What this report is about

WestInvest is a $5 billion funding program announced in September 2021 to provide ‘local infrastructure to help communities hit hard by COVID-19’ in 15 local government areas (LGAs) selected by the government. It was divided into three parts: $3 billion for NSW government agency projects; $1.6 billion for competitive grants to councils and community groups; and $400 million for non-competitive grants to councils.

Following the change of government at the 2023 election, the program was renamed the Western Sydney Infrastructure Grants Program. Funding decisions made for the community and local government grants were retained, but multiple funding decisions for the NSW government projects were changed.

The audit objective was to assess the integrity of the design and implementation of the program and the award of program funding.

Findings

The design of the program lacked integrity because it was not informed by robust research or analysis to justify the commitment of public money to a program of this scale.

The then government did not have sufficient regard to the implications for the state's credit rating. A risk to the credit rating arose because the government may have been perceived to be using proceeds from major asset sales to fund new expenditure, rather than pay down its debt.

Decisions about program design were made by the then Treasurer's office without consultation with affected communities. The rationale for these decisions was not documented or made public.

For the NSW government projects, funding allocations did not follow advice from departments. Many funded projects did not meet the objectives of the program.

The two other rounds of the program were administered effectively, except for some gaps in documentation and quality assurance. The program guidelines did not require an equitable or needs-based distribution of funding across LGAs and there was a significant imbalance in funding between the 15 LGAs.

Recommendations

Our recommendations for the administration of future funding programs included:

  • considering whether competitive grants are the best way to achieve the program's purpose
  • completing program design and guidelines before announcements
  • ensuring adequate quality assurance.

We also recommended that when providing advice for submissions by Ministers to Cabinet, agencies should ensure that departmental advice is clearly identified and is distinct from other advice or political considerations.

 

Read the PDF report

Parliamentary reference - Report number #391 - released 28 February 2024

Published

Actions for Effectiveness of SafeWork NSW in exercising its compliance functions

Effectiveness of SafeWork NSW in exercising its compliance functions

Finance
Industry
Health
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about 

This report assesses how effectively SafeWork NSW, a part of the Department of Customer Service (DCS), has performed its regulatory compliance functions for work health and safety in New South Wales. 

The report includes a case study examining SafeWork NSW's management of a project to develop a realtime monitoring device for airborne silica in workplaces. 

Findings 

There is limited transparency about SafeWork NSW's effectiveness as a regulator. The limited performance information that is available is either subsumed within DCS reporting (or other sources) and is focused on activity, not outcomes. 

As a work health and safety (WHS) regulator, SafeWork NSW lacks an effective strategic and data-driven approach to respond to emerging WHS risks. 

It was slow to respond to the risk of respirable crystalline silica in manufactured stone. 

SafeWork NSW is constrained by an information management system that is over 20 years old and has passed its effective useful life. 

While it has invested effort into ensuring consistent regulatory decisions, SafeWork NSW needs to maintain a focus on this objective, including by ensuring that there is a comprehensive approach to quality assurance. 

SafeWork NSW's engagement of a commercial partner to develop a real-time silica monitoring device did not comply with key procurement obligations. 

There was ineffective governance and process to address important concerns about the accuracy of the real-time silica monitoring device. 

As such, SafeWork NSW did not adequately manage potential WHS risks. 

Recommendations 

The report recommended that DCS should: 

  • ensure there is an independent investigation into the procurement of the research partner for the real-time silica detector 
  • embed a formal process to review and set its annual regulatory priorities 
  • publish a consolidated performance report 
  • set long-term priorities, including for workforce planning and technology uplift 
  • improve its use of data, and start work to replace its existing complaints handling system 
  • review its risk culture and its risk management framework 
  • review the quality assurance measures that support consistent regulatory decisions

 

Read the PDF report.

Parliamentary reference - Report number #390 - released 27 February 2024
 

Published

Actions for Flood housing response

Flood housing response

Planning
Whole of Government
Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery
Shared services and collaboration

What this report is about

Extreme rainfall across eastern Australia in 2021 and 2022 led to a series of major flood events in New South Wales.

This audit assessed how effectively the NSW Government provided emergency accommodation and temporary housing in response to the early 2022 Northern Rivers and late 2022 Central West flood events.

Responsible agencies included in this audit were the Department of Communities and Justice, NSW Reconstruction Authority, the former Department of Planning and Environment, the Department of Regional NSW and the Premier’s Department.

Findings

The Department of Communities and Justice rapidly provided emergency accommodation to displaced persons immediately following these flood events.

There was no plan in place to guide a temporary housing response and agencies did not have agency-level plans for implementing their responsibilities.

The NSW Government rapidly procured and constructed temporary housing villages. However, the amount of temporary housing provided did not meet the demand.

There is an extensive waitlist for temporary housing and the remaining demand in the Northern Rivers is unlikely to be met. The NSW Reconstruction Authority has not reviewed this list to confirm its accuracy.

Demobilisation plans for the temporary housing villages have been developed, but there are no long-term plans in place for the transition of tenants out of the temporary housing.

Agencies are in the process of evaluating the provision of emergency accommodation and temporary housing.

The findings from the 2022 State-wide lessons process largely relate to response activities.

Audit recommendations

The NSW Reconstruction Authority should:

  • Develop a plan for the provision of temporary housing.
  • Review the temporary housing waitlist.
  • Determine a timeline for demobilising the temporary housing villages.
  • Develop a strategy to manage the transition of people into long-term accommodation.
  • Develop a process for state-wide recovery lessons learned.

All audited agencies should:

  • Finalise evaluations of their role in the provision of emergency accommodation and temporary housing.
  • Develop internal plans for implementing their roles under state-wide plans.

Read the PDF report

Parliamentary reference - Report number #389 - released 22 February 2024

Planned

Actions for The NSW Government's international offices

The NSW Government's international offices

Industry

Most Australian state and territory governments have trade and investment offices located overseas, which operate alongside the Australian government's international Austrade offices. The NSW Government has an international network, with offices and staff located in the Americas, Greater China, India, the Middle East, North Asia, ASEAN, and the UK, Europe and Israel. These offices aim to attract international businesses to NSW and assist NSW-based businesses to operate internationally.

This audit may examine areas including the effectiveness of international offices in achieving the NSW Government's trade and investment goals, and the accountability and governance of the offices.

Planned

Actions for Regional Digital Connectivity program

Regional Digital Connectivity program

Environment
Industry
Planning

Audit background

According to the Department of Regional NSW, approximately $500 million dollars has been committed to the Regional Digital Connectivity Program (RDCP) through the Snowy Hydro Legacy Fund. The RDCP aims to improve mobile, internet and digital services for rural and regional areas of NSW. Of this funding, over $300 million was allocated to improving mobile phone coverage in regional NSW through investment in shared and multi-carrier mobile infrastructure. A further $100 million in funding was allocated to internet connectivity which aims to provide fast and reliable internet connectivity for rural and regional communities, prioritising areas currently on a satellite internet service.

Audit objective

This audit will assess if the Department of Regional NSW is effectively administering the Regional Digital Connectivity Program (RDCP) to meet program objectives. The includes considering how effectively the Department of Regional NSW identifies priority areas, distributes funding in line with program objectives, and measures the performance of the RDCP.

Estimated tabling period

June 2024

Agencies audited

Department of Regional NSW

Published

Actions for Regulation of public native forestry

Regulation of public native forestry

Environment
Industry
Compliance
Management and administration
Regulation
Risk

What this report is about

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that manages over two million hectares of public native forests and plantations supplying timber to sawmills across NSW.

The NSW Environment Protection Authority (EPA) is responsible for regulating the native forestry industry in NSW.

FCNSW must comply with Integrated Forestry Operations Approvals (IFOAs), which set out rules for how timber harvesting may occur.

Most harvesting is undertaken under the Coastal IFOA, which commenced in 2018.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

What we found

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations.

While FCNSW undertakes monitoring of its contractors, it does not do so consistently and does not target its monitoring activities on a risk basis.

FCNSW has largely fulfilled mandatory Coastal IFOA training requirements, but has not yet trained other staff who would also benefit from the training.

Contractor compliance appears to be improving, but there are gaps and inconsistencies in FCNSW's documentation of this.

FCNSW is not measuring its overall compliance to determine how it is tracking against its target.

The EPA undertakes proactive inspections of Coastal IFOA harvesting operations on a risk basis. However, it does not assess the risk at harvest sites covered by other IFOAs.

Most EPA compliance staff have received basic training, but few have received more advanced training required to effectively undertake forestry inspections.

Some EPA offices do not have the necessary equipment to undertake forestry inspections.

The EPA and FCNSW are not implementing all elements of a Memorandum of Understanding that aims to promote a cooperative relationship between the agencies.

What we recommended

The report made recommendations to FCNSW which aim to improve:

  • staff training
  • consistency of compliance reviews and data capture
  • targeting of compliance activities
  • measurement of performance.

The report made recommendations to the EPA which aim to improve:

  • risk-assessments
  • staff training
  • staff equipment.

The report also recommended that FCNSW and EPA should fully implement their Memorandum of Understanding.

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that supplies timber to sawmills in New South Wales, including timber harvested from public native forests. FCNSW is responsible for the management of around two million hectares of public native forests and plantations. Around half the area of native forests is permanently set aside for conservation.

Public native forestry is regulated through the Forestry Act 2012, Biodiversity Conservation Act 2016, Protection of the Environment Operations Act 1997 and associated regulations. Under the Forestry Act 2012, the objectives of FCNSW include, where its activities affect the environment, to conduct its operations in compliance with the principles of ecologically sustainable development contained in section 6(2) of the Protection of the Environment Administration Act 1991. This involves the integration of social, economic and environmental considerations in decision-making processes.

In undertaking its native forestry operations, FCNSW must comply with Integrated Forestry Operations Approvals (IFOA), issued jointly by the Minister for the Environment and the Minister for Agriculture, which set out rules to protect species and ecosystems where timber harvesting is occurring, and aim to ensure forests are managed in an ecologically sustainable way. FCNSW must also ensure that its contractors undertake forestry operations in line with IFOAs. The Coastal IFOA, developed in 2018, consolidated the four IFOAs for the Eden, Southern, Upper and Lower North East coastal regions of New South Wales into a single IFOA. The other three current IFOAs are Brigalow Nandewar, South Western Cypress and Riverina Redgum (the Western IFOAs).

The NSW Environment Protection Authority (EPA) is responsible for regulating native forestry in New South Wales. Under the Protection of the Environment Administration Act 1991, one of the objectives of the EPA is to protect, restore and enhance the quality of the environment in New South Wales, having regard to the need to maintain ecologically sustainable development. This includes monitoring FCNSW’s compliance with IFOA conditions, including by maintaining and enforcing a compliance program.

The Coastal IFOA also introduced a new structure and regulatory approach for IFOAs, establishing outcomes, conditions and protocols. The conditions set mandatory actions and controls intended to protect threatened plants, animals, habitats, soils and water. The protocols, referenced in the conditions, set out additional enforceable actions and controls intended to support the effective implementation of the conditions.

Public native forestry is the largest component of hardwood supply in New South Wales. The 2019–20 bushfires had a major impact on regional communities, and large areas of native forest. This heightened environmental risks and challenges in public native forestry. Five million hectares of New South Wales was impacted, including more than 890,000 hectares of native State Forests. This is over 40% of the coastal and tablelands native State Forests in New South Wales.

In addition to effective compliance activities, the success of the regulatory approach to public native forestry operations depends on how wood supply yields are modelled, and ensuring that harvested volumes do not exceed these yields. This is of particular importance in areas where forests have been severely damaged by fire. This audit did not consider sustainable yields. Recent reviews of this include an independent review of the FCNSW sustainable yield model and a Natural Resources Commission review in 2021.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

Conclusion

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations at the corporate level and for each harvest site. However, there are deficiencies in FCNSW’s compliance approach. While FCNSW undertakes monitoring of its contractors in a number of ways, it does not consistently monitor compliance across its contractors and does not target its monitoring activities on a risk basis. This increases the risk that non-compliant practices will not be identified, potentially leading to environmental harm.

FCNSW has a compliance strategy and program that sets out its compliance obligations and how they will be managed. FCNSW’s Compliance Policy outlines compliance requirements, actions to ensure compliance, and responsibilities for staff, supervisors, senior management and board members. FCNSW also has a compliance monitoring system manual that outlines its monitoring program, and its risk-assessment and incident reporting procedures. These corporate documents set out FCNSW’s overall approach to managing compliance.

Harvesting in State Forests is undertaken by contractors or sub-contractors. FCNSW provides training to its staff and contractors and undertakes monitoring to identify contractor compliance with relevant requirements through a variety of means, including its quality assurance assessment (QAA) program. FCNSW also communicates compliance obligations to contractors in harvest plans.

FCNSW is not undertaking its monitoring activities on a risk basis. The frequency of contractor supervision is inconsistent and is not tied to the contractor’s past performance, meaning that monitoring resources are not necessarily being targeted at the areas of highest -risk.

FCNSW also does not target its QAAs on a risk basis. FCNSW does not have procedures for how QAAs should occur outside the North Coast region. QAAs are conducted inconsistently, with some reviews occurring in only part of the harvest site while others cover the whole harvest site. In addition, some QAAs do not meet FCNSW’s minimum standards. FCNSW’s record keeping of QAAs is also inconsistent, making it difficult to determine true levels of compliance and the cause of identified potential non-compliances.

In addition, FCNSW does not collate and analyse the results of its compliance monitoring to target its compliance audits. Undertaking these audits on a risk basis would allow FCNSW to apply its resources to the highest-risk harvest sites and contractors.

The EPA identifies native forestry as a high priority regulatory activity and undertakes proactive inspections of Coastal IFOA harvest sites on a risk basis. However, the EPA does not assess the risk at Western IFOA harvest sites, leaving a significant gap in its inspection regime. This means that the EPA may not be inspecting all high-risk harvest sites to ensure compliance with regulations across those sites. The EPA has started to train more of its staff in conducting forestry inspections, but it currently has a limited number of trained and experienced staff to undertake this work.

The EPA has developed a Regulatory and Compliance Priorities Statement 2022–23 which identifies native forestry as a key risk. This statement identifies that forestry is a priority area for its compliance activities because of the increased environmental risk and sensitivity in forests following the 2019–20 bushfires. A divisional plan for its regulatory operations contains specific actions for forestry, including ensuring that the EPA has a consistent approach to recording regulatory actions undertaken and identifying priority areas for assurance over State Forests.

As part of its compliance activities, the EPA responds to complaints received, or reports of non-compliance, across all four IFOA areas and also carries out proactive inspections in the Coastal IFOA area. To guide these inspections, the EPA determines the level of risk posed by each harvest site in the Coastal IFOA area using information it gathers from FCNSW. The EPA prioritises inspections of sites rated as high and medium-risk, but the EPA has not undertaken risk-assessments for the three Western IFOAs. By not determining the risks in these areas, the EPA does not have assurance that it is checking FCNSW compliance with regulations across all high-risk sites.

Most EPA staff have basic training in forestry matters, but few staff have the more advanced training required to effectively undertake forestry inspections. In addition, not all EPA officers have access to the technology required to undertake forestry inspections, such as internet-enabled tablets and specialised tapes for measuring tree diameter. This limits the EPA’s ability to determine the level of compliance with regulations and respond effectively to instances of environmental harm in relation to public native forestry.

The Coastal IFOA does not contain provisions which allow the EPA to unilaterally restrict forestry activities in the aftermath of a catastrophic event such as the 2019–20 bushfires. Following the bushfires, FCNSW approached the EPA and asked for additional site-specific operating conditions (SSOC) at some locations to assist it in maintaining compliance. The SSOCs were issued by the EPA and FCNSW was required to carry out forestry operations in accordance with the SSOCs at relevant harvest sites. These SSOCs were in place for 12 months. After a year, FCNSW decided not to renew this approach with the EPA, but implemented its own voluntary measures during harvesting operations. Unlike the SSOCs, the EPA was unable to undertake enforcement activities for breaches of voluntary measures.

Appendix one – Responses from agencies
Appendix two – About the audit
Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #382 - released 22 June 2023

Published

Actions for Bushfire recovery grants

Bushfire recovery grants

Environment
Industry
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

The Bushfire Local Economic Recovery (BLER) program was created after the 2019–20 bushfires, and commits $541.8 million to bushfire affected areas in New South Wales. It is co-funded by the Commonwealth and NSW governments.

This audit assessed how effectively the Department of Regional NSW (the department) and Resilience NSW administered rounds one and two of the BLER program. These rounds were:

  • Round one: early co-funding, split between two streams:
    • ­Fast-Tracked projects 
    • ­Sector Development Grants (SDG)
  • Round two: open round.

What we found

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the BLER. 

The administration process lacked integrity, given it did not have sufficiently detailed guidelines and the assessment process for projects lacked transparency and consistency. 

At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. The department advises that some of the projects excluded were subsequently funded from other programs. 

This threshold resulted in a number of shortlisted projects in areas highly impacted by the bushfires being excluded, including all shortlisted projects located in Labor Party-held electorates.

The department's administration of the SDG stream had a detailed and transparent assessment process. However, conflicts of interest were not effectively managed. 

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework. Some weaknesses in the approach to conflicts of interest remained.

What we recommended

The Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance 
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds 
  5. documents all key decisions and approvals in line with record keeping obligations.

This audit assessed how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the Bushfire Local Economic Recovery (BLER) program.

As noted in this report, Resilience NSW was involved in the set-up and ongoing administration and monitoring of the BLER program. During the audited period, Resilience NSW was tasked with working with the Department of Regional NSW to create program objectives, guidelines and criteria. Their role also involved liaising with the Commonwealth Government, which provided co-funding for the program. Resilience NSW also had an ongoing role in quality assurance and compliance to ensure agencies administering disaster assistance did so in accordance with relevant guidelines. On 16 December 2022, the NSW Government abolished Resilience NSW.

Our work for this performance audit was completed on 3 November 2022, when we issued the final report to the two audited agencies. The audit report does not make specific recommendations to Resilience NSW. On 24 November 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

During the 2019–20 bushfire season, New South Wales experienced 11,774 fire incidents, burning 5.5 million hectares of the state. There were 26 fatalities and 2,476 homes destroyed. The agriculture sector was heavily impacted with 601,858 hectares of pasture damaged.

Due to the widespread impacts of these fires on the state, the NSW and Commonwealth governments committed $4.4 billion toward bushfire response, recovery, and preparedness. This included the establishment of the Bushfire Local Economic Recovery (BLER) program, with $541.8 million committed to support job retention and creation in areas impacted by bushfires. The program also aims to strengthen community resilience and reduce the impact of future natural disasters. The BLER program is co-funded, with the Commonwealth and NSW governments funding 50% each.

The BLER program is comprised of three funding rounds:

  • round one early co-funding, split between
    • Fast-Tracked projects
    • Sector Development Grants (SDG)
  • round two: open round
  • round three: final projects and initiatives.

Resilience NSW was involved in setting up the BLER program and the Department of Regional NSW (the department) is responsible for administering it. The Commonwealth National Recovery and Resilience Agency must also endorse any projects proposed by the NSW Government for funding as part of the funding agreement between the State and Commonwealth governments.

Successful projects under the SDG stream were announced in September 2020 and projects funded through the Fast-Tracked stream were announced in October 2020. Round two (the open round) was administered after these two streams and successful projects were announced in June 2021.

The Department of Premier and Cabinet established the 'Good Practice Guide to Grants Administration' (the Good Practice Guide) in 2010 to assist the NSW Government in ensuring grants administration was performed consistently across all NSW Government grants programs. Compliance with the Good Practice Guide was not compulsory, but provided an outline of best practice covering the entire lifecycle of a grants program. This guide was in place at the time these grants were designed and administered.

The design and delivery of round one of the program occurred quickly, as part of the response to the 2019–20 bushfires, and was responding to a request from the Commonwealth Government for rapid project identification.

The objective of this audit was to assess how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the BLER program. Round three was excluded from this audit because it had not been announced at the time of the audit.

We addressed this objective by examining whether the audited agencies:

  • effectively planned administration of the BLER program and established appropriate guidelines
  • implemented an effective assessment process for the BLER program
  • are effectively monitoring implementation of projects and program outcomes.

Conclusion

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the Bushfire Local Economic Recovery program. The administration process lacked integrity, given it did not have sufficiently detailed guidelines, and the assessment process for projects lacked transparency and consistency.

There were significant gaps in the documentation of decision-making throughout this funding stream. At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. This threshold was applied without a documented reason and was not part of the program guidelines. The department advises that some of the projects excluded through application of the threshold were subsequently funded from other programs.

The department's administration of the Sector Development Grants stream had a detailed and transparent assessment process. That said, conflicts of interest were not effectively managed, and the department did not effectively engage with stakeholders during the grants process.

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework that it followed throughout. The department also implemented probity arrangements in the open round, although some weaknesses in the department's approach to conflicts of interest remained.

Fast-Tracked stream

Following requests from the Commonwealth Government in May and June 2020 to identify projects rapidly and as soon as practical, the department used an expedited process to identify relevant projects that had applied for other grants programs but had not received funding or which were identified as local priority projects. The department developed a set of guidelines for the Fast-Tracked stream based on draft Commonwealth funding criteria, but the department's guidelines lacked sufficient detail to ensure transparent and consistent decision-making. The guidelines also did not contain detailed information on how the assessment and approval processes would work. The department did not implement conflict of interest declarations for staff involved in the assessment process.

The assessment process implemented for the Fast-Tracked stream deviated from the guidelines. For example, the guidelines did not set out a role for the then Deputy Premier or his office in the assessment process, but the Deputy Premier's office played a key role in project selection. At the direction of the Deputy Premier's office, a $1 million minimum threshold, not mentioned in the guidelines, was applied to projects, below which, projects would not be funded. This resulted in a number of shortlisted projects in areas highly impacted by the bushfires, including all shortlisted projects located in Labor Party-held electorates, being excluded without a rationale being documented at the time. The department advised that some of these projects were subsequently funded through other funding streams.

The department's assessment process was inconsistent, poorly documented and lacked transparency. The department initially identified 445 potential projects through consultation with councils and through identifying projects that had been unsuccessful for other grant programs. The department only assessed 164 of these 445 projects for funding against the criteria in the guidelines. The department did not document the rationale for not assessing the remaining 281 projects against the criteria. The department also sought advice from Public Works Advisory (PWA) on whether projects could commence within six months, which was an eligibility criterion for the Fast-Tracked stream. PWA were only asked to assess 25 of the 445 projects, of which 19 were funded through the Fast-Tracked stream. The department also did not consistently follow PWA's advice and funded projects which PWA had advised were unable to commence within six months, which was not in line with the guidelines.

The department monitors 21 of the 22 Fast-Tracked projects on a quarterly basis to ensure projects are on track. Resilience NSW is responsible for the remaining project and does not monitor this on a quarterly basis but has established a project control group that performs a similar function. The agencies advised that this project is being transitioned to the department's management.

Sector Development Grants (SDG)

The department designed and published guidelines for the SDG stream. The guidelines largely align with the Department of Premier and Cabinet's 'Good Practice Guide to Grants Administration', although they could have been strengthened by including more detail on the eligibility of projects and the role of cost benefit analyses in the assessment process. The guidelines included a detailed and transparent assessment process which the department largely followed.

There were gaps in the administration of the SDG stream assessment process. The department did not effectively manage conflicts of interest as it did not ensure all required conflict of interest forms were completed and some forms were completed after the assessment process was finalised. The department also advised that the final version of the conflict of interest register, which contained the declarations for the SDG stream, was lost during a record management system change. The department did not develop guidance for communicating with stakeholders for the SDG stream. Feedback was received from industries which had been excluded from the SDG stream, relaying their concerns, and requesting a broader range of agribusiness sectors be considered for eligibility. A communications plan or strategy could have incorporated guidance on engaging agribusiness stakeholders during the planning stages of the stream, ensuring they were aware of the rationale for the eligible industries selected.

The majority of SDG funding went to areas highly impacted by the bushfires, although some highly impacted areas received less funding than lower impacted areas, and there is no clear reason for this.

The department does not monitor SDG projects on a quarterly basis to ensure that they remain on track but it ensures it has sufficient evidence that milestones have been completed before making funding payments.

Open round

The department designed and implemented a clearly documented and detailed assessment process for the open round. There were some areas where the process could have been improved, for example, the published guidelines did not set out the role of the former Deputy Premier or include reference to consultation with members of Parliament (MP) as part of the process, despite the fact that MPs were consulted as part of this round.

The department improved its management of conflicts of interest compared to the Fast-Tracked and SDG streams by maintaining a conflict of interest register, though not all conflict of interest declarations were collected. The department also developed a communications plan which led to improvements in stakeholder engagement.

One of the purposes of the open round was to distribute funding to local government areas (LGA) which did not receive funding through the Fast-Tracked stream. This intention was not outlined in the guidelines for this funding stream. The majority of funding from the open round went to LGAs which had been highly impacted by the bushfires.

The department monitors the open round projects on a quarterly basis to ensure that they are on track.

1. Recommendations

To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds
  5. documents all key decisions and approvals in line with record keeping obligations.

Stage one of the BLER program consisted of early co-funded projects valued at a total of $180 million. This included 22 Fast-Tracked priority projects valued at a total of $107.8 million. The purpose of these projects was to deliver immediate and significant economic impacts to high and moderate bushfire-impacted areas.

A timeline of key dates may be found at Exhibit 5.

Fifty-two projects worth a total of $73.2 million were funded through the SDG stream. One grantee withdrew their project from the stream in early 2021, leaving a total of 51 projects (of which 49 are co-funded with the Commonwealth Government).

A timeline of key dates may be found at Exhibit 9.

The department distributed $283 million to 195 successful projects as part of the open round of the BLER program.

A timeline of key dates may be found at Exhibit 11.

The department entered into funding deeds with successful applicants

The Good Practice Guide advises that the agency administering a grant should enter into a formal agreement with each grant recipient which sets out the arrangements under which a grant is provided, received, managed and acquitted. Across all three streams, the department sent out a letter of offer to successful project managers to let them know that they had been successful in receiving funding, and then entered into funding deeds with grantees. The one exception was the project that RNSW managed, discussed below.

The reviewed funding deeds were signed by department staff with the appropriate level of delegation. They contained an appropriate level of information and key clauses that would allow the department to monitor the progress of the grant to ensure its completion as agreed with the grantee. The reviewed funding deeds contained key information, including:

  • total value of the grant
  • key deliverables at each milestone
  • expected completion date of both the overall project and each milestone
  • reporting requirements, including provisions to allow the department to request relevant information
  • variation procedures.

The department only makes payments after confirming that milestones have been reached

The department has provided payments to grantees only after they could demonstrate that they had completed the agreed milestone. To ensure each milestone has been completed, the department requires grantees to provide evidence that they have fulfilled the milestone. Types of evidence provided includes photographs and invoices. Where the grantee provides insufficient evidence to the department, the department follows-up with the grantee to ensure that enough information is provided to justify the milestone payment.

The department also plans to undertake site visits of projects at select milestones and at the completion of most projects. The department has undertaken a risk assessment of each SDG and open round project, and uses this risk assessment to determine the number of milestones for the project, as well as the number of site visits that the department will undertake. Fast-Tracked projects all had PWA providing either project management or assurance and as such oversight is being provided through that mechanism. The milestones and site visits at each level of risk can be seen in Exhibit 15 for SDG and Exhibit 16 for open round.

Exhibit 15: Milestones and site visits for each level of risk - SDG
Risk rating Milestones Site visits
Low Two Zero
Medium Three One
High Four Two
Source: Department of Regional NSW.
 
Exhibit 16: Milestones and site visits for each level of risk - open round
Risk rating Milestones Site visits
Low Three One
Medium Four Two
High Five Three
 Source: Department of Regional NSW.

The department does not monitor quarterly progress for SDG grants

As part of the LER framework, the department reports to the Commonwealth every quarter on the status and financials of each project, including whether there are any risks to project delivery and the mitigations in place for those risks. For projects funded through the Fast-Tracked stream and the open round, the department collects quarterly progress reports from the grantees. These progress reports allow the department to determine if there are project risks, which can then be reported to the Commonwealth. The progress reports also allow the department to determine if a milestone is likely to be met within the next quarter or whether a project variation may be needed.

While the department monitors projects funded through the Fast-Tracked stream and the open round on a quarterly basis, there is no quarterly monitoring of progress for projects funded through the SDG stream. The SDG funding deeds do not include a provision to require quarterly reporting to the department. The department only collects progress reports from grantees when the grantee reports that it has completed a milestone. Quarterly monitoring of the SDG stream would allow the department to determine if projects require corrective action.

Resilience NSW is not collecting quarterly reports for the Fast-Tracked grant it is responsible for administering

One of the projects funded through the Fast-Tracked stream was the rebuilding of three local halls across two LGAs, for a total value of $3 million. RNSW is responsible for managing this grant and entered into funding deeds with the relevant councils. It is not documented why RNSW is responsible for these funding deeds rather than the department, which is the signatory for all of the other Fast-Tracked stream funding deeds. RNSW advised it was due to the responsible RNSW Director having a strong working relationship with the relevant councils.

The funding deeds which RNSW signed with the relevant councils set out a requirement that the councils would report on this project to RNSW every quarter. The second milestone of each of these projects involved the submission of a quarterly report. However, RNSW was unable to provide evidence that it carried out this monitoring of the project. At the time of the audit, no second milestone payment had been made. Undertaking quarterly monitoring would provide RNSW with assurance that the money is being expended for the proper purpose and whether the projects will be completed by the target date.

RNSW and the relevant councils developed project control groups for each project, which allows it to monitor the implementation of the projects. PWA is also represented on these project control groups and provides an advisory role in the implementation of the projects.

RNSW and the department advised that responsibility for this project will be transitioned to the department and it will be monitored on a quarterly basis, in line with the other Fast-Tracked projects.

The department has a consistent approach to validating variations

The department's funding deeds with grantees allow for the variation of contracts at the department's discretion after the grantee has written to the department. It is important for the department to consider the impact of any project variation request on the overall program objectives, because a project which costs more than was originally planned or which takes additional time may put at risk the objectives of the BLER program. To ensure that requests for variation are handled consistently and appropriately, the department's Grants Management Office (GMO) has developed a process document which applies to variation requests across the BLER program.

For the grants reviewed as part of this audit, the GMO applied this variation process consistently and has documented the outcomes. Larger variations are reviewed at a higher level of delegation and sign-off. To determine whether a variation is accepted, the GMO considers the following factors:

  • consistency with BLER program objectives
  • delivery within the timeframes of the BLER program
  • eligibility under the BLER program guidelines
  • financial viability to deliver within the requested budget.

The department is preparing multiple evaluations, but it has delayed its process evaluation

When developing round one of the BLER program, the department developed an evaluation plan. A total of $1.1 million has been reserved for conducting process, outcome, and economic evaluations of the BLER program and two other bushfire recovery grant programs.

To assist with evaluating program outcomes and economic impact, the department is planning a post-completion survey in 2023–24. This timeline will allow most projects to be completed and enough time for project outcomes to be realised. The department advised that the data collected through this survey would allow the department to determine whether the BLER program has achieved its objectives, as it includes information such as the number of jobs created through each project.

The process evaluation was initially planned for March to June 2021. This would have aligned with the announcement of the open round funding and would have allowed for the learnings from rounds one and two of the BLER program to be applied to the development of round three. However, the department did not conduct this evaluation in a timely way. The department advised that this was because funding deed negotiations were still ongoing, and the department was waiting for 50% of funding deeds to be signed. Given this, the department was not in a position to commence its process evaluation. In December 2021, the department revised its evaluation plan and advised that it commenced its process evaluation in April 2022. It is unlikely that this will allow time for the department to apply learnings to round three, which is currently underway.

Appendix one – Responses from agencies

Appendix two – BLER program distribution

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #373 - released 2 February 2023

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Planned

Actions for NSW’s Implementation of Closing the Gap

NSW’s Implementation of Closing the Gap

Premier and Cabinet

The NSW Premier signed the new National Agreement on Closing the Gap on behalf of New South Wales in July 2020. The objective of the Agreement is to overcome the entrenched inequality faced by Aboriginal and Torres Strait Islander peoples so that their life outcomes are equal to those of all Australians. The NSW Government and NSW Coalition of Aboriginal Peak Organisations developed an implementation plan for 2021–22 which sets out five 'priority reform areas' and outlines the approach to achieving improvements in each of these. Aboriginal Affairs NSW, a unit within the Department of Premier and Cabinet, is leading this work.

This audit will focus on Aboriginal Affairs NSW’s approach to, and progress in implementing, the National Agreement on Closing the Gap. This may include its approach to partnerships and communication, governance and accountability for outcomes.

Published

Actions for NSW planning portal

NSW planning portal

Planning
Industry
Environment
Local Government
Information technology
Project management
Risk

What the report is about

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal).

Using the portal, relevant planning activities can be carried out online, including all stages of development applications.

The portal has been developed under three separate business cases in 2013, 2014 and 2020.

In late 2019, the government mandated the use of the portal for all development applications. This decision took effect across 2020–21.

This audit assessed the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. 

What we found

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information, and allow them to prepare and submit development applications online.

Shortcomings in the department's initial planning and management of the program led to a significant time overrun. It has taken the department longer and cost significantly more to implement the portal than first anticipated. 

In recent years the department has improved the planning, implementation and governance of the ePlanning program, resulting in improved delivery of the portal’s core functions.

The department now has a clear view of the scope necessary to finalise the program, but has not yet published the services it plans to implement in 2022 and 2023.

Mandating the use of the portal for all development applications changed the program's strategic risk environment and required the department to work more closely with a cohort of stakeholders, many of whom did not want to adopt the portal.

Despite this change, the department kept its overall delivery approach the same.

While implementation of the portal has delivered financial benefits, the department has overestimated their value.

The Department has only reported benefits since 2019 and has not independently assured the calculation of benefits.

What we recommended

By December 2022, the department should:

  • publish a roadmap of the services it expects to release on the portal across 2022 and 2023
  • update its ePlanning program assumptions, benefits targets and change management approach to reflect the government's decision to mandate the use of the portal for all stages of a development application
  • independently assure and report publicly the correct calculation of ePlanning program benefits.

Fast facts

  • 10 years taken to implement the portal when completed
  • 3 years longer than initially planned to implement the portal
  • $146m capital expenditure on the portal when completed
  • $38.5m more spent than planned in the business cases.

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal, or the planning portal). The department defines the portal as an online environment where community, industry and government can work together to better understand and meet their obligations under the Environmental Planning and Assessment Act 1979 (NSW). Using the portal, relevant planning activities can be carried out online throughout New South Wales. This includes, but is not limited to:

  • applying for and gaining planning approval
  • applying for and gaining approval for building works, sub-dividing land and similar activities
  • issuing occupancy and other certificates.

The portal has been developed under three separate business cases. The first business case in 2013 led to the creation of a central portal, which made planning information available to view by planning applicants and allowed some planning applications to be lodged and tracked online.

Under a second business case prepared in 2014, the department set out to improve and widen the functions available via the portal. The department prepared a third business case in 2020 to fund further improvements to the portal over the period July 2020 to June 2023. The third business case also extended the portal's functions to support the building and occupation stages of the planning cycle.

In late 2019, the government mandated the use of the portal for all stages of development applications. This decision took effect across 2020–21 and applied to all councils as well as certifiers and others involved in the planning process.

The objective of this performance audit was to assess the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. We investigated whether:

  • delivery of the NSW planning portal was planned effectively
  • sound governance arrangements are in place to ensure effective implementation of the program
  • users of the NSW planning portal are supported effectively to adopt and use the system.
Conclusion

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information and allow them to prepare and submit development applications online. Implementation was initially hindered by deficiencies in planning and it has taken the department significantly longer and cost significantly more to implement the portal than first anticipated. While the portal's implementation has delivered financial benefits, the department has overestimated their value. As a result, the department cannot yet demonstrate that the portal has achieved overall financial benefits, relative to its costs.

In the first two years of the ePlanning program, the department delivered a portal that allowed planners, developers, certifiers and the public to view important planning information. However, the department found the delivery of a second, transactional version of the portal in 2017 to be much more challenging. This version was intended to offer more integrated information and allow development applications to be submitted and managed online. The department did not rollout this version after a pilot showed significant weaknesses with the portal's performance. A subsequent review found that this was partly because the department did not have a clear view of the portal’s role or the best way to implement it. In recent years the department has improved the planning, implementation and governance of the ePlanning program resulting in improved delivery of the portal’s core functions.

By the time the program reaches its scheduled completion in 2023, it will have taken the department ten years and around $146 million in capital expenditure to implement the portal. This will be significantly longer and more expensive than the department originally expected. This overrun is partly due to an increased scope of services delivered through the portal and an initial under-appreciation of what is involved in creating a standard, central resource such as the portal. The department also experienced some significant implementation difficulties – which saw the transactional portal discontinued after it was found to be not fit for purpose. Following this, the department re-set the program in 2017–18 and re-planned much of the portal's subsequent development.

In November 2019, the New South Wales Government decided to mandate the use of the portal for all stages of development applications by the end of 2020–21. The department had previously planned that the portal would be progressively adopted by all councils and other stakeholders over the five years to 2025. The decision to mandate the portal's use for all development applications brought forward many of the portal's benefits as well as the challenges of its implementation. The department did not change its overall delivery approach in response to the changed risks associated with the government's decision to mandate use of the portal.

The current version of the portal has given the department more timely and comprehensive planning information and has helped New South Wales to provide continuous planning services during COVID-19 lockdowns, which interrupted many other public functions. The portal has also delivered financial benefits, however the department has not independently assured benefits calculations carried out by its consultant, and the reported benefits are overstated. In addition, some stakeholders report that the portal is a net cost to their organisation. This has included some certifiers and some councils which had implemented or had started to implement their own ePlanning reforms when use of the portal was mandated in 2019. The department now needs to address the issues faced by these stakeholders while continuing to deliver the remaining improvements and enhancements to the portal. Over the remaining year of the program, it will be critical that the department focuses on the agreed program scope and carefully evaluates any opportunities to further develop the portal to support future planning reforms.

This part of the report sets out how:

  • the ePlanning program has been planned and delivered
  • users of the portal have been supported
  • the program has been governed.

This part of the report sets out the ePlanning program's:

  • expected and reported financial benefits
  • calculation of financial benefits.

In 2019, the department increased its expectations for net financial benefits

The department's three ePlanning business cases each forecast substantial financial benefits from the implementation of the planning portal. The department expected that most financial benefits would flow to planning applicants due to a quicker and more consistent planning process. It also expected that government agencies and councils would benefit from the portal.

Exhibit 6: Summary of the financial benefits originally expected
  Business case 1
($ million)
Business case 2
($ million)
Business case 3
($ million)
Total
($ million)
Benefits 90.0 44.3 270.9 405.2
Costs 43.3 29.4 89.8 162.5
Net benefits 46.7 15.0 181.1 242.7

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for business case 1, 2 and 3 amounts are expressed in 2013, 2015 and 2019 dollars respectively. All amounts are discounted at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

In 2019 the department commissioned a review to explore opportunities to better identify, monitor and realise the benefits of the ePlanning program. Using this work, the department updated the expected benefits for business cases 1 and 2 to take account of:

  • errors and miscalculations in the original benefits calculations
  • slower delivery of the portal and changes to the take-up of portal services by councils
  • changes to the services supported by the portal.
Exhibit 7: Summary of the financial benefits expected for business case 1 and 2 after the 2019 update
  Original business case 1 and 2 (combined)
($ million)
New business case 1 and 2 (combined)
($ million)
Benefits 134.3 210.6
Costs 72.7 96.3
Net benefits 61.7 114.3

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for the original business case 1 and 2 are expressed in 2013 and 2015 dollars respectively. The new combined amount is expressed in 2019 dollars. All amounts are discounted or inflated at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

Reported benefits significantly exceed the current targets

In September 2021, the department reported that the program had achieved $334 million of benefits over the three financial years up to June 2021 plus the first two months of 2021–22. These reported benefits were significantly higher than expected. 

Exhibit 8: Reported financial benefits from the ePlanning program
  2018–19
($ million)
2019–20
($ million)
2020–21
($ million)
July to August 2021
($ million)
Total
($ million)
Benefits 5.2 68.8 214.7 45.1 333.8
Target 2.5 14.4 56.7 19.2 92.8
Amount and per cent above target 2.7
108%
54.4
378%
158
279%
25.9
135%
241
260%

Source: Audit Office analysis of data provided by the Department of Planning and Environment.

The department attributes the higher-than-expected financial benefits to the following:

  • benefit targets have not been updated to reflect the impact of the 2019 decision to mandate the use of the portal for all development applications. This decision brought forward the expected benefits as well as potential costs of the program. However, the department did not update its third business case which was draft at the time. The business case was subsequently approved in July 2020
  • one-off cost savings for agencies not having to develop their own systems
  • public exhibitions of planning proposals continuing to be available online during 2020 when some newspapers stopping printing due to COVID-19.

The calculation of benefits is overstated

The department reported $334 million of benefits in September 2021 due to the ePlanning program. This calculation is overstated because:

  • a proportion of reported benefits is likely to be due to other planning reforms
  • the calculation of the largest single benefit is incorrect
  • the reported benefits may not fully account for dis-benefits reported by some stakeholders.

The program’s benefits are calculated primarily from changes in planning performance data, such as the time it takes to determine a planning development application. The department currently attributes the benefits from shorter planning cycles entirely to the effect of the ePlanning program. However, planning cycles are impacted by many other factors such as the complexity of planning regulations and the availability of planning professionals. Planning cycles may also be impacted by other departmental initiatives which are designed to improve the time that it takes for a planning application to be evaluated. The Introduction describes some of these initiatives.

The largest contribution to the department’s September 2021 benefit report was an estimated saving of $151 million for developers due to lower costs associated with holding their investment for a shorter time. However, the department’s calculation of this benefit assumes a high baseline for the time to determine a development application. It also assumes that all development applications except for additions or alterations to existing properties will incur financing costs. However, a small but material number of these applications will be self-financed. The calculation also includes several data errors in spreadsheets.

The calculation of some benefits relies upon an extrapolation of the benefits experienced by a small number of early-adopter councils, including lower printing and scanning costs, fewer forms and quicker processing times. However, some councils report that their costs have increased following the introduction of the portal, primarily because aspects of the portal duplicate work that they carry out in their own systems. The portal has also required some councils to re-engineer aspects of their own systems, such as the integration of their planning systems with other council systems such as finance or property and rating systems. It has also required councils to create new ways of integrating council information systems with the planning portal.

The department has published information to help councils and certifiers to automatically integrate their systems with the planning portal. This approach uses application programming interfaces (or APIs) which are an industry-standard way for systems to share information. In April and May 2021, the government granted $4.8 million to 96 regional councils to assist with the cost of developing, implementing and maintaining APIs. The maximum amount of funding for each council was $50,000. The department is closely monitoring the implementation of APIs by councils and other portal users. Once they are fully implemented the department expects APIs to reduce costs incurred by stakeholders.

The department has not yet measured stakeholder costs. It was beyond the scope of this audit to validate these costs.

The department has not independently assured the calculation of reported benefits

In 2020 the department appointed an external provider to calculate the benefits achieved by the ePlanning program. The department advised that it chose to outsource the calculation of benefits because the provider had the required expertise and because it wanted an independent calculation of the benefits. The process involves:

  • extraction and verification of planning performance data by the department
  • population of data input sheets by the department
  • calculation of benefits by the external provider using the data input
  • confirmation by the department that the calculation includes all expected benefit sources.

The department does not have access to the benefits calculation model which is owned and operated by the external provider. The department trusts that the provider correctly calculates the benefits and does not verify the reported benefit numbers. However, as the benefits model involves many linked spreadsheets and approximately 300 individual data points, there is a risk that the calculation model contains errors beyond those discussed in this audit.

The reported benefits have only been calculated since 2019

The department originally intended to track benefits from October 2014. However, it only started to track benefits in 2019 when it appointed an external provider to calculate the benefits achieved by the portal. Any benefits or dis-benefits between the introduction of the portal and 2019 are unknown and not included in the department’s calculation of benefits.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #366 - released 21 June 2022