Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.

Published

Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
 
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
 
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.

 

Parliamentary reference - Report number #260 - released 17 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Government advertising 2015

Government advertising 2015

Premier and Cabinet
Environment
Whole of Government
Compliance
Internal controls and governance
Procurement
Project management

The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.

This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.

 

Parliamentary reference - Report number #253 - released 22 June 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Distributing Legal Aid in New South Wales

Distributing Legal Aid in New South Wales

Justice
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

We found the Commission to be performing well in delivering legal aid services. It has maintained and expanded services despite funding pressures and increasing demand. Overall, we found the Commission’s practices of making people aware of legal issues and its services to be comprehensive. Communication is via brochures, telephone and internet. We also found its processing of applications for legal aid to be sound.

 

Parliamentary reference - Report number #163 - released 13 December 2006

Published

Actions for The Police Assistance Line: Follow-up audit

The Police Assistance Line: Follow-up audit

Justice
Management and administration
Procurement
Service delivery
Workforce and capability

In this 2006 follow-up audit, we found that NSW Police had addressed most of the key areas for improvement we identified in 2003. The contact centre which operates the Police Assistance Line (PAL) is well managed, and has implemented several improvements since our 2003 audit. The centre’s speed in answering and handling PAL calls is better than in 2003. Caller satisfaction with PAL services is high, and NSW Police calculate it releases 200 police for frontline duty. The centre also receives around 4,000 enquiry calls each week further reducing the load on local police.

 

Parliamentary reference - Report number #161 - released 6 December 2006

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006