Reports
Actions for Volume Eight 2012 focusing on Transport and Ports
Volume Eight 2012 focusing on Transport and Ports
We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.
Some of the findings of the report include:
-
government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)
-
passenger services revenue only covered 20 per cent of RailCorp's operating costs
-
Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests
-
At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually
-
Transport patronage continued to grow with 510 million journeys on train, bus and ferry services
-
CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time
-
On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12
-
Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes
-
Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.
Actions for Volume One 2012 focusing on themes from 2011
Volume One 2012 focusing on themes from 2011
The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.
Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.
Actions for Volume Six 2011 focus on Environment, Water and Regional Infrastructure
Volume Six 2011 focus on Environment, Water and Regional Infrastructure
The Environment Protection Authority’s expenditure for the financial year 2010/11 was $92 million - $76 million of this was for environment protection and regulation. The Office of Environment and Heritage and the Environment Protection Authority commenced 145 prosecutions for environmental offences and 106 were completed in the financial year 2010/11, down from the 134 prosecutions completed in 2009/10. Financial penalties for 2010/11 totalled $969,000 down from $1,403,000 in 2009/10. The average fine decreased from $10,468 in 2009/10 to $9,141 in 2010/11.
Actions for Government expenditure and transport planning in relation to implementing Barangaroo
Government expenditure and transport planning in relation to implementing Barangaroo
Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project.
Parliamentary reference - Report number #214 - released 15 June 2011
Actions for Volume One 2011
Volume One 2011
The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations.
Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Coal Mining Royalties
Coal Mining Royalties
Department of Industry and Investment cannot assure the people of NSW that all royalties owed are being paid in full. This is because it does not have sufficiently robust systems and processes to identify what is owed and to make sure it is paid.
Parliamentary reference - Report number #208 - released 30 November 2010
Actions for NSW Lotteries Sales Transaction
NSW Lotteries Sales Transaction
The Auditor-General of New South Wales, Mr Peter Achterstraat, tabled his review of the Government’s sale of NSW Lotteries. The review was designed to address concerns raised regarding the sale process.
No financial imprudence or waste found Mr Achterstraat found no evidence to indicate that the successful bid was inconsistent with the rules, or that there was waste of public resources or financial imprudence with the Government’s sale of NSW lotteries in early 2010.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.