Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #336 - released 23 June 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Matching skills training with market needs

Matching skills training with market needs

Industry
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Workforce and capability

The NSW Department of Industry targets subsidies towards training programs delivering skills most needed in New South Wales. However, the Department still provides subsidies to qualifications that the market may no longer need, according to a report released by Margaret Crawford, Auditor-General for New South Wales. 

In 2012, governments across Australia entered into the National Partnership Agreement on Skills Reform. Under the National Partnership Agreement, the Australian Government provided incentive payments to States and Territories to move towards a more contestable Vocational Education and Training (VET) market. The aim of the National Partnership Agreement was to foster a more accessible, transparent, efficient and high quality training sector that is responsive to the needs of students and industry. 

The New South Wales Government introduced the Smart and Skilled program in response to the National Partnership Agreement. Through Smart and Skilled, students can choose a vocational course from a list of approved qualifications and training providers. Students pay the same fee for their chosen qualification regardless of the selected training provider and the government covers the gap between the student fee and the fixed price of the qualification through a subsidy paid to their training provider. 

Smart and Skilled commenced in January 2015, with the then Department of Education and Communities having primary responsibility for its implementation. Since July 2015, the NSW Department of Industry (the Department) has been responsible for VET in New South Wales and the implementation of Smart and Skilled. 

The NSW Skills Board, comprising nine part-time members appointed by the Minister for Skills, provides independent strategic advice on VET reform and funding. In line with most other States and Territories, the Department maintains a 'Skills List' which contains government subsidised qualifications to address identified priority skill needs in New South Wales.

This audit assessed the effectiveness of the Department in identifying, prioritising, and aligning course subsidies to the skill needs of NSW. To do this we examined whether:

  • the Department effectively identifies and prioritises present and future skill needs 
  • Smart and Skilled funding is aligned with the priority skill areas
  • skill needs and available VET courses are effectively communicated to potential participants and training providers.

Smart and Skilled is a relatively new and complex program, and is being delivered in the context of significant reform to VET nationally and in New South Wales. A large scale government funded contestable market was not present in the VET sector in New South Wales before the introduction of Smart and Skilled. This audit's findings should be considered in that context.
 

Conclusion
The Department effectively consults with industry, training providers and government departments to identify skill needs, and targets subsidies to meet those needs. However, the Department does not have a robust, data driven process to remove subsidies from qualifications which are no longer a priority. There is a risk that some qualifications are being subsidised which do not reflect the skill needs of New South Wales. 
The Department needs to better use the data it has, and collect additional data, to support its analysis of priority skill needs in New South Wales, and direct funding accordingly.
In addition to subsidising priority qualifications, the Department promotes engagement in skills training by:
  • funding scholarships and support for disadvantaged students
  • funding training in regional and remote areas
  • providing additional support to deliver some qualifications that the market is not providing.

The Department needs to evaluate these funding strategies to ensure they are achieving their goals. It should also explore why training providers are not delivering some priority qualifications through Smart and Skilled.

Training providers compete for funding allocations based on their capacity to deliver. The Department successfully manages the budget by capping funding allocated to each Smart and Skilled training provider. However, training providers have only one year of funding certainty at present. Training providers that are performing well are not rewarded with greater certainty.

The Department needs to improve its communication with prospective students to ensure they can make informed decisions in the VET market.

The Department also needs to communicate more transparently to training providers about its funding allocations and decisions about changes to the NSW Skills List. 

The NSW Skills List is unlikely to be missing high priority qualifications, but may include lower priority qualifications because the Department does not have a robust process to identify and remove these qualifications from the list. The Department needs to better use available data, and collect further data, to support decisions about which qualifications should be on the NSW Skills List.

The Department relies on stakeholder proposals to update the NSW Skills List. Stakeholders include industry, training providers and government departments. These stakeholders, particularly industry, are likely to be aware of skill needs, and have a strong incentive to propose qualifications that address these needs. The Department’s process of collecting stakeholder proposals helps to ensure that it can identify qualifications needed to address material skill needs. 

It is also important that the Department ensures the NSW Skills List only includes priority qualifications that need to be subsidised by government. The Department does not have robust processes in place to remove qualifications from the NSW Skills List. As a result, there is a risk that the list may include lower priority skill areas. Since the NSW Skills List was first created, new additions to the list have outnumbered those removed by five to one.

The Department does not always validate information gathered from stakeholder proposals, even when it has data to do so. Further, its decision making about what to include on, or delete from, the NSW Skills List is not transparent because the rationale for decisions is not adequately documented. 

The Department is undertaking projects to better use data to support its decisions about what should be on the NSW Skills List. Some of these projects should deliver useful data soon, but some can only provide useful information when sufficient trend data is available. 

Recommendation

The Department should: 

  • by June 2019, increase transparency of decisions about proposed changes to the NSW Skills List and improve record-keeping of deliberations regarding these changes
  • by December 2019, use data more effectively and consistently to ensure that the NSW Skills List only includes high priority qualifications
The Department funds training providers that deliver qualifications on the NSW Skills List. Alignment of funding to skill needs relies on the accuracy of the NSW Skills List, which may include some lower priority qualifications.

Only qualifications on the NSW Skills List are eligible for subsidies under Smart and Skilled. As the Department does not have a robust process for removing low priority qualifications from the NSW Skills list, some low priority qualifications may be subsidised. 

The Department allocates the Smart and Skilled budget through contracts with Smart and Skilled training providers. Training providers that meet contractual obligations and perform well in terms of enrolments and completion rates are rewarded with renewed contracts and more funding for increased enrolments, but these decisions are not based on student outcomes. The Department reduces or removes funding from training providers that do not meet quality standards, breach contract conditions or that are unable to spend their allocated funding effectively. Contracts are for only one year, offering training providers little funding certainty. 

Smart and Skilled provides additional funding for scholarships and for training providers in locations where the cost of delivery is high or to those that cater to students with disabilities. The Department has not yet evaluated whether this additional funding is achieving its intended outcomes. 

Eight per cent of the qualifications that have been on the NSW Skills List since 2015 are not delivered under Smart and Skilled anywhere in New South Wales. A further 14 per cent of the qualifications that are offered by training providers have had no student commencements. The Department is yet to identify the reasons that these high priority qualifications are either not offered or not taken up by students.

Recommendation

The Department should:

  • by June 2019, investigate why training providers do not offer, and prospective students do not enrol in, some Smart and Skilled subsidised qualifications 
  • by December 2019, evaluate the effectiveness of Smart and Skilled funding which supplements standard subsidies for qualifications on the NSW Skills List, to determine whether it is achieving its objectives
  • by December 2019, provide longer term funding certainty to high performing training providers, while retaining incentives for them to continue to perform well.
The Department needs to improve its communication, particularly with prospective students.

In a contestable market, it is important for consumers to have sufficient information to make informed decisions. The Department does not provide some key information to prospective VET students to support their decisions, such as measures of provider quality and examples of employment and further education outcomes of students completing particular courses. Existing information is spread across numerous channels and is not presented in a user friendly manner. This is a potential barrier to participation in VET for those less engaged with the system or less ICT literate.

The Department conveys relevant information about the program to training providers through its websites and its regional offices. However, it could better communicate some specific information directly to individual Smart and Skilled training providers, such as reasons their proposals to include new qualifications on the NSW Skills List are accepted or rejected. 

While the Department is implementing a communication strategy for VET in New South Wales, it does not have a specific communications strategy for Smart and Skilled which comprehensively identifies the needs of different stakeholders and how these can be addressed. 

Recommendation

By December 2019, the Department should develop and implement a specific communications strategy for Smart and Skilled to:

  • support prospective student engagement and informed decision making
  • meet the information needs of training providers 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #305 - released 26 July 2018

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.