Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.

Some of the findings of the report include:

  • government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)

  • passenger services revenue only covered 20 per cent of RailCorp's operating costs

  • Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

  • At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually

  • Transport patronage continued to grow with 510 million journeys on train, bus and ferry services

  • CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time

  • On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12

  • Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes

  • Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.

 

Published

Actions for Volume Five 2012 focusing on superannuation, compensation and housing

Volume Five 2012 focusing on superannuation, compensation and housing

Finance
Treasury
Premier and Cabinet
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Procurement
Regulation

The NSW Government’s defined benefit superannuation funds have had positive returns for the last three years. However, the returns fell significantly in 2011-12. Global economic conditions led to substantial volatility and uncertainty in markets creating challenges for superannuation funds’ trustees.

Published

Actions for Managing Overtime: RailCorp and Roads and Maritime Services

Managing Overtime: RailCorp and Roads and Maritime Services

Transport
Management and administration
Workforce and capability

Overtime is a significant cost for RailCorp and Roads and Maritime Services, adding about ten per cent to the cost of regular salaries. RailCorp’s overtime cost was $133.7 million in 2010–11, and at Roads and Maritime Services it cost $49.3 million.

 

Parliamentary reference - Report number #223 - released 20 June 2012

Published

Actions for Volume One 2012 focusing on themes from 2011

Volume One 2012 focusing on themes from 2011

Health
Industry
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Shared services and collaboration

The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Volume Six 2011 focus on Environment, Water and Regional Infrastructure

Volume Six 2011 focus on Environment, Water and Regional Infrastructure

Planning
Industry
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The Environment Protection Authority’s expenditure for the financial year 2010/11 was $92 million - $76 million of this was for environment protection and regulation. The Office of Environment and Heritage and the Environment Protection Authority commenced 145 prosecutions for environmental offences and 106 were completed in the financial year 2010/11, down from the 134 prosecutions completed in 2009/10. Financial penalties for 2010/11 totalled $969,000 down from $1,403,000 in 2009/10. The average fine decreased from $10,468 in 2009/10 to $9,141 in 2010/11.

Published

Actions for Volume Five 2011 focus on Superannuation, Compensation and Housing

Volume Five 2011 focus on Superannuation, Compensation and Housing

Finance
Treasury
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Shared services and collaboration

The audits of the New South Wales Government controlled superannuation entities financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. Findings show that Treasury should review the structure and number of public sector superannuation funds and consider whether efficiencies and cost savings could be achieved through consolidation.

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Volume One 2011

Volume One 2011

Industry
Planning
Finance
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations. 

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009