Reports

Published

Actions for Government assistance to industry

Government assistance to industry

Industry
Management and administration
Project management

Governments provide assistance to industry for a number of reasons, including facilitating economic growth, increase employment, support regional development, or grow priority industries.
 
This audit examined seven programs administered by the former Department of Trade and Investment, Regional Infrastructure and Services that provide at least $2 million per year in grants and subsidies to industry. This included the State Investment Attraction Scheme and Regional Industries Investment Fund.

 

Parliamentary reference - Report number #262 - released 17 December 2015

Published

Actions for Volume Thirteen 2015 Electricity

Volume Thirteen 2015 Electricity

Planning
Information technology
Internal controls and governance
Project management
Risk

The NSW Government continues to divest its interest in electricity businesses.
 
In 2014-15, Macquarie Generation and Delta Electricity’s Colongra power stations were sold, collectively raising over $1.7 billion in gross proceeds.
 
In November 2015, the NSW Government announced the lease of TransGrid for 99 years to a private sector consortium for $10.3 billion and the sale of Delta Electricity’s Vales Point power station for $1.0 million. It expects to lease 50.4 percent of Ausgrid and Endeavour Energy during 2016, but retain 100 percent ownership of Essential Energy.
 
Its net investment in the electricity businesses at 30 June 2015 was $10.8 billion ($11.4 billion at 30 June 2014). This comprised $14.0 million in the electricity generators, $2.1 billion in TransGrid and $8.7 billion in the distributors.

Published

Actions for Volume Twelve 2015 Part One Trade & Investment and TAFE

Volume Twelve 2015 Part One Trade & Investment and TAFE

Planning
Education
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

Serious system limitations prevented TAFE NSW from providing sufficient and appropriate evidence to support recorded student revenue of $477 million, student receivables and accrued income of $47.6 million and unearned revenue of $398 million.
 
These limitations resulted in: 

  • a qualified audit opinion being issued for TAFE NSW;
  • delays in enrolling students;
  • inability to fully reconcile cash balances;
  • difficulties in reconciling student enrolments with revenues recorded in the financial statements;
  • large volumes of manual processing.

Published

Actions for Volume Twelve 2015 Part Two Water

Volume Twelve 2015 Part Two Water

Planning
Environment
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.

Published

Actions for Volume Nine 2015 Planning and Environment

Volume Nine 2015 Planning and Environment

Planning
Environment
Information technology
Internal controls and governance
Project management
Risk

The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
 
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.

Published

Actions for Volume Seven 2015 Part One Law and Order

Volume Seven 2015 Part One Law and Order

Justice
Information technology
Internal controls and governance
Project management
Risk

Many factors are contributing to the overcrowding of the NSW prison system. This is in turn putting pressure on operations in the courts, and could ultimately impact rates of reoffending.

The lack of capacity is impacting more than just the NSW prison system. Over the weekend of 31 October 2015 some inmates held by the NSW Police Force could not be brought before a court because of capacity shortages.

This was one of the findings reported in Volume Seven 2015 of the Auditor-General’s Report to Parliament, which covers law and order services provided by the NSW Police Force, Department of Justice, and NSW Trustee and Guardian.

Published

Actions for Volume Seven 2015 Part Two Emergency Services

Volume Seven 2015 Part Two Emergency Services

Justice
Information technology
Internal controls and governance
Project management
Risk

Demand for emergency services increased by eight per cent, in response to 187,282 incidents during 2014-15. Total volunteer numbers have risen over the last three years by 2.4 per cent to 98,536, improving capacity to deal with such incidents. NSW Rural Fire Service had only five emergency declarations in 2014-15 compared to 48 the year before, resulting in natural disaster expenditure falling by $89.0 million.
 
Fire and Rescue NSW response time to incidents and NSW Rural Fire Service fire containment continue to improve.
 
These are some of the matters highlighted in Part 2 of Volume Seven 2015 of the Auditor-General’s Report to Parliament, which covers emergency services agencies.

Published

Actions for Identifying productivity in the public sector

Identifying productivity in the public sector

Health
Education
Community Services
Transport
Justice
Treasury
Whole of Government
Internal controls and governance
Management and administration

This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court.

Productivity is commonly defined as the amount of output per unit of input.

 

Parliamentary reference - Report number #256 - released 16 July 2015

Published

Actions for Implementing performance audit recommendations

Implementing performance audit recommendations

Premier and Cabinet
Treasury
Whole of Government
Health
Education
Community Services
Transport
Justice
Compliance
Internal controls and governance
Management and administration

NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
 
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.

 

Parliamentary reference - Report number #254 - released 24 June 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015