Reports
Actions for Transport 2020
Transport 2020
1. Financial Reporting |
|
Audit opinion | Unmodified audit opinions issued for the financial statements of all Transport cluster entities. |
Quality and timeliness of financial reporting | All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements. Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances. |
Impact of COVID-19 on passenger revenue and patronage | Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19. The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing. |
Completion of the CBD and South East Light Rail | The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed. |
2. Audit Observations |
|
Internal control | While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management. There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below). |
Agency responses to emergency events | Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning. |
RailCorp transition to TAHE | On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders. A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE. Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures. This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE. Recommendation: TAHE management should:
Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base. |
Completeness and accuracy of contracts registers | Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers. Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
|
This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations
- the impact of emergencies and the pandemic.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.
Section highlights
|
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our:
- observations and insights from our financial statement audits of agencies in the Transport cluster
- assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.
Section highlights
|
Appendix one – List of 2020 recommendations
Appendix two – Status of 2019, 2018 and 2017 recommendations
Appendix three – Management letter findings
Appendix four – Financial data
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Stronger Communities 2020
Stronger Communities 2020
This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2020. The table below summarises our key observations.
1. Financial reporting |
|
Quality of financial reporting | Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements. |
Compliance with financial reporting requirements |
The Treasury extended the statutory deadline for the submission of the 2019–20 financial statements. For agencies subject to Treasurer's Directions, Treasury required agencies to submit their 30 June 2020 financial statements by 5 August 2020. For other agencies, the deadline was extended to 31 October 2020. All agencies in the cluster met the revised statutory deadlines. Cluster agencies substantially completed the mandatory early close procedures set by NSW Treasury. However, nine agencies including the Department of Communities and Justice (the department) did not complete one or more mandatory requirements, such as assessing the impact of new and updated accounting standards. |
Financial implications of recent emergencies |
Emergency events significantly impacted cluster agencies in 2019–20. Our review of seven cluster agencies most affected highlighted some had incurred additional expenditure because of the bushfires and floods. Others lost revenue due to the COVID-19 pandemic. During the year these agencies collectively received additional funding of $1.1 billion from the State to respond to:
The Sydney Cricket Ground Trust, Venues NSW and Office of Sport lodged insurance claims of $51.3 million with the Treasury Managed Fund with respect to lost revenues from the pandemic. The losses were mainly due to event cancellations and covered various periods ranging from mid-March to 31 December 2020. The change in economic conditions caused by the COVID-19 pandemic resulted in the NSW Government cancelling the refurbishment of Stadium Australia it had previously approved in August 2019. Venues NSW wrote off $16.8 million of redevelopment costs during 2019–20. |
Restatement of the Sydney Cricket Ground valuation | The valuation of the Sydney Cricket Ground (the Stadium) included costs of $28.6 million which were not eligible for capitalisation. The financial statements were restated to reflect the reduction in the value of the Stadium and the asset revaluation reserve. |
Unresolved data quality issues in the VS Connect system |
The department continues to address significant data quality issues resulting from its implementation of the VS Connect system (the System) in 2019. The issues relate to the completeness and accuracy of the data transferred from the legacy system. The System is used by the department to manage its Victims Support Services (VSS) and for financial reporting purposes. An independent actuary helps the department estimate its liability for VSS claims. The actuary's valuation at 30 June 2020 was again impacted by the data quality issues. Consequently, the actuary adopted a revised valuation methodology compared to previous years. Recommendation (repeat issue): The department should resolve the data quality issues in the VS Connect System before 31 March 2021. |
AASB 16 'Leases' resulted in significant changes to agencies' financial position |
Cluster agencies implemented three new accounting standards for the first time in 2019–20. Adoption of AASB 16 'Leases' resulted in cluster agencies collectively recognising right-of-use assets and lease liabilities of $1.7 billion and $1.1 billion respectively on 1 July 2019. Significant misstatements in how lease related balances had been calculated were found in 17 of the 29 cluster agencies. The cluster outsources the management of most of its owned and leased property portfolio to Property NSW, but cluster agencies remain responsible for any deliverables under that arrangement. The misstatements were mainly caused by late revisions of key assumptions and issues with the accuracy and completeness of Property NSW's lease information. |
2. Audit observations |
|
Internal control deficiencies |
Our 2019–20 financial audits identified 191 internal control issues. Of these, two were high risk and almost one-third were repeat findings from previous audits. While repeat findings reduced by 5.7 percentage points in 2019–20, the number remains high. Recommendation (repeat issue): Cluster agencies should action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues. |
Agencies response to recent emergencies |
The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies rose from $67.4 million in 2018–19 to $497 million in 2019–20. The COVID-19 pandemic presented unprecedented challenges for the cluster. Social distancing and other infection control measures disrupted the traditional means of delivering services. Agencies established committees or response teams to respond to these challenges. The department introduced measures to minimise the risk of the spread of COVID-19 amongst inmates in custodial settings. |
Managing excess annual leave |
Managing excess annual leave was a challenge for cluster agencies directly involved in the government's response to the emergency events. Employees in frontline cluster agencies deferred leave plans and many have taken little or no annual leave during the reporting period. Annual leave liabilities rose at the department, NSW Police Force, Fire and Rescue NSW, Office of the NSW Rural Fire Service, the Legal Aid Commission of New South Wales and the Office of the Director of Public Prosecutions. The combined liabilities increased from $620 million to $692 million or 11.6 per cent between 30 June 2019 and 30 June 2020. |
Implementation of Machinery of Government (MoG) changes |
Administrative Arrangement Orders effective from 1 July 2019, created the department of Communities and Justice and transferred functions and staff, together with associated assets and liabilities into the department from the former departments of Justice and Family and Community Services. The department continues to establish its governance arrangements following the MoG changes. Recommendation: The department should finalise appropriate governance arrangements for its new organisational structure as soon as possible. This includes:
|
Delivery of the Prison Bed Capacity Program |
The department continued to expand prison system capacity through the NSW Government's $3.8 billion Prison Bed Capacity Program. The department reported it spent $480 million on the Program in 2019–20. Six prison expansion projects were completed during the year, which added 1,660 new and 395 refurbished beds to the NSW prison system. Data from the department shows the number of adult inmates in the NSW prison system reached a maximum of 14,165 during the year. Operational capacity was 16,096 beds on 19 August 2020. |
This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analysis, conclusions and recommendations.
Agencies in the Stronger Communities cluster were significantly impacted by the bushfires, floods and the COVID-19 pandemic in 2019–20. Our 2019–20 financial audits of the seven cluster agencies most significantly impacted by the recent emergency events considered:
- the financial implications of the emergency events
- changes to agencies' operating models and control environments
- delivery of new or expanded projects, programs or services at short notice.
Our findings on these seven agencies' responses to the recent emergencies are included throughout this report. These agencies are:
- Department of Communities and Justice
- Fire and Rescue NSW
- NSW Police Force
- Office of the NSW Rural Fire Service
- Office of the NSW State Emergency Service
- Sydney Cricket and Sports Ground Trust
- Venues NSW.
The Department of Communities and Justice is the principal agency of the cluster. The names of all agencies in the Stronger Communities cluster are included in Appendix one.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster for 2020, including any financial implications from the recent emergency events.
Section highlights
|
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our:
- observations and insights from our financial statement audits of agencies in the Stronger Communities cluster
- assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
- review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.
Section highlights
|
Appendix one – Timeliness of financial reporting by agency
Appendix two – Management letter findings by agency
Appendix three – List of 2020 recommendations
Appendix four – Status of 2019 recommendations
Appendix five – Selected agencies for review of response to emergency events
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for CBD South East Sydney Light Rail: follow-up performance audit
CBD South East Sydney Light Rail: follow-up performance audit
This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.
The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.
The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.
The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.
The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.
Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).
On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.
In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.
In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.
Conclusion
Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.
Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.
From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.
TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.
Appendix one – Response from agency
Appendix two – Governance and reporting arrangements for the CSELR
Appendix three – 2018 CSELR governance changes
Appendix four – About the audit
Appendix five – Performance auditing
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Parliamentary reference - Report number #335 - released 11 June 2020
Actions for Train station crowding
Train station crowding
This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.
The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.
Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.
The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.
Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.
Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.
There are three main causes of station crowding:
- patronage growth exceeding the current capacity limits of the rail network
- service disruptions
- special events.
Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.
Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.
In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.
This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.
TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.
ConclusionSydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program. TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events. Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans. Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions. Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management. |
ConclusionTfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events. |
ConclusionSydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities. TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear. |
Appendix one – Response from agency
Appendix two – Sydney rail network
Appendix three – Rail services contract
Appendix four – Crowding pedestrian modelling
Appendix five – Airport Link stations case study
Appendix six – About the audit
Appendix seven – Performance auditing
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Parliamentary reference - Report number #333 - released 30 April 2020
Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.
The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.
This audit had two objectives:
- To assess the economy of the approach chosen to achieve the objectives of the Program.
- To assess the effectiveness of the consultation and oversight of the Program.
We addressed the audit objectives by answering the following questions:
a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.
Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.
2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.
Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
- providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
- providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
- making business cases available to the public.
The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.
The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.
Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
- work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received.
There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.
There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public.
Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.
Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.
The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.
Recommendations
For future infrastructure programs, NSW Government agencies should:
- develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
- establish whole-of-government oversight early in the program to guide major decisions. This should include:
- agreeing on objectives and ensuring all agencies understand these
- clearly defining roles and responsibilities for all agencies
- establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.
By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:
- setting measurable targets for the desired benefits
- clearly allocating ownership for achieving the desired benefits
- monitoring progress toward achieving the desired benefits and reporting publicly on the results.
Appendix one - Response from agencies
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #310 - released 12 December 2018
Actions for Transport 2018
Transport 2018
The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.
This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.
This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.
Observation | Conclusions and recommendations |
2.1 Quality of financial reporting | |
Unqualified audit opinions were issued for all agencies' financial statements | Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement. |
2.2 Key accounting issues | |
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS. |
RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million. The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase. |
2.3 Timeliness of financial reporting | |
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. | Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018. |
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. | Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process. |
2.4 Financial sustainability | |
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018. | NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. |
2.5 Passenger revenue and patronage | |
Transport agencies revenue growth increased at a higher rate than patronage. | Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. |
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. | Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences. |
2.6 Cost recovery from public transport users | |
Overall cost recovery from users has decreased. | Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18. |
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from:
- our financial statement audits of agencies in the Transport cluster for 2018
- the areas of focus identified in the Audit Office annual work program.
The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.
Observation | Conclusions and recommendations |
3.1 Internal controls | |
There was an increase in findings on internal controls across the Transport cluster. | Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues. |
3.2 Audit Office Annual work program | |
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology. |
Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. |
RailCorp is expected to convert to TAHE from 1 July 2019. | Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements. |
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. | TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. |
Not all agencies monitor unplanned maintenance across the Transport cluster. | Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster. |
This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.
We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report.
In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.
Actions for Mobile speed cameras
Mobile speed cameras
The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.
Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.
Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.
This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.
The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.
Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.
A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.
There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #308 - released 18 October 2018
Actions for Regional Assistance Programs
Regional Assistance Programs
Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.
The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.
The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.
This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:
- How well are the relevant agencies managing the assessment and recommendation process?
- How do the relevant agencies ensure that funded projects are being delivered?
- Do the funded projects meet program and project objectives?
The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.
The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.
The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.
Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.
While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.
Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.
The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.
Recommendations
- By June 2018, Infrastructure NSW should:
- ensure probity reports address whether all elements of the probity plan have been effectively implemented.
- By June 2018, Infrastructure NSW and Transport for NSW should:
- maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans
Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.
Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.
Recommendations
- By December 2018, Infrastructure NSW should:
- conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
- publish the circumstances under which unspent funds can be allocated to changes in project scope
- measure benefits delivered by projects that were completed before December 2017
- implement an annual process to measure benefits for projects completed after December 2017
- By December 2018, Transport for NSW and Infrastructure NSW should:
- incorporate a benefits realisation framework as part of the detailed application.
Appendix one - Response from agencies
Appendix two - Maps of funded projects
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #300 - released 17 May 2018
Actions for Managing risks in the NSW public sector: risk culture and capability
Managing risks in the NSW public sector: risk culture and capability
The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.
We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.
Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.
This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:
- agencies can demonstrate that senior management is committed to risk management
- information about risk is communicated effectively throughout agencies
- agencies are building risk management capabilities.
The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.
In assessing an agency’s risk culture, we focused on four key areas:
Executive sponsorship (tone at the top)
In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.
That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.
For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.
Employee perceptions of risk management
Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.
Integration of risk management into daily activities and links to decision-making
We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.
Support and guidance to help staff manage risks
Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.
Recommendation
By May 2019, NSW Treasury should:
- Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.
Appendix one - Response from agencies
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #298 - released 23 April 2018
Actions for Internal Controls and Governance 2017
Internal Controls and Governance 2017
Agencies need to do more to address risks posed by information technology (IT).
Effective internal controls and governance systems help agencies to operate efficiently and effectively and comply with relevant laws, standards and policies. We assessed how well agencies are implementing these systems, and highlighted opportunities for improvement.
1. Overall trends
New and repeat findings |
The number of reported financial and IT control deficiencies has fallen, but many previously reported findings remain unresolved. |
High risk findings |
Poor systems implementations contributed to the seven high risk internal control deficiencies that could affect agencies. |
Common findings |
Poor IT controls are the most commonly reported deficiency across agencies, followed by governance issues relating to cyber security, capital projects, continuous disclosure, shared services, ethics and risk management maturity. |
2. Information Technology
IT security |
Only two-thirds of agencies are complying with their own policies on IT security. Agencies need to tighten user access and password controls. |
Cyber security |
Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat. |
Other IT systems |
Agencies can improve their disaster recovery plans and the change control processes they use when updating IT systems. |
3. Asset Management
Capital investment |
Agencies report delays delivering against the significant increase in their budgets for capital projects. |
Capital projects |
Agencies are underspending their capital budgets and some can improve capital project governance. |
Asset disposals |
Eleven per cent of agencies were required to sell their real property through Property NSW but didn’t. And eight per cent of agencies can improve their asset disposal processes. |
4. Governance
Governance arrangements |
Sixty-four per cent of agencies’ disclosure policies support communication of key performance information and prompt public reporting of significant issues. |
Shared services |
Fifty-nine per cent of agencies use shared services, yet 14 per cent do not have service level agreements in place and 20 per cent can strengthen the performance standards they set. |
5. Ethics and Conduct
Ethical framework |
Agencies can reinforce their ethical frameworks by updating code‑of‑conduct policies and publishing a Statement of Business Ethics. |
Conflicts of interest |
All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour. |
6. Risk Management
Risk management maturity |
All agencies have implemented risk management frameworks, but with varying levels of maturity. |
Risk management elements |
Many agencies can improve risk registers and strengthen their risk culture, particularly in the way that they report risks to their lead agency. |
This report covers the findings and recommendations from our 2016–17 financial audits related to the internal controls and governance of the 39 largest agencies (refer to Appendix three) in the NSW public sector. These agencies represent about 95 per cent of total expenditure for all NSW agencies and were considered to be a large enough group to identify common issues and insights.
The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2017 cluster financial audit reports tabled in Parliament from October to December 2017.
This new report offers strategic insight on the public sector as a whole
In previous years, we have commented on internal control and governance issues in the volumes we published on each ‘cluster’ or agency sector, generally between October and December. To add further value, we then commented more broadly about the issues identified for the public sector as a whole at the start of the following year.
This year, we have created this report dedicated to internal controls and governance. This will help Parliament to understand broad issues affecting the public sector, and help agencies to compare their own performance against that of their peers.
Without strong control measures and governance systems, agencies face increased risks in their financial management and service delivery. If they do not, for example, properly authorise payments or manage conflicts of interest, they are at greater risk of fraud. If they do not have strong information technology (IT) systems, sensitive and trusted information may be at risk of unauthorised access and misuse.
These problems can in turn reduce the efficiency of agency operations, increase their costs and reduce the quality of the services they deliver.
Our audits do not review every control or governance measure every year. We select a range of measures, and report on those that present the most significant risks that agencies should mitigate. This report divides these into the following six areas:
- Overall trends
- Information technology
- Asset management
- Governance
- Ethics and conduct
- Risk management.
Internal controls are processes, policies and procedures that help agencies to:
- operate effectively and efficiently
- produce reliable financial reports
- comply with laws and regulations.
This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume then illustrates this year’s controls and governance findings in more detail.
Issues |
Recommendations |
1.1 New and repeat findings |
|
The number of internal control deficiencies reduced over the past three years, but new higher-risk information technology (IT) control deficiencies were reported in 2016–17. Deficiencies repeated from previous years still make up a sizeable proportion of all internal control deficiencies. |
Recommendation Agencies should focus on emerging IT risks, but also manage new IT risks, reduce existing IT control deficiencies, and address repeat internal control deficiencies on a more timely basis. |
1.2 High risk findings |
|
We found seven high risk internal control deficiencies, which might significantly affect agencies. |
Recommendation Agencies should rectify high risk internal control deficiencies as a priority |
1.3 Common findings |
|
The most common internal control deficiencies related to poor or absent IT controls. We found some common governance deficiencies across multiple agencies. |
Recommendation Agencies should coordinate actions and resources to help rectify common IT control and governance deficiencies. |
Information technology (IT) has become increasingly important for government agencies’ financial reporting and to deliver their services efficiently and effectively. Our audits reviewed whether agencies have effective controls in place over their IT systems. We found that IT security remains the source of many control weakness in agencies.
Issues | Recommendations |
2.1 IT security |
|
User access administration While 95 per cent of agencies have policies about user access, about two-thirds were compliant with these policies. Agencies can improve how they grant, change and end user access to their systems. |
Recommendation Agencies should strengthen user access administration to prevent inappropriate access to sensitive systems. Agencies should:
|
Privileged access Sixty-eight per cent of agencies do not adequately manage who can access their information systems, and many do not sufficiently monitor or restrict privileged access. |
Recommendation Agencies should tighten privileged user access to protect their information systems and reduce the risks of data misuse and fraud. Agencies should ensure they:
|
Password controls Forty-one per cent of agencies did not meet either their own standards or minimum standards for password controls. |
Recommendation Agencies should review and enforce password controls to strengthen security over sensitive systems. As a minimum, password parameters should include:
|
2.2 Cyber Security |
|
Cyber security framework Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat. |
Recommendation The Department of Finance, Services and Innovation should revisit its existing framework to develop a shared cyber security terminology and strengthen the current reporting requirements for cyber incidents. |
Cyber security strategies While 82 per cent of agencies have dedicated resources to address cyber security, they can strengthen their strategies, expertise and staff awareness. |
Recommendations The Department of Finance, Services and Innovation should:
Agencies should ensure they adequately resource staff dedicated to cyber security. |
2.3 Other IT systems |
|
Change control processes Some agencies need to improve change control processes to avoid unauthorised or inaccurate system changes. |
Recommendation Agencies should consistently perform user acceptance testing before system upgrades and changes. They should also properly approve and document changes to IT systems. |
Disaster recovery planning Agencies can do more to adequately assess critical business systems to enforce effective disaster recovery plans. This includes reviewing and testing their plans on a timely basis. |
Recommendation Agencies should complete business impact analyses to strengthen disaster recovery plans, then regularly test and update their plans. |
Agency service delivery relies on developing and renewing infrastructure assets such as schools, hospitals, roads, or public housing. Agencies are currently investing significantly in new assets. Agencies need to manage the scale and volume of current capital projects in order to deliver new infrastructure on time, on budget and realise the intended benefits. We found agencies can improve how they:
- manage their major capital projects
- dispose of existing assets.
Issues | Recommendations or conclusions |
3.1 Capital investment |
|
Capital asset investment ratios Most agencies report high capital investment ratios, but one-third of agencies’ capital investment ratios are less than one. |
Recommendation Agencies with high capital asset investment ratios should ensure their project management and delivery functions have the capacity to deliver their current and forward work programs. |
Volume of capital spending Most agencies have significant forward spending commitments for capital projects. However, agencies’ actual capital expenditure has been below budget for the last three years. |
Conclusion The significant increase in capital budget underspends warrant investigation, particularly where this has resulted from slower than expected delivery of projects from previous years. |
3.2 Capital projects |
|
Major capital projects Agencies’ major capital projects were underspent by 13 percent against their budgets. |
Conclusion The causes of agency budget underspends warrant investigation to ensure the NSW Government’s infrastructure commitment is delivered on time. |
Capital project governance Agencies do not consistently prepare business cases or use project steering committees to oversee major capital projects. |
Conclusion Agencies that have project management processes that include robust business cases and regular updates to their steering committees (or equivalent) are better able to provide those projects with strategic direction and oversight. |
3.3. Asset disposals |
|
Asset disposal procedures Agencies need to strengthen their asset disposal procedures. |
Recommendations Agencies should have formal processes for disposing of surplus properties. Agencies should use Property NSW to manage real property sales unless, as in the case for State owned corporations, they have been granted an exemption. |
Governance refers to the high-level frameworks, processes and behaviours that help an organisation to achieve its objectives, comply with legal and other requirements, and meet a high standard of probity, accountability and transparency.
This chapter sets out the governance lighthouse model the Audit Office developed to help agencies reach best practice. It then focuses on two key areas: continuous disclosure and shared services arrangements. The following two chapters look at findings related to ethics and risk management.
Issues | Recommendations or conclusions |
4.1 Governance arrangements |
|
Continuous disclosure Continuous disclosure promotes improved performance and public trust and aides better decision-making. Continuous disclosure is only mandatory for NSW Government Businesses such as State owned corporations. |
Conclusion Some agencies promote transparency and accountability by publishing on their websites a continuous disclosure policy that provides for, and encourages:
|
4.2 Shared services |
|
Service level agreements Some agencies do not have service level agreements for their shared service arrangements. Many of the agreements that do exist do not adequately specify controls, performance or reporting requirements. This reduces the effectiveness of shared services arrangements. |
Conclusion Agencies are better able to manage the quality and timeliness of shared service arrangements where they have a service level agreement in place. Ideally, the terms of service should be agreed before services are transferred to the service provider and:
|
Shared service performance Some agencies do not set performance standards for their shared service providers or regularly review performance results. |
Conclusion Agencies can achieve better results from shared service arrangements when they regularly monitor the performance of shared service providers using key measures for the benefits realised, costs saved and quality of services received. Before agencies extend or renegotiate a contract, they should comprehensively assess the services received and test the market to maximise value for money. |
All government sector employees must demonstrate the highest levels of ethical conduct, in line with standards set by The Code of Ethics and Conduct for NSW government sector employees.
This chapter looks at how well agencies are managing these requirements, and where they can improve their policies and processes.
We found that agencies mostly have the appropriate codes, frameworks and policies in place. But we have highlighted opportunities to improve the way they manage those systems to reduce the risks of unethical conduct.
Issues | Recommendations or conclusions |
5.1 Ethical framework |
|
Code of conduct All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour. |
Recommendation Agencies should regularly review their code-of-conduct policies and ensure they keep their codes of conduct up-to-date. |
Statement of business ethics Most agencies maintain an ethical framework, but some can enhance their related processes, particularly when dealing with external clients, customers, suppliers and contractors. |
Conclusion Agencies can enhance their ethical frameworks by publishing a Statement of Business Ethics, which communicates their values and culture. |
5.2 Potential conflicts of interest |
|
Conflicts of interest All agencies have a conflicts-of-interest policy, but most can improve how they identify, manage and avoid conflicts of interest. |
Recommendation Agencies should improve the way they manage conflicts of interest, particularly by:
|
Gifts and benefits While all agencies already have a formal gifts-and-benefits policy, we found gaps in the management of gifts and benefits by some that increase the risk of unethical conduct. |
Recommendation Agencies should improve the way they manage gifts and benefits by promptly updating registers and providing annual training to staff. |
Risk management is an integral part of effective corporate governance. It helps agencies to identify, assess and prioritise the risks they face and in turn minimise, monitor and control the impact of unforeseen events. It also means agencies can respond to opportunities that may emerge and improve their services and activities.
This year we looked at the overall maturity of the risk management frameworks that agencies use, along with two important risk management elements: risk culture and risk registers.
Issues | Recommendations or conclusions |
6.1 Risk management maturity |
|
All agencies have implemented risk management frameworks, but with varying levels of maturity in their application. Agencies’ averaged a score of 3.1 out of five across five critical assessment criteria for risk management. While strategy and governance fared best, the areas that most need to improve are risk culture, and systems and intelligence. |
Conclusion Agencies have introduced risk management frameworks and practices as required by the Treasury’s:
However, more can be done to progress risk management maturity and embed risk management in agency culture. |
6.2 Risk management elements |
|
Risk culture Most agencies have started to embed risk management into the culture of their organisation. But only some have successfully done so, and most agencies can improve their risk culture.
|
Conclusion Agencies can improve their risk culture by:
|
Risk registers and reporting Some agencies do not report their significant risks to their lead agency, which may impair the way resources are allocated in their cluster. Some agencies do not integrate risk registers at a divisional and whole-of-enterprise level. |
Conclusion Agencies not reporting significant risks at the cluster level increases the likelihood that significant risks are not being mitigated appropriately. |
Effective risk management can improve agency decision-making, protect reputations and lead to significant efficiencies and cost savings. By embedding risk management directly into their operations, agencies can also derive extra value for their activities and services.