Actions for Government expenditure and transport planning in relation to implementing Barangaroo
Government expenditure and transport planning in relation to implementing Barangaroo
Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project.
Parliamentary reference - Report number #214 - released 15 June 2011
Actions for Volume One 2011
Volume One 2011
The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations.
Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Coal Mining Royalties
Coal Mining Royalties
Department of Industry and Investment cannot assure the people of NSW that all royalties owed are being paid in full. This is because it does not have sufficiently robust systems and processes to identify what is owed and to make sure it is paid.
Parliamentary reference - Report number #208 - released 30 November 2010
Actions for NSW Lotteries Sales Transaction
NSW Lotteries Sales Transaction
The Auditor-General of New South Wales, Mr Peter Achterstraat, tabled his review of the Government’s sale of NSW Lotteries. The review was designed to address concerns raised regarding the sale process.
No financial imprudence or waste found Mr Achterstraat found no evidence to indicate that the successful bid was inconsistent with the rules, or that there was waste of public resources or financial imprudence with the Government’s sale of NSW lotteries in early 2010.
Actions for Volume Seven 2010 focus on Environment, Climate Change and Water
Volume Seven 2010 focus on Environment, Climate Change and Water
The report includes comments on his financial audits of NSW Government environment, climate change and water agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 resulted in one qualified Independent Auditor’s Report. Sydney Water has not recognised assets and liabilities of the Build-Own-Operate schemes in their statement of financial position. The combined profit after tax of the four largest water utilities increased substantially from $300 million in 2008-09 to $584 million in 2009-10. Distributions to the Government were $379 million up 17 per cent or $55 million from last year.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
Actions for Volume Four 2010 focus on Electricity
Volume Four 2010 focus on Electricity
The report includes comments on financial audits of government agencies in the electricity sector. The audits of the seven NSW electricity corporations’ financial reports for the year ended 30 June 2010 each resulted in an unqualified Independent Auditor’s Report. We did note significant uncertainty that may affect the value of power station assets due to the unknown impacts of any future carbon pollution reduction scheme and the Government’s proposed electricity industry reforms.
Actions for Knowing the Collections
Knowing the Collections
The Museum is doing much to improve access to its collections. However, as with other natural history museums, only a small proportion is on public display. Its efforts range from placing information on the internet for use by the public and scientific users, to helping indigenous Australian and Pacific Islander communities reconnect with their respective cultures.
Parliamentary reference - Report number #203 - released 1 September 2010
Actions for Volume One 2010
Volume One 2010
The report includes comments on his annual audit of entitlements paid to Members of NSW Parliament and financial audits of WorkCover, Justice Health, Waste Recycling Processing Corporation and some other NSW Government agencies.
In his audit the Auditor-General had called for a system to be developed to ensure accrued loyalty/reward benefits are used to reduce Members’ parliamentary business travel expenditure, rather than be forfeited when a Member leaves Parliament. He also called for better controls over the Logistic Support Allocation used for transport, communications, printing, stationery, office supplies and equipment.