Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Volume Fourteen 2014 Focusing on Trade and Investment

Volume Fourteen 2014 Focusing on Trade and Investment

Planning
Finance
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Risk

There are 63 agencies in the DTIRIS cluster. These agencies include nine electricity and eight water agencies that were reported in the NSW Auditor-General’s report to Parliament Volume Five 2014 on 11 November 2014. Commentary in this volume is on the remaining 46 DTIRIS cluster agencies. The findings found the quality of financial statements in the trade and investment cluster needs to improve.

Published

Actions for Volume Twelve 2014 Health

Volume Twelve 2014 Health

Health
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

The quality of financial statements in the health cluster continues to improve with significantly fewer misstatements. The financial statements of all cluster agencies received unqualified audit opinions. Health has maintained or bettered its emergency triage performance and the percentage of patients admitted for elective surgery within clinically appropriate timeframes has improved.

Published

Actions for Volume Eleven 2014 Focusing on Planning and Environment

Volume Eleven 2014 Focusing on Planning and Environment

Planning
Local Government
Environment
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Risk

The quality of financial reporting in the planning and environment cluster continues to improve with fewer reported misstatements over the last two years. The financial statements of all agencies within this cluster received unqualified audit opinions, except for one small agency where the audit is incomplete. Many cluster agencies’ actual revenues, expenses, assets and liabilities varied from budget by more than five per cent, suggesting financial management and budgetary controls could be improved.

Published

Actions for Volume Seven 2014 Focusing on Transport

Volume Seven 2014 Focusing on Transport

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.

Published

Actions for Volume Five 2014 Focusing on Electricity and Water

Volume Five 2014 Focusing on Electricity and Water

Planning
Environment
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

In 2013-14, the NSW Government electricity businesses generated $9 billion in revenue ($9.6 billion during 2012-13) and achieved a combined net profit after tax of $1.5 billion ($1.6 billion). The combined profit after tax for NSW Distributors was $1.2 billion in 2013-14 down from $1.3 billion in 2012-13. The Distributors’ revenues decreased by $205 million to $6.8 billion in 2013-14, largely due to lower consumption by customers associated with milder weather conditions, economic impacts, energy efficiency measures and an increase in the number of customers using solar energy.

Published

Actions for Volume Four 2014 focusing on New South Wales State Finances

Volume Four 2014 focusing on New South Wales State Finances

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Asset valuation
Financial reporting
Internal controls and governance

For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.

Published

Actions for Making the Most of Government Purchasing Power - Telecommunications

Making the Most of Government Purchasing Power - Telecommunications

Whole of Government
Compliance
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General has found that agencies have consistently failed to negotiate the best price for their telecommunication contracts and are not getting value for money because of inadequate contract and expense management processes.

The audit examined six agencies to assess whether the government was getting value for money from its telecommunications contracts. It again raised problems with the way NSW government agencies manage contracts.

 

Parliamentary reference - Report number #244 - released 26 June 2014

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Health
Asset valuation
Financial reporting
Management and administration
Procurement
Service delivery

Periodically we review the extent to which agencies have changed their practices as a result of our audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our September 2002 report, to assess whether NSW Health has improved its buying of hospital supplies using electronic systems.

NSW Health spends over $1.3 billion on hospital supplies. It is the largest expenditure area after employee costs. Reform of this area has the potential to make significant savings that could be redirected to frontline services.

As part of our series of audits in the area of e-government, our previous audit looked closely at the extent to which technology was being used to deliver potentially major savings in purchasing hospital supplies. This is a key area of so-called “process re-engineering” in the “e” field, and NSW Health provided an ideal case study.

Whilst implementing large-scale e-procurement has many technical aspects, it is not chiefly a technical issue. The key requirements for success reside in effective change management, in particular being clear as to who has the authority to make change decisions and be held accountable.

This audit looks at NSW Health’s successes to date, and its frustrations and challenges in making further progress in this field. Many of the issues raised in this report may provide lessons for any agency that is seeking to drive a significant change program.

 