Reports
Actions for Planning, Industry and Environment 2019
Planning, Industry and Environment 2019
This report outlines the results of audits of the financial statements of agencies now grouped in the NSW Planning, Industry and Environment cluster.
Unqualified audit opinions were issued for 56 of the 66 cluster agencies’ 30 June 2019 financial statements. Ten audits remain incomplete. The cluster agencies need to improve the timeliness of financial reporting.
The Audit Office continued to identify issues regarding unprocessed Aboriginal land claims and the recognition of Crown land. ‘Auditor-General’s reports to parliament have recommended action to reduce the level of unprocessed land claims since 2007. However, the number of unprocessed claims continued to increase’, Margaret Crawford said.
One in five internal control findings were repeat issues. Key themes included information technology, asset management and improvements required to expense and payroll controls.
The report makes several recommendations including:
- Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019
- the Department of Planning, Industry and Environment should prioritise action to reduce unprocessed Aboriginal land claims
- the Department of Planning, Industry and Environment should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.
This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2019. The table below summarises our key observations.
1. Machinery of Government changes
Creation of the Planning, Industry and Environment cluster |
The Machinery of Government (MoG) changes abolished the former Planning and Environment cluster and former Industry cluster, and created the Planning, Industry and Environment cluster on 1 July 2019. The Department of Planning and Environment (DPE), the Department of Industry (DOI), the Office of Environment and Heritage, and the Office of Local Government were abolished and the majority of their functions were transferred to the new Department of Planning, Industry and Environment (DPIE). |
The Department of Planning, Industry and Environment is still in the process of implementing changes |
The MoG changes bring risks and challenges to the cluster. A MoG Steering Committee, with the support of various project control groups and working groups, identified and developed responses to key risks arising from the changes. However, the DPIE will take some time to fully integrate the policies, systems and processes of the abolished Departments and agencies. |
2. Financial reporting
Audit opinions | Unqualified audit opinions were issued for 56 of the 66 cluster agencies' 30 June 2019 financial statements audits. Ten financial statements audits are still ongoing. |
Timeliness of financial reporting |
Fifty-five of the 57 agencies subject to statutory deadlines submitted their financial statements on time. Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions issued by the statutory deadline. Agencies prepared and submitted their early close procedures in accordance with the mandatory timeframe set by NSW Treasury. However, 17 of the 49 agencies where we reviewed early close procedures were assessed as either partially addressing or not addressing one or more of the mandatory requirements. The cluster agencies could benefit from an increased focus on early close procedures. |
Introduction of AASB 16 'Leases' |
We noted errors in the lease data used in Property NSW's AASB 16 impact calculations, which affect both Property NSW and other government agencies. These errors were significant enough to present a risk of material misstatements to the financial statements of Property NSW and other government agencies in future reporting periods. We had similar findings in our recent performance audit on 'Property Asset Utilisation', which highlighted issues with the quality of Property NSW's records. Recommendation: Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019. |
Unprocessed Aboriginal land claims have continued to increase |
Despite an increase in the number of claims resolved, the number of unprocessed Aboriginal land claims increased by 7.2 per cent from the prior year to 35,855 at 30 June 2019. Claims can be made over Crown land assets of the DPIE or other government agencies. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land. We first recommended action to address unprocessed claims in 2007. Recommendation (repeat issue): The DPIE should prioritise action to reduce unprocessed Aboriginal land claims. |
3. Audit observations
Internal controls |
One in five internal control issues identified and reported to management in 2018–19 were repeat issues. The lack of user access review was the most common IT general control issue in the cluster. |
Drought relief |
The NSW Government announced an emergency drought relief package of $500 million in 2018, in addition to other financial assistance measures already in place. Limited documentation and written agreements between relevant delivery agencies resulted in a $31.0 million misstatement relating to grant revenue. |
Recognition of Crown land |
Crown land is an important asset of the state. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel. Last year we recommended the DOI should ensure the database of Crown land is complete and accurate. While the DOI has commenced actions to improve the database, this continued to be an issue in 2018–19. Recommendation (repeat issue): The DPIE should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control. |
Developer contributions | The former DPE continued to accumulate more developer contributions revenues than it spent on infrastructure projects. Total unspent funds increased to $274 million at 30 June 2019. |
This report provides parliament and other users of the Planning, Industry and Environment cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
This cluster was created by the Machinery of Government changes on 1 July 2019. This report is focused on agencies in the Planning, Industry and Environment cluster from 1 July 2019. However, these agencies were all in other clusters during 2018–19. Please refer to the section on Machinery of Government changes for more details.
Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions that are given effect by Administrative orders.
The MoG changes, announced following the NSW State election on 23 March 2019, created the Planning, Industry and Environment (PIE) cluster. The Administrative Changes Orders issued on 2 April 2019, 1 May 2019 and 28 June 2019 gave effect to these changes. These orders became effective on 1 July 2019.
Section highlights
The 2019 MoG changes significantly impacted the former Planning and Environment, and Industry clusters and agencies.
- The PIE cluster combines most of the functions and agencies of the former Planning and Environment and Industry clusters from 1 July 2019.
- The Department of Planning, Industry and Environment is the principal agency in the PIE cluster.
- The MoG changes bring risks and challenges to the PIE cluster.
- A MoG Steering Committee was established to oversee the transitional processes.
- The full integration of the systems and processes will not be completed in the near future.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.
Section highlights
- Unqualified audit opinions were issued for all completed 30 June 2019 financial statements audits. However, some cluster agencies can further enhance the quality of financial reporting.
- Timeliness of financial reporting remains an issue for 13 agencies.
- Deficiencies were identified in the data used to calculate the impact of AASB 16 ‘Leases’ effective from 1 July 2019. Property NSW should urgently address these deficiencies.
- Unprocessed Aboriginal land claims continue to increase. DPIE should prioritise action to reduce unprocessed Aboriginal land claims.
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our audit observations and insights from our financial statement audits of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.
Section highlights
- One in five issues identified and reported to management in 2018–19 were repeat issues.
- The lack of user access review was the most common IT general control issue in the PIE cluster.
- The PIE cluster provided significant financial assistance for drought relief.
- There continues to be significant deficiencies in Crown land records. The DPIE should ensure the Crown land database is complete and accurate.
- Unspent developer contributions funds continued to build up in 2018–19.
Appendix one – List of 2019 recommendations
Appendix two – Status of 2018 recommendations
Appendix three – Cluster agencies
Appendix four – Financial data
Appendix five – Management letter findings
Appendix six – Timeliness of financial reporting
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Stronger Communities 2019
Stronger Communities 2019
A report has been released on the NSW Stronger Communities cluster.
From 1 July 2019, the functions of the former Department of Justice, the former Department of Family and Community Services and many of the cluster agencies moved to the new Stronger Communities cluster. The Department of Communities and Justice is the principal agency in the new Stronger Communities cluster.
The report focuses on key observations and findings from the most recent financial audits of agencies in the Stronger Communities cluster.
Unqualified audit opinions were issued on the financial statements for all agencies in the cluster.
There were 157 audit findings on internal controls. Two of these were high risk and 59 were repeat findings from previous financial audits. ‘Cluster agencies should prioritise actions to address internal control weaknesses promptly with particular focus given to issues that are assessed as high risk’, the Auditor-General said.
The report notes that the NSW Government’s new workers' compensation legislation, which gave eligible firefighters presumptive rights to workers' compensation, cost emergency services agencies $180 million in 2018–19, mostly in increased premiums.
This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2019. The table below summarises our key observations.
This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analyses, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
This cluster was significantly impacted by the Machinery of Government (MoG) changes on 1 July 2019. This report focuses on the agencies that from 1 July 2019, comprised the Stronger Communities cluster. The MoG changes moved some agencies from the clusters to which they belonged in 2018–19 to the Stronger Communities cluster. Conversely, the MoG also moved some agencies formerly in the Family and Community Services cluster and Justice cluster elsewhere. Please refer to the section on Machinery of Government changes for more details.
The Department of Communities and Justice is the principal agency of the cluster. The newly created department combines functions of the former Department of Justice and the Department of Family and Community Services.
Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes occur when the government reorganises these structures and functions and those changes are given effect by Administrative Orders.
The MoG changes announced following the NSW State election on 23 March 2019 significantly impacted the Stronger Communities cluster through Administrative Changes Orders issued on 2 April 2019 and 1 May 2019. These orders took effect on 1 July 2019.
Section highlights
The 2019 MoG changes significantly impacted the former Justice and Family and Community Services (FACS) departments and clusters.
- The Stronger Communities cluster combines most of the functions and agencies of the former Justice and FACS clusters from 1 July 2019.
- The Department of Communities and Justice is now the principal agency in the new cluster.
- The MoG changes bring new responsibilities, risks and challenges to the cluster.
- A temporary office has been established by the Department of Communities and Justice to support the cluster in the planning, delivery and reporting associated with implementing the changes.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations relating to the financial reporting of agencies in the Stronger Communities cluster for 2019.
Section highlights
- Unqualified audit opinions were issued for all agencies' 30 June 2019 financial statements. However, further actions can be taken by some cluster agencies to enhance the quality of their financial reporting.
- In November 2018, the Department of Justice implemented a new Victims Support Services system called VS Connect. Significant data quality issues arising from the VS Connect system implementation impacted the Department's ability to reliably estimate its Victims Support Scheme claims liabilities at 30 June 2019.
We recommend the Department of Communities and Justice resolves the data quality issues in the new VS Connect System before 30 June 2020 and capture and apply lessons learned from recent project implementations, including LifeLink, Justice SAP and VS Connect, in any relevant future implementations. - Our audits found some cluster agencies needed to do more work on their impact assessments and preparedness to implement the new accounting standards, to minimise the risk of errors in their 2019–20 financial statements.
- Cluster agencies with annual leave balances exceeding the State's target should further review their approach to managing leave balances.
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.
Section highlights
- Cluster agencies should action recommendations to address internal control weaknesses promptly. Particular focus should be given to prioritising high risk issues. The 2018–19 financial audits of cluster agencies identified 157 internal control issues. Of these, two were high risk and 37.6 per cent were repeat findings from previous audits.
- Data from the Department of Justice shows the inmate population reached a maximum of 13,798, compared to an operational capacity of 14,626 beds on 31 August 2019. This equates to an operational vacancy rate of 5.7 per cent, which is more than the recommended 5.0 per cent buffer. This is the first time the vacancy rate has exceeded the target over the last five years. Growth in the NSW prison population is being managed through the NSW Government's $3.8 billion Prison Bed Capacity Program.
- In September 2018, the NSW Government introduced new workers' compensation legislation, which gives eligible firefighters presumptive rights to workers' compensation when diagnosed with one of 12 prescribed cancers. The new legislation cost emergency services agencies $180 million in 2018–19, mainly through additional workers' compensation premiums.
Appendix one – Timeliness of financial reporting by agency
Appendix two – Management letter findings by agency
Appendix three – List of 2019 recommendations
Appendix four – Status of 2018 recommendations
Appendix five – Cluster agencies
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Transport 2019
Transport 2019
This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.
Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.
The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.
The report makes several recommendations including:
- agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
- the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.
This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.
1. Machinery of Government changes
Transport for NSW, as the lead agency, will absorb the functions of Roads and Maritime Services |
The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes. This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force. Transport is considering the impact of the changes on its operating model and financial reporting. |
2. Financial reporting
Audit opinions |
Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster. TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment. The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error. |
Preparedness for new accounting standards |
Agencies across the cluster are progressing in their implementation of the new accounting standards. Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards. |
Valuation of assets remains a challenge in the Transport cluster |
Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.
Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities. |
Inconsistent accounting policies across the Transport cluster |
There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies. As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster. |
Revenue growth |
Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW. The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares. |
Negative Opal cards |
Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal). In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations. |
3. Audit observations
Internal controls | There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management. Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls. |
Write-off of assets | In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network. These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities. |
Transport Asset Holding Entity (TAHE) |
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model. |
Excess annual leave |
Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.
|
Completeness and accuracy of contracts registers |
There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.
|
This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.
Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.
The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.
Section highlights
Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.
- The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
- The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
- As at the date of this report, the Act is not yet in force.
- There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
- As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
- Transport is working on a number of options as to how to implement the changes.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.
Section highlights
- Unqualified audit opinions were issued on all agencies' financial statements.
- RMS required an extension from NSW Treasury for their early close procedures.
- TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
- Valuation of assets remains a challenge across the cluster.
- There remains Opal cards with negative balances.
- Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
- Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.
Section highlights
- There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
- Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
- Twenty-six per cent of Transport employees have excess annual leave.
- There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.
Appendix one – Timeliness of financial reporting by agency
Appendix two – Management letter findings by agency
Appendix three – List of 2019 recommendations
Appendix four – Status of 2017 and 2018 recommendations
Appendix five – Cluster agencies
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Engagement of probity advisers and probity auditors
Engagement of probity advisers and probity auditors
Three key agencies are not fully complying with the NSW Procurement Board’s Direction for engaging probity practitioners, according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin. They also do not have effective processes to achieve compliance or assure that probity engagements achieved value for money.
Probity is defined as the quality of having strong moral principles, honesty and decency. Probity is important for NSW Government agencies as it helps ensure decisions are made with integrity, fairness and accountability, while attaining value for money.
Probity advisers provide guidance on issues concerning integrity, fairness and accountability that may arise throughout asset procurement and disposal processes. Probity auditors verify that agencies' processes are consistent with government laws and legislation, guidelines and best practice principles.
According to the NSW State Infrastructure Strategy 2018-2038, New South Wales has more infrastructure projects underway than any state or territory in Australia. The scale of the spend on procuring and constructing new public transport networks, roads, schools and hospitals, the complexity of these projects and public scrutiny of aspects of their delivery has increased the focus on probity in the public sector.
A Procurement Board Direction, 'PBD-2013-05 Engagement of probity advisers and probity auditors' (the Direction), sets out the requirements for NSW Government agencies' use and engagement of probity practitioners. It confirms agencies should routinely take into account probity considerations in their procurement. The Direction also specifies that NSW Government agencies can use probity advisers and probity auditors (probity practitioners) when making decisions on procuring and disposing of assets, but that agencies:
- should use external probity practitioners as the exception rather than the rule
- should not use external probity practitioners as an 'insurance policy'
- must be accountable for decisions made
- cannot substitute the use of probity practitioners for good management practices
- not engage the same probity practitioner on an ongoing basis, and ensure the relationship remains robustly independent.
The scale of probity spend may be small in the context of the NSW Government's spend on projects. However, government agencies remain responsible for probity considerations whether they engage external probity practitioners or not.
The audit assessed whether Transport for NSW, the Department of Education and the Ministry of Health:
- complied with the requirements of ‘PBD-2013-05 Engagement of Probity Advisers and Probity Auditors’
- effectively ensured they achieved value for money when they used probity practitioners.
These entities are referred to as 'participating agencies' in this report.
We also surveyed 40 NSW Government agencies with the largest total expenditures (top 40 agencies) to get a cross sector view of their use of probity practitioners. These agencies are listed in Appendix two.
Conclusion
We found instances where each of the three participating agencies had not fully complied with the requirements of the NSW Procurement Board Direction ‘PBD-2013-05 Engagement of Probity Advisers and Probity Auditors’ when they engaged probity practitioners. We also found they did not have effective processes to achieve compliance or assure the engagements achieved value for money.
In the sample of engagements we selected, we found instances where the participating agencies did not always:
- document detailed terms of reference
- ensure the practitioner was sufficiently independent
- manage probity practitioners' independence and conflict of interest issues transparently
- provide practitioners with full access to records, people and meetings
- establish independent reporting lines reporting was limited to project managers
- evaluate whether value for money was achieved.
We also found:
- agencies tend to rely on only a limited number of probity service providers, sometimes using them on a continuous basis, which may threaten the actual or perceived independence of probity practitioners
- the NSW Procurement Board does not effectively monitor agencies' compliance with the Direction's requirements. Our enquiries revealed that the Board has not asked any agency to report on its use of probity practitioners since the Direction's inception in 2013.
There are no professional standards and capability requirements for probity practitioners
NSW Government agencies use probity practitioners to independently verify that their procurement and asset disposal processes are transparent, fair and accountable in the pursuit of value for money.
Probity practitioners are not subject to regulations that require them to have professional qualifications, experience and capability. Government agencies in New South Wales have difficulty finding probity standards, regulations or best practice guides to reference, which may diminish the degree of reliance stakeholders can place on practitioners’ work.
The NSW Procurement Board provides direction for the use of probity practitioners
The NSW Procurement Board Direction 'PBD-2013-15 for engagement of probity advisers and probity auditors' outlines the requirements for agencies' use of probity practitioners in the New South Wales public sector. All NSW Government agencies, except local government, state owned corporations and universities, must comply with the Direction when engaging probity practitioners. This is illustrated in Exhibit 1 below.
Actions for Managing growth in the NSW prison population
Managing growth in the NSW prison population
The Department of Justice has relied heavily on temporary responses to accommodate growing prisoner numbers according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin.
At the time of this audit, the NSW Department of Justice (DOJ) was responsible for delivering custodial corrections services in New South Wales through its Corrective Services NSW division (Corrective Services NSW). From 1 July 2019, the Department of Family and Community Services and Justice will be responsible for these functions.
Within DOJ, Corrective Services NSW is responsible for administering sentences and legal orders through custodial and community-based management of adult offenders. Its key priorities are:
- providing safe, secure and humane management of prisoners
- reducing reoffending
- improving community safety and confidence in the justice system.
The prison population in New South Wales grew by around 40 per cent between 2012 to 2018, from 9,602 to 13,630 inmates. This rate of growth was higher than experienced prior to 2012. DOJ forecasts growth to continue over the short and longer-term.
DOJ has responded to inmate population growth by doubling-up and tripling-up the number of prison beds in cells, reactivating previously closed prisons, and a $3.8 billion program of new prison capacity. DOJ has also developed a long-term prison infrastructure strategy that projects long-term needs and recommended investments to meet these needs.
This audit assessed how efficiently and effectively DOJ is responding to growth in the NSW prison population. In this report, we have not analysed the sources of demand or recommended ways that custody may be avoided. These are largely government policy issues.
The Productivity Commission’s Report on Government Services outlines the performance indicator framework for corrective services in Australia (Appendix three). We have used measures from this framework to assess the efficiency and effectiveness of DOJ’s responses to prison bed capacity needs.
In this section, we analyse system-wide indicators as DOJ has not consistently published or reported data for individual correctional centres over the period of review.
Appendix one - Response from agency
Appendix two - Managing women in custody
Appendix three - Corrective services performance indicator framework
Appendix four - About the audit
Appendix five – Performance auditing
Parliamentary Reference: Report number #319 - released 24 May 2019
Actions for Contingent workforce - management and procurement
Contingent workforce - management and procurement
The Department of Industry, Transport for NSW and the Department of Education were not able to demonstrate that the use of contingent labour is the best resourcing strategy to meet their business needs or deliver value for money.
None of the three agencies we reviewed were able to demonstrate that contingent labour is the best resourcing strategy to meet their agencies’ business needs or delivers value for money. There are three reasons for this. First, agencies’ use of contingent labour was not informed by workforce planning at an agency level, with limited work undertaken in this area. Second, two of the three agencies have limited oversight of their contingent workforce. Information is not reliable or accurate, reports are onerous to produce, and there is limited reporting to the agency’s executive. Finally, none of the agencies routinely monitor and centrally document the performance of contingent workers to ensure services are delivered as planned. Together, these factors make it difficult for agencies to ensure contingent labour is engaged only when needed, at reasonable rates, and delivers quality services.
Some of these issues will be addressed by Contractor Central, which had only been introduced at Education at the time of our review. The new software program enables staff to easily obtain real-time reports on its contingent workforce. The recruitment broker also has the potential to improve value through better negotiation and benchmarking of pay rates. However, Contractor Central will only address some of the issues highlighted above. Better workforce planning and performance monitoring are needed to ensure an agencies’ workforce, including contingent workers, meets its business needs and represents value for money.
Download appendices for report on Contingent workforce
Parliamentary reference - Report number #282 - released 27 April 2017
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017.
Financial reporting | |
Observation | Conclusion |
Only one qualified audit opinion was issued on the 2015–16 financial statements of NSW public sector agencies, compared to two in 2014–15. | The quality of financial reporting continued to improve across the NSW public sector. |
More 2015–16 financial statements and audit opinions were signed within three months of the year end. | Timely financial reporting was facilitated by more agencies resolving significant accounting issues early, completing asset valuations on time and compiling sufficient evidence to support financial statement balances. |
NSW Treasury’s early close procedures in 2015–16 were again successful in improving the quality and timeliness of financial reporting, largely facilitated by the early resolution of accounting issues. For 2016–17, NSW Treasury has narrowed the scope of mandatory early close procedures. |
The narrowed scope of mandatory early close procedures may diminish the good performance in ensuring the quality and timeliness of financial reporting achieved in recent years. To mitigate this risk, NSW Treasury has mandated that agencies perform non-financial asset valuations and prepare proforma financial statements in their early close procedures. It also encourages them to continue with the good practices embedded in recent years. |
Although most agencies complied with NSW Treasury’s early close asset revaluation procedures we identified areas where they can improve. | Asset revaluations need to commence early enough to ensure all assets are identified and the results are analysed, recorded and reflected accurately in the early close financial statements. |
Number of misstatements | |||||
Year ended 30 June | 2015-16 | 2014-15 | 2013-14 | 2012-13 | 2011-12 |
Total reported misstatements | 298 | 396 | 459 | 661 | 1,077 |
All material misstatements identified by agencies and audit teams were corrected before the financial statements and audit opinions were signed. A material misstatement relates to an incorrect amount, classification, presentation or disclosure in the financial statements that could reasonably be expected to influence the economic decisions of users.
Significant matters reported to the portfolio Minister, Treasurer and Agency Head
In 2015–16, we reported the following significant matters to the portfolio Minister, Treasurer and agency head in our Statutory Audit Reports:
Appropriate financial controls help ensure the efficient and effective use of resources and the implementation and administration of agency policies. They are essential for quality and timely decision making.
In 2015–16, our audit teams made the following key observations on the financial controls of NSW public sector agencies.
Financial controls | |
Observation | Conclusion |
More needs to be done to implement audit recommendations on a timely basis. We found 212 internal control issues identified in previous audits had not been adequately addressed by 30 June 2016. |
Delays in implementing audit recommendations can impact the quality of financial information and the effectiveness of decision making. Agencies need to ensure they have action plans, timeframes and assigned responsibilities to address recommendations in a timely manner. |
Agencies continue to face challenges managing information security. Most information technology issues we identified related to poor IT user administration in areas like password controls and inappropriate access. | Agencies should review the design and effectiveness of information security controls to ensure data is adequately protected. |
We found shared service provider agreements did not always adequately address information security requirements. |
Where agencies use shared service providers they should consider whether the service level arrangements adequately address information security. |
Thirteen of 108 agencies required to attest to having a minimum set of information security controls did not do so in their 2015 annual reports. | The 'NSW Government Digital Information Security Policy' recognises the growing need for effective information security. With cyber security threats continuing to increase as digital services expand we plan to look at cyber security as part of our 2017–18 performance audit program. |
We identified instances where service level agreements with shared service providers were outdated, signed too late or did not exist. | Corporate and shared service arrangements are more effective when service level arrangements are negotiated and signed in time, clearly detail rights and responsibilities and include meaningful KPIs, fee arrangements and dispute resolution processes. |
Internal controls at GovConnect, the private sector provider of transactional and information technology services to many NSW public sector agencies were ineffective in 2015–16. We found mitigating actions taken to manage transition risks from ServiceFirst to GovConnect were ineffective in ensuring effective control over client transactions and data. | The Department of Finance, Services and Innovation should ensure GovConnect addresses the control deficiencies. It should also examine the breakdowns in the transition of the shared service arrangements and apply the learnings to other services being transitioned to the private sector. |
Maintenance backlogs exist in several NSW public sector agencies, including Roads and Maritime Services, Sydney Trains, NSW Health, the Department of Education and the Department of Justice. | To address backlog maintenance it is important for agencies to have asset lifecycle planning strategies that ensure newly built and existing assets are funded and maintained to a desired service level. |
Actions for Volume Eight 2013 focusing on Transport and Ports
Volume Eight 2013 focusing on Transport and Ports
Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.
The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.
Actions for Volume Six 2013 focusing on Law, Order and Emergency Services
Volume Six 2013 focusing on Law, Order and Emergency Services
We issued unqualified audit opinions on the above agencies’ 30 June 2013 financial statements. During the year, The Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. As a result, the law and order services agencies were required to perform early close procedures. All law and order service agencies were broadly successful in performing the procedures, which helped them submit financial statements by an earlier due date. This in turn enabled the financial statement audits to be finalised within an earlier timeframe of eight weeks (nine weeks in 2011-12).
As previously recommended, the Department of Attorney General and Justice should continue integrating policies, operations and systems between its divisions and, once complete, analyse the costs and benefits. The Department of Attorney-General and Justice should also ensure it has the necessary processes in place to enable it to regularly monitor and measure the performance and success of the Victims Support Scheme in providing a more accessible, streamlined and targeted service to victims of violent crime in New South Wales.
Actions for Distributing Legal Aid in New South Wales
Distributing Legal Aid in New South Wales
We found the Commission to be performing well in delivering legal aid services. It has maintained and expanded services despite funding pressures and increasing demand. Overall, we found the Commission’s practices of making people aware of legal issues and its services to be comprehensive. Communication is via brochures, telephone and internet. We also found its processing of applications for legal aid to be sound.
Parliamentary reference - Report number #163 - released 13 December 2006