The Auditor-General for New South Wales, Margaret Crawford, released her report today on the Industry cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster agencies received unqualified audit opinions for 41 out of the 47 financial statements presented for audit for 30 June 2018. Six audits remain incomplete. 'While it is pleasing to note that unqualified audit opinions have been issued, the timeliness of financial reporting needs to be improved through better oversight, prompt resolution of issues, and an increased focus on early close procedures', the Auditor-General said.

This report analyses the results of our audits of financial statements of the Industry cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Industry cluster agencies' financial statements with the results of our audits, including our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

The Department of Industry (the Department) is the lead agency in a cluster of 50 agencies. Other significant agencies in the cluster include Local Land Services, New South Wales Rural Assistance Authority, Technical and Further Education Commission (TAFE NSW), various sporting agencies, Forestry Corporation NSW and Water NSW.

The cluster:

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Industry cluster for 2018.
 

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for 41 out of 47 financial statement audits. Six audits are continuing.

The number of misstatements identified in financial statements submitted for audit increased from 73 in 2016–17 to 92 in 2017–18.
Conclusion: Agencies continue to address financial reporting issues and ensure significant matters that may impact the audit opinion are appropriately dealt with. The increase in the number of misstatements indicates a renewed focus on quality is required.
2.2 Timeliness of financial reporting
Nineteen out of 37 audit opinions were issued within the statutory deadline. Delays occurred due to the time required to resolve issues identified during the audit, or to obtain appropriate evidence to support balances or disclosures in the financial statements. There were also delays in receiving the signed certification from the agency, required before we can issue an audit opinion.

We reviewed the conduct of early close procedures at 17 agencies. Fifteen of these agencies were assessed as not fully addressing mandatory early close procedures.
Recommendation: Timeliness of financial reporting should be improved through better oversight of the preparation of financial statements, prompt resolution of issues, and an increased focus on early close procedures.
2.3 Key financial reporting issues
Information system limitations continue at TAFE NSW. TAFE NSW implemented additional processes to verify the accuracy and completeness of revenue from student fees. Conclusion: Procedures to address system limitations are costly, causing delays in financial reporting and increased resource commitments for staff, contractors and audit.
Misstatements and internal control issues continue to be identified in accounting for Crown land. The information system used to record Crown land was not designed to facilitate efficient financial reporting. These limitations and other control weaknesses impacted the completeness and accuracy of the Department's financial statements.
Recommendation: The Department should address system limitations and control weaknesses to ensure complete and accurate reporting for Crown land.
Unprocessed Aboriginal land claims continue to increase. Recommendation (repeat issue): The Department should reduce unprocessed Aboriginal land claims.
2.4 Financial information and sustainability
Cluster agencies recorded a combined surplus of $58.0 million compared to a combined deficit of $86.0 million in the previous year.

 

We identified five agencies with potential sustainability issues such as low liquidity or negative net assets. Conclusion: Adequate arrangements are in place to mitigate potential sustainability issues. These arrangements include a commitment from the Department to provide financial support if required. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Industry cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal control
Almost one in three internal control issues identified in 2017–18 were repeat issues. Recommendation (repeat issue): Recommendations to management to address internal control issues from prior years should be addressed promptly to reduce risks and improve processes.
3.2 Information technology controls
User access administration over financial systems remains an area of weakness. Two high risk and 18 moderate risk issues related to user access administration across nine agencies were identified. Recommendation (repeat issue): Agencies' controls over administration of user access to critical systems should:
  • retain documentation of approvals to create, modify and deactivate user access
  • allocate appropriate access rights
  • perform and document regular user access reviews
  • log and monitor privileged/super user account activity
  • deactivate terminated user access on a timely basis.
3.3 Annual work program
Errors continue to be identified in the Crown land database.

Instances were identified where Crown land was not recognised by the appropriate entity, or was recognised by more than one entity.
Recommendation: The Department should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.
Approximately 700 managers of Crown land do not submit financial statements required by the Public Finance and Audit Act 1983. NSW Treasury and the Department are continuing work to clarify reporting arrangements for these entities.
3.4 Managing maintenance
Some cluster agencies do not monitor their backlog maintenance. Consequently, the total backlog maintenance in the Industry cluster is unknown. This impacts the reliability and consistency of information about assets and their condition. When backlog maintenance is unknown, it is difficult for agencies to develop an accurate and effective maintenance plan that focuses on areas of highest need. It also means agencies' maintenance plans are reactive rather than preventative.
Effective maintenance planning helps agencies to:
  • quantify and budget asset maintenance costs
  • support service delivery at the lowest possible long-term cost
  • reduce service disruptions and losses due to asset failure
  • identify and respond to risks posed by the age and condition of assets.
Recommendation: Cluster agencies should develop an asset maintenance plan and complete an assessment of the condition of their assets to identify any maintenance backlogs. 
Maintenance budgets in some cluster agencies are not set based on actual maintenance needs. Recommendation: Cluster agencies should set their maintenance budgets based on identified maintenance needs to more accurately budget and prioritise expenditure.

Agencies in the Industry cluster provide services across a wide variety of areas. This chapter outlines certain service delivery outcomes for 2017–18 for the Industry cluster. It provides important contextual information about the cluster's operation, but the data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Procurement and reporting of consultancy services

Procurement and reporting of consultancy services

Finance
Education
Community Services
Industry
Justice
Planning
Premier and Cabinet
Health
Treasury
Transport
Environment
Information technology

Agencies need to improve their compliance with requirements governing the procurement of consultancy services. These requirements help agencies access procurement savings. Also, some agencies have under-reported consultancy fees in their annual reports for the 2016-17 financial year, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The report examined twelve agencies' compliance with procurement and reporting obligations for consultancy services. It notes that it is difficult to quantify total government expenditure on consultants as agencies define ‘consultants’ differently.

NSW Government agencies engage consultants to provide professional advice to inform their decision‑making. The spend on consultants is measured and reported in different ways for different purposes and the absence of a consistently applied definition makes quantification difficult.

The NSW Government’s procurement principles aim to help agencies obtain value for money and be fair, ethical and transparent in their procurement activities. All NSW Government agencies, with the exception of State Owned Corporations, must comply with the NSW Procurement Board’s Direction when engaging suppliers of business advisory services. Business advisory services include consultancy services. NSW Government agencies must disclose certain information about their use of consultants in their annual reports. The table below illustrates the detailed procurement and reporting requirements.

  Relevant guidance Requirements
Procurement of consultancy services PBD 2015 04 Engagement of major suppliers of consultancy and other services (the Direction) including the Standard Commercial Framework
(revised on 31 January 2018, shortly before it was superseded by 'PBD 2018 01')
 
Required agencies to seek the Agency Head or Chief Financial Officer's approval for engagements over $50,000 and report the engagements in the Major Suppliers' Portal (the Portal). 
  PBD 2018 01 Engagement of professional services suppliers
(replaced 'PBD 2015 04' in May 2018)
Requires agencies to seek the Agency Head or Chief Financial Officer's approval for engagements that depart from the Standard Commercial Framework and report the engagements in the Portal. Exhibit 3 in the report includes the key requirements of these three Directions.
 
Reporting of consultancy expenditure Annual Reports (Departments) Regulation 2015 and Annual Reports (Statutory Bodies) Regulation 2015 Requires agencies to disclose, in their annual reports, details of consultants engaged in a reporting year.
  Premier's Memorandum 
'M2002 07 Engagement and Use of Consultants'
 
Outlines additional reporting requirements for agencies to describe the nature and purpose of consultancies in their annual reports.

We examined how 12 agencies complied with their procurement and reporting obligations for consultancy services between 1 July 2016 and 31 March 2018. Participating agencies are listed in Appendix two. We also examined how NSW Procurement supports the functions of the NSW Procurement Board within the Department of Finance, Services and Innovation.

This audit assessed:

  • agency compliance with relevant procurement requirements for their use of consultants
  • agency compliance with disclosure requirements about consultancy expenditure in their annual reports 
  • the effectiveness of the NSW Procurement Board (the Board) in fulfilling its functions to oversee and support agency procurement of consultancy services. 
Conclusion
No participating agency materially complied with procurement requirements when engaging consultancy services. Eight participating agencies under reported consultant fees in their annual reports. The NSW Procurement Board is not fully effective in overseeing and supporting agencies' procurement of consultancy services.
All 12 agencies that we examined did not materially comply with the NSW Procurement Board Direction for the use of consultants between 1 July 2016 and 31 March 2018. 
Eight agencies did not comply with annual reporting requirements in the 2016–17 financial reporting year. Three agencies did not report expenditure on consultants that had been capitalised as part of asset costs, and one agency did not disclose consultancy fees incurred by its subsidiaries. Agencies also defined ‘consultants’ inconsistently.
The NSW Procurement Board's Direction was revised in January 2018, and mandates the use of the Standard Commercial Framework. The Direction aims to drive value for money, reduce administrative costs and simplify the procurement process. In practice, agencies found the Framework challenging to use. To better achieve the Direction’s intent, the Board needs to simplify procurement and compliance processes. 
The Board is yet to publish any statistics or analysis of agencies’ procurement of business advisory services due to issues with the quality of data and systems limitations. Also, the Board’s oversight of agency and supplier compliance with the Framework is limited as it relies on self reporting, and the information provided is insufficient to properly monitor compliance. NSW Procurement is yet to develop an effective procurement and business intelligence system for use by government agencies. Better procurement support, benefit realisation monitoring and reporting by NSW Procurement will help promote value for money in the engagement of consultants.

Published

Actions for Matching skills training with market needs

Matching skills training with market needs

Industry
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Workforce and capability

The NSW Department of Industry targets subsidies towards training programs delivering skills most needed in New South Wales. However, the Department still provides subsidies to qualifications that the market may no longer need, according to a report released by Margaret Crawford, Auditor-General for New South Wales. 

In 2012, governments across Australia entered into the National Partnership Agreement on Skills Reform. Under the National Partnership Agreement, the Australian Government provided incentive payments to States and Territories to move towards a more contestable Vocational Education and Training (VET) market. The aim of the National Partnership Agreement was to foster a more accessible, transparent, efficient and high quality training sector that is responsive to the needs of students and industry. 

The New South Wales Government introduced the Smart and Skilled program in response to the National Partnership Agreement. Through Smart and Skilled, students can choose a vocational course from a list of approved qualifications and training providers. Students pay the same fee for their chosen qualification regardless of the selected training provider and the government covers the gap between the student fee and the fixed price of the qualification through a subsidy paid to their training provider. 

Smart and Skilled commenced in January 2015, with the then Department of Education and Communities having primary responsibility for its implementation. Since July 2015, the NSW Department of Industry (the Department) has been responsible for VET in New South Wales and the implementation of Smart and Skilled. 

The NSW Skills Board, comprising nine part-time members appointed by the Minister for Skills, provides independent strategic advice on VET reform and funding. In line with most other States and Territories, the Department maintains a 'Skills List' which contains government subsidised qualifications to address identified priority skill needs in New South Wales.

This audit assessed the effectiveness of the Department in identifying, prioritising, and aligning course subsidies to the skill needs of NSW. To do this we examined whether:

  • the Department effectively identifies and prioritises present and future skill needs 
  • Smart and Skilled funding is aligned with the priority skill areas
  • skill needs and available VET courses are effectively communicated to potential participants and training providers.

Smart and Skilled is a relatively new and complex program, and is being delivered in the context of significant reform to VET nationally and in New South Wales. A large scale government funded contestable market was not present in the VET sector in New South Wales before the introduction of Smart and Skilled. This audit's findings should be considered in that context.
 

Conclusion
The Department effectively consults with industry, training providers and government departments to identify skill needs, and targets subsidies to meet those needs. However, the Department does not have a robust, data driven process to remove subsidies from qualifications which are no longer a priority. There is a risk that some qualifications are being subsidised which do not reflect the skill needs of New South Wales. 
The Department needs to better use the data it has, and collect additional data, to support its analysis of priority skill needs in New South Wales, and direct funding accordingly.
In addition to subsidising priority qualifications, the Department promotes engagement in skills training by:
  • funding scholarships and support for disadvantaged students
  • funding training in regional and remote areas
  • providing additional support to deliver some qualifications that the market is not providing.

The Department needs to evaluate these funding strategies to ensure they are achieving their goals. It should also explore why training providers are not delivering some priority qualifications through Smart and Skilled.

Training providers compete for funding allocations based on their capacity to deliver. The Department successfully manages the budget by capping funding allocated to each Smart and Skilled training provider. However, training providers have only one year of funding certainty at present. Training providers that are performing well are not rewarded with greater certainty.

The Department needs to improve its communication with prospective students to ensure they can make informed decisions in the VET market.

The Department also needs to communicate more transparently to training providers about its funding allocations and decisions about changes to the NSW Skills List. 

The NSW Skills List is unlikely to be missing high priority qualifications, but may include lower priority qualifications because the Department does not have a robust process to identify and remove these qualifications from the list. The Department needs to better use available data, and collect further data, to support decisions about which qualifications should be on the NSW Skills List.

The Department relies on stakeholder proposals to update the NSW Skills List. Stakeholders include industry, training providers and government departments. These stakeholders, particularly industry, are likely to be aware of skill needs, and have a strong incentive to propose qualifications that address these needs. The Department’s process of collecting stakeholder proposals helps to ensure that it can identify qualifications needed to address material skill needs. 

It is also important that the Department ensures the NSW Skills List only includes priority qualifications that need to be subsidised by government. The Department does not have robust processes in place to remove qualifications from the NSW Skills List. As a result, there is a risk that the list may include lower priority skill areas. Since the NSW Skills List was first created, new additions to the list have outnumbered those removed by five to one.

The Department does not always validate information gathered from stakeholder proposals, even when it has data to do so. Further, its decision making about what to include on, or delete from, the NSW Skills List is not transparent because the rationale for decisions is not adequately documented. 

The Department is undertaking projects to better use data to support its decisions about what should be on the NSW Skills List. Some of these projects should deliver useful data soon, but some can only provide useful information when sufficient trend data is available. 

Recommendation

The Department should: 

  • by June 2019, increase transparency of decisions about proposed changes to the NSW Skills List and improve record-keeping of deliberations regarding these changes
  • by December 2019, use data more effectively and consistently to ensure that the NSW Skills List only includes high priority qualifications
The Department funds training providers that deliver qualifications on the NSW Skills List. Alignment of funding to skill needs relies on the accuracy of the NSW Skills List, which may include some lower priority qualifications.

Only qualifications on the NSW Skills List are eligible for subsidies under Smart and Skilled. As the Department does not have a robust process for removing low priority qualifications from the NSW Skills list, some low priority qualifications may be subsidised. 

The Department allocates the Smart and Skilled budget through contracts with Smart and Skilled training providers. Training providers that meet contractual obligations and perform well in terms of enrolments and completion rates are rewarded with renewed contracts and more funding for increased enrolments, but these decisions are not based on student outcomes. The Department reduces or removes funding from training providers that do not meet quality standards, breach contract conditions or that are unable to spend their allocated funding effectively. Contracts are for only one year, offering training providers little funding certainty. 

Smart and Skilled provides additional funding for scholarships and for training providers in locations where the cost of delivery is high or to those that cater to students with disabilities. The Department has not yet evaluated whether this additional funding is achieving its intended outcomes. 

Eight per cent of the qualifications that have been on the NSW Skills List since 2015 are not delivered under Smart and Skilled anywhere in New South Wales. A further 14 per cent of the qualifications that are offered by training providers have had no student commencements. The Department is yet to identify the reasons that these high priority qualifications are either not offered or not taken up by students.

Recommendation

The Department should:

  • by June 2019, investigate why training providers do not offer, and prospective students do not enrol in, some Smart and Skilled subsidised qualifications 
  • by December 2019, evaluate the effectiveness of Smart and Skilled funding which supplements standard subsidies for qualifications on the NSW Skills List, to determine whether it is achieving its objectives
  • by December 2019, provide longer term funding certainty to high performing training providers, while retaining incentives for them to continue to perform well.
The Department needs to improve its communication, particularly with prospective students.

In a contestable market, it is important for consumers to have sufficient information to make informed decisions. The Department does not provide some key information to prospective VET students to support their decisions, such as measures of provider quality and examples of employment and further education outcomes of students completing particular courses. Existing information is spread across numerous channels and is not presented in a user friendly manner. This is a potential barrier to participation in VET for those less engaged with the system or less ICT literate.

The Department conveys relevant information about the program to training providers through its websites and its regional offices. However, it could better communicate some specific information directly to individual Smart and Skilled training providers, such as reasons their proposals to include new qualifications on the NSW Skills List are accepted or rejected. 

While the Department is implementing a communication strategy for VET in New South Wales, it does not have a specific communications strategy for Smart and Skilled which comprehensively identifies the needs of different stakeholders and how these can be addressed. 

Recommendation

By December 2019, the Department should develop and implement a specific communications strategy for Smart and Skilled to:

  • support prospective student engagement and informed decision making
  • meet the information needs of training providers 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #305 - released 26 July 2018

Published

Actions for Transport 2017

Transport 2017

Transport
Asset valuation
Information technology
Internal controls and governance
Project management

The following report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, the report notes the agencies can improve their asset revaluation processes.

1. Financial reporting and controls

Audit opinions

Unqualified audit opinions were issued for all agencies' financial statements.

Early close

Early close procedures continue to facilitate timely preparation of financial statements and completion of audits, but agencies can improve their asset revaluation processes. The revaluations were not completed by the early close deadline.
Key audit matters The cluster corrected the value of rail tunnels and earthworks by recording an additional $8.5 billion in infrastructure assets.
Passenger revenue and patronage Revenue increased by seven per cent at a similar rate to patronage. Opal fare structure changes came into effect on 5 September 2016. Continued rises in patronage can increase pressure on public transport punctuality.
Negative balances on Opal Cards

There was $2.6 million in revenue not collected during 2016–17 financial year through negative balance Opal Cards. This represents 0.2 per cent of total annual passenger revenue. Transport advise the cumulative balance of negative balance Opal Cards is $4.2 million as at 30 June 2017.

Recommendation: Transport for NSW (TfNSW) should implement measures to prevent loss of revenue from passengers tapping off with negative balance Opal Cards.

Investment in infrastructure Agencies spent $8.5 billion on assets in 2016–17 and have contractual capital commitments of $11.3 billion over the next five years.
Internal controls IT systems user access administration remains an area of weakness.


2. Service Delivery

Punctuality According to Transport data, average punctuality is above target for Sydney Trains, Ferries and Light Rail, but below target for NSW Trains services. State Transit Authority of NSW (STA) is not meeting punctuality targets. STA continued working with TfNSW on delivering improved punctuality.
Public transport capacity Passenger crowding is above benchmark for many morning peak suburban rail services, as indicated by Transport data. Eleven of the 14 bus contract regions had full buses.

Bus crowding

There are no target measures on crowding for bus operators in any contract region.

Recommendation: TfNSW should develop target measures on crowding for bus operators in all contract regions and publish the results.

Customer satisfaction

Surveys conducted by Transport indicate customer satisfaction exceeded target for all modes of public transport.

This report provides Parliament and other users of Transport cluster agencies' financial statements with audit results, observations, conclusions and recommendations in the following areas:

  • Financial reporting and controls
  • Service delivery.

Confidence in public sector decision-making and transparency is enhanced when financial reporting is accurate and timely. Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies.

This chapter outlines our audit observations, conclusions or recommendations related to financial reporting and controls of Transport cluster agencies for 2016–17.

Observation Conclusion or recommendation
Quality of financial reporting
Unqualified opinions were issued for all agencies’ financial statements. Unqualified audit opinions were issued on the 2016–17 financial statements of all agencies in the Transport cluster. Agencies complied with the new disclosure requirements required under accounting standard AASB 124 'Related Party Disclosures'.
Old tunnels and earthworks valued. The cluster corrected the value of rail tunnels and earthworks by recording an additional $8.5 billion in infrastructure assets.
Timeliness of financial reporting  
Most agencies complied with the statutory timeframes for completion of early close procedures and preparation and audit of financial statements. Early close procedures continue to facilitate timely preparation of financial statements and completion of audits, but agencies can make further improvement in the revaluation process.
TfNSW and RailCorp completed asset revaluations after the early close deadline. While all revaluation matters were resolved and corrected, completing the revaluation process earlier would enable more timely review, identification and resolution of matters.
Passenger revenue, patronage and cost recovery
Revenue increased by 7 per cent at a similar rate to patronage. Public transport passenger revenue increased by $93 million (seven per cent) in 2016–17, and patronage increased by 49 million (seven per cent) across all modes of transport. There were some changes in the method of calculating reported patronage between 2015–16 and 2016–17. If the methods had been consistent, the patronage increase would be 6.5 per cent. Opal fare structure changes came into effect on 5 September 2016.
Value of negative balance Opal Cards doubled since last year.

There was $2.6 million in revenue not collected during 2016–17 financial year through negative balance Opal Cards. This represents 0.2 per cent of total annual passenger revenue. Transport advise the cumulative balance of negative balance Opal Cards is $4.2 million as at 30 June 2017.

Recommendation: TfNSW should implement measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

The overall cost recovery from users of public transport increased slightly to 21.3 per cent. Cost of service per passenger journey for buses and ferries decreased. Revenue per passenger journey for all modes remained fairly stable.
Investment in infrastructure
There was a significant investment in transport assets in 2016–17. Agencies spent $8.5 billion on assets in 2016–17, including $3.8 billion on rail systems and $3.8 billion on road and maritime infrastructure systems.
Transport cluster have capital commitment of $11.3 billion over the next five years.
 
The transport cluster has significant contractual commitments over the next five years on rail and road infrastructure projects.
 

Internal controls

User access administration over systems remains an area of weakness. We identified six moderate and eight low risk issues related to user systems access administration across four agencies. This included review of highly privileged/super user account transactions not performed effectively and user access reviews not performed. These weaknesses increase the risk of users having excessive or unauthorised access to critical financial systems and information.

Achievement of government outcomes can be improved through effective delivery of the right mix of services, whether from the public, private or not‑for‑profit sectors. Service delivery reform will be most successful if there is clear accountability for service delivery outcomes, decisions are aligned to strategic direction and performance is monitored and evaluated.

This chapter outlines our audit observations, conclusions or recommendations related to service delivery in the Transport cluster agencies for 2016–17.

Observations Conclusion or recommendation

Punctuality

Average punctuality is above target for Sydney Trains, but below target for NSW Trains services. Punctuality targets are not met by all bus operators. Meeting punctuality targets is a continuing challenge for NSW Trains’ and STA bus services.
The 2017 performance audit 'Passenger Rail Punctuality' reported that based on forecast patronage increases, rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. The 2017 performance audit found that given the likely lead times involved with major infrastructure projects, there remains a significant risk of poor punctuality after 2019. Transport advised it is currently either delivering or planning rail network upgrades to address current growth and longer-term future demand. This includes investments such as procurement of suburban and intercity trains, Sydney Metro services and further timetable planning into the 2020s.
 
After reaching its punctuality target in 2015–16 for the first time in 13 years, NSW Trains regional services was below the target in 2016–17. NSW Trains regional services achieved an average of 75 per cent punctuality in 2016–17, four per cent less than 2015–16.
The bus contracts do not have an option to impose financial penalties on STA for poor punctuality performance. In 2015–16, we recommended TfNSW should consider including financial penalties for not meeting each punctuality KPI in future contracts with bus operators. An opportunity to implement the recommendation requires a contract renewal process to be finalised with STA, which did not occur during 2016–17.

Public transport capacity

There are no target measures on crowding for bus operators in any contract region. Recommendation: TfNSW should develop target measures on crowding for bus operators in all contract regions and publish the results.

Customer Satisfaction

Customers on ferries continued to be most satisfied, followed by those on light rail. Sydney Trains and NSW Trains had fewer complaints in 2016–17. Customer satisfaction exceeded target for all modes of transport.

Project management

Transport cluster manages many of the State high profile/high risk projects. Major Transport projects include WestConnex, Sydney Metro Northwest, Sydney Metro City and Southwest, Woolgoolga to Ballina - Pacific Highway upgrade, NorthConnex, CBD and South East Light Rail and Newcastle Light Rail.
Safety performance
Road fatalities decreased by eight per cent between July 2016 and June 2017, from 390 to 359 deaths. Road fatalities mainly involved speed, fatigue and vehicle occupants not wearing available restraints.
 

Maintenance

RMS’ maintenance backlog of $3.7 billion is higher than the $3.4 billion reported in 2016. Transport cluster agencies manage $134 billion in property, plant and equipment. The total backlog maintenance of $4.1 billion at 30 June 2017 represents 3.1 per cent of those assets.

Published

Actions for Industry 2017

Industry 2017

Industry
Asset valuation
Compliance
Internal controls and governance
Procurement
Project management
Risk

The following report highlights the results of the financial audits of NSW Government entities in the Industry cluster. The report focuses on key observations and findings from the most recent audits of these entities.

The report notes that TAFE NSW will continue to incur extra costs each year to produce reliable financial information due to deficiencies in its student administration system. TAFE NSW plans to replace its Student Administration and Learning Management system in 2018-19 at an estimated cost of $89 million.

1. Financial reporting and controls

Financial reporting

Unqualified audit opinions were issued for 44 out of 48 financial statement audits with four audits incomplete. Early close procedures continue to promote earlier and better quality financial reporting.
Financial performance The cluster recorded a net deficit of $107 million in 2016–17 ($78.0 million in 2015–16). Contributing to the overall cluster net deficit was the Department's $226 million net deficit offset by net surpluses at Water NSW and the Forestry Corporation of New South Wales.
TAFE NSW continues to experience system issues TAFE NSW incurs extra costs each year to produce reliable financial information due to deficiencies in its student administration system. TAFE NSW plans to replace its Student Administration and Learning Management system in 2018–19 at an estimated cost of $89 million.
Internal controls

We identified 180 internal control issues, including 61 repeat issues across the cluster. We rated four of these issues as 'high' risk, 98 as ‘moderate’ risk and 78 as ‘low’ risk.

Of the 180 issues raised, 37 related to financial reporting and 52 related to controls over processes such as procurement and fixed assets.

Some internal control issues and recommendations identified in previous years, have been repeated and should be addressed promptly to reduce risks and improve processes.

Deficient user administration access Agencies need to strengthen user access administration to critical financial systems.

2. Service delivery

Premier and State Priorities    

Australian Bureau of Statistics data shows the Premier's priority for job creation has been achieved.

While performance has declined for the State priority to increase the proportion of people completing apprenticeships and traineeships, the Department advises it has initiatives in place to achieve this State priority, and the State priority for New South Wales to lead Australia in business confidence.

Crown land   The Department is working to respond to the recommendations from a Parliamentary Inquiry into Crown Land and to implement the revised framework contained in the Crown Land Management Act 2016.
Aboriginal land claims

Despite a continued focus, the Department has been unsuccessful in reducing the number of unprocessed Aboriginal land claims.

The Department should continue to implement measures to reduce the backlog of unprocessed Aboriginal land claims.

This report focuses on agencies in the Industry cluster. The report focuses on audit results, observations, conclusions and recommendations for financial reporting and controls, and service delivery.

This cluster leads the State's promotion of New South Wales as the place to invest and produce goods and services. Significant cluster agencies deliver services in the following areas:

Confidence in public sector decision-making and transparency is enhanced when financial reporting is accurate and timely. Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies.

This chapter outlines audit observations, conclusions and recommendations for the financial reporting and controls of agencies in the cluster for 2016–17.

Observation Conclusion or recommendation
2.1 Quality of financial reporting
Unqualified audit opinions were issued for 44 out of 48 financial statement audits. Four audits are continuing. Ongoing improvements in the preparation of financial statements helped identify and resolve material issues.
The number of misstatements within the cluster fell from 104 in 2015–16 to 70 in 2016–17. The ‘early close procedures’ initiative introduced by the Treasury in 2011–12 has reduced the number of misstatements each year.
2.2 Timeliness of financial reporting
Most agencies complied with the Treasury’s early close procedures and the timetable for the preparation and audit of financial statements. Greater focus on financial reporting and effective early close procedures has improved the timeliness of financial reporting, but further improvements are required.
2.3 Key financial issues from cluster agencies
The Department of Industry completed a revaluation of Crown land and continues work on improving the accounting for Crown land. The value of Crown land recognised in the Department's financial statements at 30 June 2017 was $5.3 billion. The revaluation was carried out using a revised mass valuation approach which reduced complexity and subjectivity and improved transparency.
There is no process in place to ensure agencies recognise all the Crown land they manage and control. Recommendation: The Department should confirm the completeness and accuracy of the Crown land database with other organisations that manage and control Crown land to improve the reliability of its records.
TAFE NSW incurred approximately $6 million of direct costs to deal with issues in its student administration system and establish the integrity of its financial data for 2016–17. TAFE NSW will continue to incur extra costs each year to produce reliable financial information. TAFE NSW advises it intends to replace the Student Administration and Learning Management system it jointly implemented with the Department of Education three years ago at a cost $40.2 million. TAFE plans to implement the new system in 2018–19 at an estimated cost of $89 million.
 
2.4 Key financial information  
The cluster recorded a net deficit of $107 million in 2016–17 ($78.0 million in 2015–16). The overall cluster net deficit included the Department's $226 million net deficit which was partly offset by net surpluses in a number of other agencies, including Water NSW and the Forestry Corporation of New South Wales. Most agencies in the cluster, including the Department, but excluding the State owned corporations, are dependent on the NSW Government for the majority of their revenue.
 
2.5 Financial performance and sustainability  
We assessed the performance of certain agencies against key financial sustainability indicators. This identified four agencies with adjusted net deficits and two agencies with liquidity ratios below one. Overall, based on our analysis these agencies are not at high risk of sustainability concerns.
2.6 Internal controls  
A significant number of repeat internal control issues were again raised with management for certain agencies in the cluster.
 
Recommendation (repeat issue): Internal control issues and recommendations from previous years should be addressed promptly to reduce risks and improve processes.
User access administration over financial systems needs to be improved. 17 moderate risk issues related to user access administration across nine agencies were identified.

Recommendation: Agencies should ensure administration of user access to critical systems

  • retains documentation of approvals to create, modify and deactivate user access
  • allocates appropriate access rights
  • performs and documents regular user access reviews
  • logs and monitors privileged/super user account activity
  • deactivates terminated user access on a timely basis
  • does not allow shared generic user accounts, instead of unique user accounts for staff performing administration tasks.

Government outcomes can be achieved by delivering services through a mix of the public, private or not-for-profit sectors. Service delivery reform is most successful if there is clear accountability for service delivery outcomes, decisions are aligned to the government's strategic direction, and performance and value for money are monitored and evaluated.

This chapter outlines our audit observations, conclusions and recommendations for the service delivery of agencies in the cluster for 2016–17.

Issues Conclusion or recommendation

3.1 Measuring and reporting on performance

The Department is responsible for two State priorities (increasing apprenticeships and business confidence) and the Premier's priority of creating jobs. The Department also supports four state priorities. Australian Bureau of Statistics data shows the Premier's priority for job creation continues to be achieved. The Department reported that the number of people completing apprenticeships and traineeships had declined to 59 per cent against a 2019 target of 65 per cent, while the State was ranked first or second on a range of business confidence indicators.

3.2 Improvements required in the administration of Crown land

The Department faces many challenges in the administration of Crown land. These challenges range from inadequate systems and processes through to satisfying competing commercial, environmental, and community interests.

The Department has implemented, or is implementing the recommendations from a performance audit on the Sale and Lease of Crown land and the Parliamentary Inquiry into Crown land.

It is also implementing the revised framework for Crown land contained in the Crown Land Management Act 2016.

3.3 Aboriginal land claims over Crown land

The number of unprocessed Aboriginal land claims continues to increase. Work on finalising Aboriginal Land Agreements, which may help address the claims backlog, is continuing. Recommendation (repeat Issue): The Department should continue to implement measures to reduce the number of unprocessed Aboriginal land claims.
 

3.4 Skills development

Eleven contracted Smart and Skilled service providers had their contracts cancelled for quality issues. There were 391 providers of Smart and Skilled qualifications as at October 2017. The Department of Industry spent $1.4 billion on the provision of vocational education and training. The Department has controls in place to monitor the performance of contracted service providers to ensure quality delivery of training.

Published

Actions for State Finances 2017

State Finances 2017

Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Treasury
Universities
Whole of Government
Environment
Asset valuation
Financial reporting
Information technology
Internal controls and governance

Total State Sector Accounts received an unqualified audit opinion for the fifth consecutive year.

There was a $5.7 billion State budget surplus and continued investment in new infrastructure, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets. This report also comments on key accounting matters, including the correction of some previously reported balances and the first time reporting of combined Cabinet members’ compensation in the Total State Sector Accounts.

Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2017.

You will note that the format of this report has changed from previous years.

The intent of this change is to draw attention to the key matters that have been the focus of our audit and highlight significant factors that have contributed to the outcome.

First, it is pleasing to report once again that I issued a clear audit opinion on the State’s consolidated financial statements. This outcome demonstrates the Government’s continued focus on the quality of financial reporting across the NSW public sector.

High quality financial management and reporting are crucial to properly inform the public and build community confidence in our system of government.

The Treasury’s Financial Management Transformation program also aims to improve financial governance, budgeting and reporting arrangements across the sector. My Office is working collaboratively with The Treasury on reforms to reduce the burden of reporting, without weakening established safeguards.

The reforms should include measures to provide independent assurance of the budget process, of outcome reporting by agencies, and the power to “follow the dollar” given the increasing use of non-government organisations to deliver Government programs.

This Report also highlights another year of strong financial performance. The State’s budget result was a $5.7 billion surplus, and investment in new infrastructure has continued, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets.

Finally, could I take this opportunity to thank the staff of The Treasury for the way they approached this audit. Our partnership is critical to ensuring NSW is an exemplar of quality financial management and reporting.

02_Margaret_signature.jpg

Margaret Crawford 
24 October 2017

A clear audit opinion on the State’s consolidated financial statements was issued.

Timely and accurate financial reporting is essential for informed decision making, effective management of public funds and enhancing public accountability.

This year’s clear audit opinion reflects the Government’s continued efforts to improve the quality of financial reporting across the NSW public sector.

Since the introduction of ‘early close procedures’ in 2011-12, the number of significant errors in financial statements of agencies has generally fallen largely due to identifying and resolving complex accounting issues early. Agencies’ 2016-17 financial statements submitted for audit contained nine errors exceeding $20 million. All errors were subsequently corrected in the individual agencies financial statements.

Agencies should continue to respond to key accounting issues as soon as they are identified. Where issues are identified, accounting position papers should be prepared for consideration by the Audit Office, their Audit and Risk Committee members, and when relevant, The Treasury.

The State addressed the following key accounting matters during 2016-17. 

The State recognised rail tunnels and earthworks valued at $8.5 billion.

Some rail tunnels and earthworks have never been valued by the State. These include the City Circle, the country rail network and other tunnels and earthworks built before the year 2000. Some of these tunnels and earthworks date back to the early 1900s.

For many years, the State did not account for these assets as they believed that their value could not be reliably measured. This year an independent valuer was engaged to perform a comprehensive valuation. The methodology used demonstrated
that the assets could have been reflected in the financial statements earlier.

The State recorded an additional $8.5 billion to correct the value of infrastructure assets at 1 July 2016.

Cabinet member’s compensation and related party transactions were reviewed.

Due to changes in Accounting Standards, the State had to consider 'related party information' in the financial statements. Previously this only applied to for-profit entities.

This year, requirements to report related party information extended to members of Cabinet, considered to be “key management personnel” of the State, as defined by Accounting Standards.

The Treasury implemented a process to assess and report Cabinet member’s compensation, and transactions between Cabinet members and/or their close family members, and government agencies.

Collectively, Cabinet members’ remuneration was $8.8 million, which was mainly salaries and allowances, and $3.5 million of non-monetary benefits such as security and drivers. The Treasury determined there were no other specific “related party” transactions or balances that required disclosure in the State’s financial statements.

Information system limitations continue at TAFE NSW.

TAFE NSW has experienced ongoing issues with its student administration system.

TAFE NSW has again implemented additional processes to verify the accuracy and completeness of revenue from sales of goods and services.

TAFE NSW expects to spend up to $89 million on a new information system to address these issues. Modules of the new student enrolment system are expected to be in place for the 2018 enrolment period.

Restatements relating to the General Government Sector's investment in the commercial sector.

The State corrected two previously reported balances relating to the General Government Sector’s investment in the commercial sector.

Accounting Standards require the General Government Sector to effectively store gains or losses related to its investment in the commercial sector in reserves until the investment is derecognised.

When these investments are disposed of, the cumulative gains and losses must be cleared and recognised in the operating result. However, the Government had previously cleared the cumulative gains and losses directly to Accumulated Funds within equity.

To comply with Accounting Standards, a total of $6 billion previously reported as a movement in equity  at 30 June 2016, has now been corrected to the operating result.

In addition, Accounting Standards only allow gains or losses on its investments to be stored in reserves. In past years, the State recognised all changes in the value of its investment in Available for Sale Reserves, including the capital contributed to establish the State’s investment. In 2016-17, a total of $23.4 billion of contributed capital was corrected to accumulated funds at 1 July 2015.

The State’s budget result was a $5.7 billion surplus, $2.0 billion higher than the budget estimate.

The Total State Sector comprises 310 entities controlled by the NSW Government.

Of the total, the General Government Sector comprises 215 entities that provide goods and services not directly paid for by consumers.

The non-General Government Sector comprises 95 Government businesses that provide goods and services such as water and electricity, or financial services.

A principal measure of a Government’s overall performance is its Net Operating Balance, or Budget Result. The Net Operating Balance reports the difference between the cost of General Government service delivery and the revenue earned to fund these sectors.

The State has recorded budget surpluses and exceeded the original budget result in nine of the last ten years.

The State maintained its AAA credit rating.

The object of the Act is to maintain the AAA credit rating.

NSW’s finances are managed in alignment with the Fiscal Responsibility Act 2012 (the Act).

The Act established the framework for fiscal responsibility and strategy needed to protect the State’s AAA credit rating and service delivery to the people of NSW.

The purpose of maintaining the AAA credit rating is to reduce the cost of, and ensure the broadest access to, borrowings.

A triple-A credit rating also helps maintain business and consumer confidence so economic activity and employment are sustained. The legislation sets out targets and principles for financial management to achieve this.

New South Wales has credit ratings of AAA/Negative from Standard & Poor’s and Aaa/Stable from Moody’s Investors Service.

The fiscal targets for achieving this objective are:

General Government expenditure growth is lower than long term revenue growth.

General Government expenditure growth was 4.2 per cent in 2016-17, below the long-term revenue growth of 5.6 per cent.

Eliminating unfunded superannuation liabilities by 2030.

The Act sets a target of eliminating unfunded defined benefit superannuation liabilities by 2030. The State’s net superannuation liability was $58.6 billion at 30 June 2017 ($71.2 billion at 30 June 2016).

The Government predicts the 2030 target will be achieved. The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2016-17, the State made employer contributions of $1.5 billion, which is largely consistent with contributions over the past five years.

The liability values in the graph below do not reflect the values recorded in the Total State Sector Accounts. For financial reporting purposes, Accounting Standards (AASB 119 Employee Benefits) require the State to discount its superannuation liability using the government bond rate (refer to page 10 of this report). 

The relevant government bond rate in the current economic climate is 2.62 per cent.

The State’s target for the unfunded superannuation liability is measured using AASB 1056 Superannuation Entities. This is because it adopts a measurement basis that reflects expected earnings on fund assets, which are currently between 5.9 and 7.4 per cent. Using these rates, the liability is $15.0 billion at 30 June 2017 ($16.1 billion at 30 June 2016). The unfunded liability is $2.4 billion less than when the Act was introduced.

The State’s assets grew by $31.6 billion during 2016-17 to $409 billion.

Valuing the State’s physical assets.

When we audit the financial statements, we focus on areas we consider as higher risk. These areas are often complex, and require the use of estimates and judgements.

The State has $307.2 billion of physical assets measured at fair value in accordance with Australian Accounting Standards. Fair value calculations are inherently complex and sensitive to assumptions and estimates, increasing the risk these assets are incorrectly valued.

In our audits, we assess the reasonableness and appropriateness of assumptions used in valuing physical assets. This includes obtaining an understanding of the valuation methodologies applied and judgements made. We also review the completeness of asset registers, and the mathematical accuracy of valuation models.

Net movements between years includes additions, disposals, depreciation and valuations. This year, valuations of physical assets added $16.2 billion to the State’s assets, comprising: 

  • Transport for NSW and Railcorp $8.5 billion

  • New South Wales Land and Housing Corporation $4.8 billion

  • Roads and Maritime Services $930 million

  • Crown Entity $400 million.    

The State’s financial assets increased $27.5 billion in 2016-17

The State’s financial assets have increased by 88 per cent over the past four years. In 2016-17, financial assets increased primarily due to proceeds from the sale of government assets and businesses.

The Government implemented reforms to better use the State’s financial assets. A key element was the creation of an Asset and Liability Committee (ALCO) to provide advice on ways to improve balance sheet management.

Since the creation of the ALCO, reforms include:

  • Establishment of the New South Wales Infrastructure Future Fund (NIFF). The net proceeds from the State’s asset recycling program are invested into the NIFF, which is managed by TCorp, with a balance of $14.6 billion by 30 June 2017. Funds raised are invested through the NIFF until the Government requires them for critical infrastructure projects that are part of the Restart NSW and Rebuilding NSW program of works. ALCO and TCorp provide advice on the NIFF’s performance and management

  • Establishment of the Social and Affordable Housing Fund ($1.1 billion at 30 June 2017). ALCO oversees the Fund to ensure an appropriate investment approach that will maintain funding certainty for new social and affordable housing stock

  • Cash and liquidity management reforms to centralise cash previously held by agencies in the Treasury Banking System. This reform is designed to ensure agencies have adequate levels of liquidity but with surplus funds invested centrally for better returns.

The State’s liabilities decreased by $13.1 billion during 2016-17 to $182 billion.

Valuing the State’s liabilities relies on an actuarial assessment.

Nearly half of the State’s liabilities relate to its employees. This includes unfunded superannuation, and employee benefits, such as long service and recreation leave.

Valuation of these obligations is subject to complex estimation techniques and significant judgements. Small changes in assumptions can materially impact the financial statements.

We address the risk associated with auditing these balances:

  • using actuarial specialists

  • testing controls around underlying employee data used in data models, and testing the accuracy of the calculations

  • evaluating assumptions applied in calculating employee entitlements such as the discount rate and the probability of long service leave vesting conditions being met.

The State’s superannuation obligations reduced by $12.6 billion in 2016-17.

The State’s $58.6 billion superannuation liability represents obligations for past and present employees, less the value of assets set aside to meet those obligations. The superannuation liability decreased from $71.2 billion to $58.6 billion, largely due to an increase in the discount rate from 1.99 per cent to 2.62 per cent. This alone reduced the liability by $9.2 billion

The State’s borrowings totalled $70.6 billion at 30 June 2017.

The State’s borrowings totalled $70.6 billion at 30 June 2017, $9.5 billion less than the previous year. This was largely due to the repayment of borrowings when the assets of Ausgrid and Endeavour Energy were leased to the private sector.

TCorp issues bonds to raise funds for NSW Government agencies. The bonds are actively traded in financial markets providing price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.

The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.

General Government Sector debt is being restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to better match liabilities with the funding requirements of infrastructure assets and reduces refinancing risks. It also allows the Government to take advantage of the low interest rate environment.

The State recorded revenue of $83.5 billion in  2016-17, an increase of $5.3 billion from 2015-16.

The State’s results are underpinned by revenue growth in taxation, fees and fines.

Taxation, fees, fines and other revenue comprises $30.5 billion of taxation ($28.7 billion in 2015-16) and $5.3 billion of fees, fines and other revenue ($4.6 billion).

Tax revenue for the Total State Sector increased by $1.8 billion, or 6.4 per cent compared to 2015-16, primarily due to:

  • one-off business asset sales and lease transactions, including $718 million in transfer duty from the Ausgrid and Endeavour Energy lease transactions

  • $385 million increase in payroll tax from growth in NSW employment and average employee compensation

  • a $426 million increase in land taxes.

Growth in stamp duty is expected to slow over the next 4 years.

General Government Sector stamp duties have increased from $6.2 billion in 2012-13 to $11.5 billion in 2016-17, an annual average growth rate of 16.5 per cent. The Government’s budget forecasts the growth in stamp duties to decline, to an average annual growth rate of 2.6 per cent between 2016-17 and 2020-21.

The State received Commonwealth grants and subsidies of $30.8 billion in 2016-17.

The State received $30.8 billion from the Commonwealth Government in 2016-17, $1.6 billion more than in 2015-16. This was primarily due to transaction based asset recycling grants of $1.0 billion and a $720 million increase in national land transport grants. This increase was offset by a $435 million decrease in General Purpose Grants, which mainly comprises New South Wales’ share of the Goods and Services Tax (GST). 

The State spent $79.4 billion in 2016-17 to deliver services to the community, an increase of $3.9 billion from 2015-16.

Overall expenses increased 5.2 per cent from last year. Most of the increase was due to higher employee costs and operating costs.

Total salaries and wages increased by 4.2 per cent from 2015-16.

Total salaries and wages increased to $30 billion from $28.8 billion in 2015-16. The Government wages policy aims to limit the growth in remuneration and other employee costs to no more than 2.5 per cent per annum.

Operating expenses increased by 12.4 per cent from 2015-16.

Within operating expenses, payments for supplies, services and other expenses increased, in part, due to the State:

  • reacquiring mining licenses worth $482 million and additional land remediation costs of $101 million

  • spending more on health including additional drug supplies relating to Hepatitis C.

State spend on transport and communications increased by 68.1 per cent since 2012-13.

While spending on health and education remain the largest functional areas provided by Government, expenditure on transport and communication increased, on average, by 13.9 per cent annually between 2012-13 and 2016-17. This increase reflects the Government’s investment in transport infrastructure such as the Sydney Metro and Westconnex. Over the same period, spending on health increased by $3.9 billion.

Expenditure on fuel and energy has decreased by an average of 44.7 per cent since 2012-13, reflecting the State’s leases of electricity network assets.

In 2011, the Government established Restart NSW to fund high priority infrastructure projects.

Restart NSW projects are primarily funded from the proceeds from the asset recycling program enabling Government to deliver new infrastructure investment.

Restart NSW provides funding for the delivery of Rebuilding NSW, which is the Government’s 10-year plan to invest $20 billion in new infrastructure.

The State finalised long-term leases of Ausgrid and Endeavour Energy assets.

In June 2017, the Government finalised its long-term lease of 50.4 per cent of Endeavour Energy. This transaction follows on from the long-term leases of TransGrid in December 2015 and 50.4 per cent of Ausgrid in December 2016. Net proceeds of $15.0 billion were paid into Restart NSW relating to these transactions.

The Government also finalised an arrangement for the private sector to provide land titling and registry services to the public for 35 years. The State, through Restart NSW, received an upfront payment of $2.6 billion from the new operator.

Restart NSW is funding $29.8 billion of new infrastructure.

The Government has detailed its plan to invest $20 billion into the Rebuilding NSW plan from Restart NSW.

At 30 June 2017, around $2.9 billion has already been spent on Rebuilding NSW projects from Restart NSW, with a further $9 billion included in the budget aggregates. The Government has also earmarked a further $8.1 billion in Restart NSW for future projects.

The most significant project is the Sydney Metro. The Government has committed $7.0 billion from Restart NSW to build a 30-kilometre metro line, linking Sydney Metro Northwest at Chatswood, through new stations in the lower North Shore, the Sydney CBD and southwest to Bankstown. At 30 June 2017, $2.4 billion has been spent on this project from Restart NSW.

Other significant projects funded by Restart NSW include a $1.8 billion contribution to WestConnex and reserved funding of $1 billion towards the State’s Major Stadia Network program.

The Treasury initiated the Financial Management Transformation (FMT) program with the aim of changing and improving financial governance, budgeting and reporting arrangements of the New South Wales public sector.

FMT aims to deliver better outcomes for the people of New South Wales and focuses on transparency and accountability for expenditure, and better value for money.

New Financial Management System

PRIME is the Information Technology (IT) solution component of the FMT program, replacing several historical systems. PRIME will provide both financial and performance information within one IT platform for all agencies in the NSW public sector.

It is expected to give Government more timely information to plan and deliver its policy priorities and the budget.

Independent assurance over the budget process would improve confidence in the reliability of the State’s financial information.

Published

Actions for Passenger Rail Punctuality

Passenger Rail Punctuality

Transport
Information technology
Infrastructure
Service delivery

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

A NSW Government priority is to ‘maintain or improve reliability of public transport services over the next four years’. Punctuality is a key element of reliability, and the level of patronage is a critical factor in the ability to maintain punctuality. Increasing patronage places pressure on the length of time trains need to wait at stations to load and offload passengers which can lead to delays. The NSW Long Term Transport Master Plan forecasts that rail patronage could increase by 26 per cent between 2012 and 2031.  

Passenger rail services in NSW are provided under a purchaser-provider model. Transport for NSW enters contracts with:

  • Sydney Trains for Sydney suburban passenger rail services
  • NSW Trains for services that commence or terminate outside Sydney, including intercity services that operate between Central station and the South Coast, Southern Highlands, Blue Mountains and Central Coast and Newcastle.

Transport for NSW sets performance targets and standards for these services, develops the timetables, procures trains for the service providers, and is responsible for long term planning.

This audit assessed whether these rail agencies have plans and strategies to maintain or improve performance in getting the growing number of suburban and intercity rail passengers to their destinations on time.

Conclusion:

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

Transport for NSW has undertaken considerable work on developing strategies to increase capacity and maintain punctuality after 2019, but remains some way from putting a costed plan to the government. There is a significant risk that investments will not be made soon enough to handle future patronage levels. Ideally, planning and investment decisions should have been made already.

Punctuality measurement is satisfactory, but agencies could publish more information

Passenger rail punctuality indicators adopted in NSW are good practice. The key train punctuality indicator is better than indicators used by many other rail operators. It is also better than the on-time-running indicator that it replaced. Unlike the on-time-running indicator, the punctuality indicator classifies trains that have been cancelled or skipped stations as late and results are not adjusted to take account of delays caused by factors such as extreme weather or police operations.

NSW also has a customer delay measure which represents good practice. Work has started on refining and embedding customer delay as a key performance measure for the planned new Rail Operations Centre.

As train frequency approaches a ‘turn up and go’ level of service, rather than running to a timetable, more emphasis will need to be placed on excess waiting time and customer delay when assessing performance.

Measurement of punctuality is reasonably precise. There are some measurement inaccuracies which should be addressed, such as the estimated arrival time of a train being incorrect at some destination stations, but these do not affect punctuality results materially.  

Train punctuality is reported publicly, but not to the detail of the indicators in the contracts between Transport for NSW and Sydney Trains and NSW Trains. There is very limited public reporting of customer delay.

Overall punctuality is good, but some services are relatively poor

System-wide train punctuality has usually exceeded target since 2005, but some services suffer from poor punctuality compared to the rest of the network.  

The part of the network around North Sydney is creating problems for the punctuality of afternoon peak services heading through it and out to Western Sydney and to Hornsby via Strathfield. Transport for NSW and Sydney Trains are well advanced with strategies to address this up to 2019.  

The East Hills express trains in the afternoon peak also performed well below target. The rail agencies recently analysed this issue and believe it relates to the train timetable and signalling which restricts how close trains can run behind each other into Campbelltown. It further advises that this will be corrected over the next three years.  

Intercity train punctuality is below that of suburban trains and there was an extended period of declining punctuality between 2011 and 2014. Transport for NSW suggested that the old age of trains is a factor, and the recently announced intercity fleet acquisition may help address this. Apart from ensuring that train crew and station staff are available and perform their duties adequately, NSW Trains can do little to impact the punctuality of its intercity services directly. Train maintenance, track and signal maintenance, and management of trains on the rail network are performed by Sydney Trains. NSW Trains’ ability to influence improvement is hampered by key indicators in some contracts being undefined. Transport for NSW, Sydney Trains and NSW Trains are now working collaboratively to make improvements to the contracts.

Initiatives are in place or are planned to deliver good punctuality until 2019

Patronage increases, which can lead to overcrowding and trains having to wait longer at stations, are likely to present a significant challenge to maintaining punctuality into the future.

Based on patronage projections, the rail agencies have strategies to maintain punctuality up to and including joining the Sydney Metro Northwest to the network at Chatswood in 2019. These include improving infrastructure at particular parts of the network, increasing staff training, reducing the number of speed restrictions, and a new Rail Operations Centre. The projects are being managed by experienced staff, with good governance arrangements, quality assurance processes and planning systems in place. New timetables should provide more services and cater for more passengers, including off peak. They should increase network efficiency through better utilisation of capacity, but some passengers may face longer journey times and more may need to change trains mid-journey.  

The planned Rail Operations Centre has the potential to make operational decision-making more customer-focussed, by placing more emphasis on minimising customer delay during disruptions. If implemented well, it will also generate information to help agencies better identify the root cause of incidents that delay trains and improve communication with passengers so they can make better real-time travel decisions.

Predicted passenger growth presents a risk to punctuality after 2019

The rail system will struggle to maintain punctuality much beyond 2019 based on current patronage forecasts and system limitations.

From 2024, the Sydney Metro City and Southwest will help by extending the metro network from Chatswood under Sydney Harbour, through the city and out to Bankstown. Announced fleet upgrades will also help. Transport for NSW advises that it is also working with the Greater Sydney Commission to ensure network capacity constraints are considered in future urban planning.

In addition to investment in new metro networks, sustained and substantial investment needs to be made into the existing heavy rail network to meet demand and ensure its ongoing reliability. Transport for NSW has been developing strategies for this purpose, including an Advanced Train Control system. Its aim is to put a costed plan to the government by the third quarter of this (2017) calendar year. Given the likely lead times involved with major infrastructure projects, there remains a significant risk of poor punctuality after 2019.

Punctuality could be at risk sooner if recent patronage growth continues

If patronage continues to increase at a faster rate than forecast, particularly during the morning peak, the network will struggle to cope before 2019. Transport for NSW forecast that between 2011 and 2026 morning peak rail patronage would increase each year by approximately 3.3 per cent. Between 2011 and 2016 the number of passengers travelling to the city during the morning peak grew by an average of 4.4 per cent each year, including annual growth of 6.6 per cent since May 2014.

A good understanding of patronage levels, trends and drivers is critical to effective planning. The audit identified some shortcomings in measurement of peak passenger loads. Transport for NSW advised that measurement approaches have been improved recently, and this will soon flow into improved data quality.  

Given the increasing flexibility in work practices available to many city workers, the relatively new field of behavioural insights may offer opportunities to ‘nudge’ some passengers away from travelling at the height of the peak with benefits for them and the network.

  1. Transport for NSW should ensure that programs to address rail patronage growth over the next five to ten years are provided to the government for Cabinet consideration as soon as possible.
     
  2. Sydney Trains and Transport for NSW should:
    a) maintain effective oversight and resourcing for all strategies designed to address rail patronage growth
    b) adjust strategies for any patronage growth above projection.
     
  3. Sydney Trains, NSW Trains and Transport for NSW should publish Customer Delay results by June 2018.
     
  4. Transport for NSW, Sydney Trains and NSW Trains should agree by December 2017:
    a) specific performance requirements for intercity train, track and signal availability and reliability
    b) guidelines for train priorities during disruptions and indicators of control centre performance in implementing these guidelines.
     
  5. Sydney Trains, NSW Trains and Transport for NSW should by June 2018:
    a) improve the accuracy of patronage measurement and develop a better understanding of patronage growth trends
    b) address small errors in the adjustment factors used for determining a train’s punctuality status
    c) improve their understanding of the factors impacting on intercity punctuality.
     
  6. Transport for NSW should, commencing June 2017, explore the potential to use behavioural insights to encourage more passengers to travel outside the height of the morning peak (8 am to 9 am).