Refine search Expand filter

Reports

Published

Actions for Volume Seven 2011 focus on Law, Order and Emergency Services

Volume Seven 2011 focus on Law, Order and Emergency Services

Justice
Financial reporting
Management and administration
Procurement
Project management
Risk

The audits of these agencies’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. It is recommended that emergency services agencies continue to develop and implement comprehensive volunteer workforce management plans to ensure they have the right volunteer resources.

Published

Actions for Volume Five 2011 focus on Superannuation, Compensation and Housing

Volume Five 2011 focus on Superannuation, Compensation and Housing

Finance
Treasury
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Shared services and collaboration

The audits of the New South Wales Government controlled superannuation entities financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. Findings show that Treasury should review the structure and number of public sector superannuation funds and consider whether efficiencies and cost savings could be achieved through consolidation.

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for The effectiveness of cautioning for minor Cannabis offences

The effectiveness of cautioning for minor Cannabis offences

Justice
Health
Project management
Service delivery

Over the last ten years the NSW Police Force (Police) has used cautioning to divert over 39,000 minor cannabis offenders from the courts, saving at least $20 million in court costs. People cautioned for minor cannabis offences are also less likely to reoffend than those dealt with by the courts. Adults are more likely to be cautioned for minor cannabis offences today than when cautioning was introduced ten years ago. However this is not the case for young offenders who are more likely to be charged today. Cautioning may help people think about the consequences of their cannabis use. However few people seek help to reduce it with only 1.6 per cent of offenders contacting the drug helpline under the adult cautioning scheme. And there have been no evaluations yet on whether cautioning reduces drug use in NSW.

 

Parliamentary reference - Report number #211 - released 7 April 2011

Published

Actions for Managing Sick Leave

Managing Sick Leave

Justice
Internal controls and governance
Management and administration
Workforce and capability

The NSW Police and Department of Corrective Services (DCS) have committed to improve performance and productivity in their organisations. Both agencies have introduced several initiatives to promote the health, safety and welfare of their personnel. In addition the DCS policy provides for acknowledgements and sanctions based on the amount of medically uncertified leave taken by the employee. There are additional steps that could be taken to improve the management of sick leave.

 

Parliamentary reference - Report number #100 - released 23 July 2002