Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997

Published

Actions for Corporate Governance - Volume Two: In practice

Corporate Governance - Volume Two: In practice

Whole of Government
Internal controls and governance
Workforce and capability

This Report, Volume Two: Corporate Governance in Practice reports upon how actual corporate governance practices by NSW public sector boards compare with “better practice”.

It found criteria and processes for appointing directors to boards are not always transparent. It also found a more systematic and rigorous approach to the range of corporate governance issues is required across the public sector if it is to approach "better practice", there is a lack of accountability for board decision making and board performance and where boards are to serve a governance role, then a basic framework needs to be created to ensure they can operate efficiently and effectively.

 

Parliamentary reference - Report number #39 - released 17 June 1997

Published

Actions for Corporate Governance - Supplement to Volume Two: Survey Findings

Corporate Governance - Supplement to Volume Two: Survey Findings

Whole of Government
Internal controls and governance
Workforce and capability

A Supplement to Volume Two: Survey Findings has also been prepared, presenting The Audit Office’s survey findings in detail. This may serve as a useful benchmark for governance in the NSW public sector.

It found that, supporting/enabling legislation, governance structures and boards creation processes should facilitate better governance practice. It also found boards and management should understand their roles, responsibilities and duties and that these should be clearly articulated in legislation, board directors should possess appropriate qualifications and expertise to fulfil their responsibilities, boards need to ensure that adequate systems are in place to be able to oversight on the activity of the agency and boards must be accountable to those whose interests they represent.

 

Parliamentary reference - Report number #39 - released 17 June 1997

Published

Actions for Redundancy arrangements

Redundancy arrangements

Industry
Planning
Compliance
Management and administration
Workforce and capability

The audit identified that overall the agencies had carried out the redundancy process satisfactorily and the process, with some exceptions, complied with Government and internal policies. Government policy states that performance problems should be dealt with by managing the performance of the employee rather than restructuring/redundancy processes. In a limited number of instances certain employees, whose performance had been questioned, had been offered and accepted voluntary redundancy.

The audit also indicates that the process of redundancies has resulted in lower salary costs, in real dollar terms, without undue increase in either overtime or consultancy costs nor any detrimental effect on service quality. However, it is noted that the decrease in staffing levels occurred exclusively in the non-budget sector. Budget sector staffing levels increased by 1.4 per cent during 1989-95. There are also signs that the need for and the benefits arising out of redundancies are not well planned or measured. The need for redundancies often arises from a desire to reduce staff related costs while there is no comparison of the costs of redundancy compared to benefits.

 

Parliamentary reference - Report number #37 - released 17 April 1997

Published

Actions for Review of NSW Agriculture

Review of NSW Agriculture

Industry
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Workforce and capability

Following a request from the NSW Legislative Council in September 1996, a performance audit into various matters affecting the operation of the New South Wales Department of Agriculture was undertaken by The Audit Office.

Among the recommendations from this report, the Audit Office found that:

  • An economic appraisal should be undertaken before all major developments, including rationalisation plans, are implemented. It should include details of anticipated benefits from the changes planned, so that their achievement can be evaluated after implementation.

  • Government policies should be made explicit or else established by directives in writing. Planning Infrastructure and human resources should be planned to maximise efficiency and effectiveness. If Government chooses alternatives that have higher costs or lower benefits for the Department, then these should be explicitly funded.

  • The Department should strengthen its system of internal control by strengthening the role of the Board of Management as a means of management control, directing an overhaul of the Charter of the Internal Audit Committee and using it to drive the Department’s internal audit function and ensuring implementation of an effective financial management information system.

 

Parliamentary reference - Report number #36 - released 27 March 1997