Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Coal Mining Royalties
Coal Mining Royalties
Department of Industry and Investment cannot assure the people of NSW that all royalties owed are being paid in full. This is because it does not have sufficiently robust systems and processes to identify what is owed and to make sure it is paid.
Parliamentary reference - Report number #208 - released 30 November 2010
Actions for NSW Lotteries Sales Transaction
NSW Lotteries Sales Transaction
The Auditor-General of New South Wales, Mr Peter Achterstraat, tabled his review of the Government’s sale of NSW Lotteries. The review was designed to address concerns raised regarding the sale process.
No financial imprudence or waste found Mr Achterstraat found no evidence to indicate that the successful bid was inconsistent with the rules, or that there was waste of public resources or financial imprudence with the Government’s sale of NSW lotteries in early 2010.
Actions for Volume Seven 2010 focus on Environment, Climate Change and Water
Volume Seven 2010 focus on Environment, Climate Change and Water
The report includes comments on his financial audits of NSW Government environment, climate change and water agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 resulted in one qualified Independent Auditor’s Report. Sydney Water has not recognised assets and liabilities of the Build-Own-Operate schemes in their statement of financial position. The combined profit after tax of the four largest water utilities increased substantially from $300 million in 2008-09 to $584 million in 2009-10. Distributions to the Government were $379 million up 17 per cent or $55 million from last year.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
Actions for Volume Four 2010 focus on Electricity
Volume Four 2010 focus on Electricity
The report includes comments on financial audits of government agencies in the electricity sector. The audits of the seven NSW electricity corporations’ financial reports for the year ended 30 June 2010 each resulted in an unqualified Independent Auditor’s Report. We did note significant uncertainty that may affect the value of power station assets due to the unknown impacts of any future carbon pollution reduction scheme and the Government’s proposed electricity industry reforms.
Actions for Government Investment in V8 Supercar Racing at Sydney Olympic Park
Government Investment in V8 Supercar Racing at Sydney Olympic Park
We recognise that the event was prepared in a tight timeframe, attracted a large crowd and was proclaimed a success by the Premier. However, we concluded that: Government received inadequate advice when assessing the proposal and post-event analysis indicates that costs are more than planned and that economic impacts are less than estimated largely because of fewer visitors from interstate.
Parliamentary reference - Report number #202 - released 23 June 2010
Actions for Severance Payments to Special Temporary Employees
Severance Payments to Special Temporary Employees
In reviewing both the severance pay guidelines and a sample of payments, we found the guidelines to be clear and all except two payments were made in accordance with them. In these two cases the severance payment was stipulated in the employment contract guaranteeing the STE a minimum of six months pay on termination, irrespective of the length of service.
Parliamentary reference - Report number #201 - released 16 June 2010
Actions for Improving the Performance of Metropolitan Bus Services
Improving the Performance of Metropolitan Bus Services
The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.
Parliamentary reference - Report number #198 - released 10 March 2010
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006