The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations. 

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Fare evasion on public transport: Follow-up audit

Fare evasion on public transport: Follow-up audit

Transport
Finance
Management and administration

The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.

However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.

 

Parliamentary reference - Report number #150 - released 26 April 2006

Published

Actions for Lease to Fox Studios Australia

Lease to Fox Studios Australia

Premier and Cabinet
Asset valuation
Infrastructure
Management and administration
Procurement
Project management

The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.

The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.

 

Parliamentary reference - Report number #44 - released 8 December 1997

Published

Actions for Redundancy arrangements

Redundancy arrangements

Industry
Planning
Compliance
Management and administration
Workforce and capability

The audit identified that overall the agencies had carried out the redundancy process satisfactorily and the process, with some exceptions, complied with Government and internal policies. Government policy states that performance problems should be dealt with by managing the performance of the employee rather than restructuring/redundancy processes. In a limited number of instances certain employees, whose performance had been questioned, had been offered and accepted voluntary redundancy.

The audit also indicates that the process of redundancies has resulted in lower salary costs, in real dollar terms, without undue increase in either overtime or consultancy costs nor any detrimental effect on service quality. However, it is noted that the decrease in staffing levels occurred exclusively in the non-budget sector. Budget sector staffing levels increased by 1.4 per cent during 1989-95. There are also signs that the need for and the benefits arising out of redundancies are not well planned or measured. The need for redundancies often arises from a desire to reduce staff related costs while there is no comparison of the costs of redundancy compared to benefits.

 

Parliamentary reference - Report number #37 - released 17 April 1997

Published

Actions for Review of NSW Agriculture

Review of NSW Agriculture

Industry
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Workforce and capability

Following a request from the NSW Legislative Council in September 1996, a performance audit into various matters affecting the operation of the New South Wales Department of Agriculture was undertaken by The Audit Office.

Among the recommendations from this report, the Audit Office found that:

  • An economic appraisal should be undertaken before all major developments, including rationalisation plans, are implemented. It should include details of anticipated benefits from the changes planned, so that their achievement can be evaluated after implementation.

  • Government policies should be made explicit or else established by directives in writing. Planning Infrastructure and human resources should be planned to maximise efficiency and effectiveness. If Government chooses alternatives that have higher costs or lower benefits for the Department, then these should be explicitly funded.

  • The Department should strengthen its system of internal control by strengthening the role of the Board of Management as a means of management control, directing an overhaul of the Charter of the Internal Audit Committee and using it to drive the Department’s internal audit function and ensuring implementation of an effective financial management information system.

 

Parliamentary reference - Report number #36 - released 27 March 1997