Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and

Published

Actions for NSW State Emergency Service Management of Volunteers

NSW State Emergency Service Management of Volunteers

Justice
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The SES needs to better understand the location, availability and skills of its volunteers so it can properly plan for emergency events. It needs to improve how it selects and retains the right volunteers and provide more up-to-date and focused training. The SES has improved volunteer safety with injury claims falling by 40 per cent to 70 in the four years to 30 June 2013. The average cost of claims has fallen by 58 per cent to $3,547. The SES attribute

Published

Actions for Fitness of Firefighters

Fitness of Firefighters

Justice
Internal controls and governance
Risk
Workforce and capability

Fire and Rescue NSW do not know whether all its firefighters are fit to perform their full range of operational duties. Once they are employed, there are no formal checks on firefighters’ health and fitness during their career. Also, while a health standard for firefighters has been developed it has not been agreed nor implemented.   Parliamentary reference - Report number #239 - released 1 April 2014

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handback,

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the c