2016

Justice
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Overcrowding in the NSW prison system continues to worsen along with the backlog of cases in the District Court, according to a report released by the New South Wales Auditor-General, Margaret Crawford on the annual financial statements audits in the Justice cluster.

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Volume Eight 2013 focusing on Transport and Ports

Volume Eight 2013 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Procurement
Project management
Regulation
Workforce and capability

Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.

The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.

Published

Actions for Volume Six 2013 focusing on Law, Order and Emergency Services

Volume Six 2013 focusing on Law, Order and Emergency Services

Justice
Compliance
Fraud
Project management
Workforce and capability

We issued unqualified audit opinions on the above agencies’ 30 June 2013 financial statements. During the year, The Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. As a result, the law and order services agencies were required to perform early close procedures. All law and order service agencies were broadly successful in performing the procedures, which helped them submit financial statements by an earlier due date. This in turn enabled the financial statement audits to be finalised within an earlier timeframe of eight weeks (nine weeks in 2011-12).

As previously recommended, the Department of Attorney General and Justice should continue integrating policies, operations and systems between its divisions and, once complete, analyse the costs and benefits. The Department of Attorney-General and Justice should also ensure it has the necessary processes in place to enable it to regularly monitor and measure the performance and success of the Victims Support Scheme in providing a more accessible, streamlined and targeted service to victims of violent crime in New South Wales.

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005