Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Planning, Industry and Environment 2020

Planning, Industry and Environment 2020

Planning
Environment
Industry
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions

There are 45 separate entities in the cluster. Unqualified audit opinions were issued for 38 cluster agencies' 30 June 2020 financial statements audits. Four financial statements audits are still ongoing, and three agencies were not subject to audit due to NSW Treasury reporting exemptions.

Timeliness of financial reporting

The majority of cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting financial statements. Twenty‑four of the 26 cluster agencies required to submit early close financial statements met the revised timeframe.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions not issued by the statutory deadline.

Implementation of AASB 16 'Leases'

Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations.

Recommendation (partially repeat):

Property NSW should:

  • review and document the accounting implications for each lease
  • ensure the accuracy and validity of lease data used for the lease calculations
  • review user access to the leasing system, including privileged users.

Our audits of the cluster agencies identified there was a lack of thorough quality assurance over the accuracy of lease information provided by Property NSW.

Recommendation:

The Department and cluster agencies should:

  • quality assure and validate the information provided by Property NSW
  • ensure changes made by Property NSW on lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.

Unprocessed Aboriginal land claims continued to increase

In 2019–20, the Department resolved an additional 468 Aboriginal land claims compared to the prior year. However, the total number of unprocessed Aboriginal land claims increased by 914 to 36,769 at 30 June 2020. The number of claims remaining unprocessed for more than ten years after lodgement increased by 10.9 per cent from last year. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land.

Auditor-General's Reports to Parliament since 2007 have recommended action to address the increasing number of unprocessed claims. To date, the Department has not been able to resolve this issue.

During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

Financial reporting of Crown land managers

The Department will need to provide additional support and guidance to help Crown land managers (CLMs) meet their financial reporting obligations.

Recommendation:

The Department should:

  • in consultation with NSW Treasury, develop an appropriate statutory reporting framework for CLMs
  • ensure sufficient resources are available to help CLMs meet their reporting obligations.

During 2019–20, NSW Treasury established the reporting exemption criteria for the CLMs. Based on available information, the Department determined 31 CLMs would not meet the exemption criteria and therefore are required to prepare annual financial statements.

2. Audit observations

Internal controls

Six high‑risk issues were identified across the cluster in 2019–20:

  • 5 of those were related to financial reporting issues identified in Property NSW, Wentworth Park Sporting Complex Land Manager, Lord Howe Island Board, Planning Ministerial Corporation and Hunter and Central Coast Development Corporation
  • 1 issue was related to Lord Howe Island Board's outdated business continuity plan.

One in three internal control issues identified and reported to management in 2019–20 were repeat issues.

Recommendation:

Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing high‑risk and repeat issues.

Agencies response to recent emergencies

The unprecedented bushfires and COVID‑19 pandemic presented challenges for the cluster. Agencies established taskforces or response teams to respond to these emergencies.

With more staff working from home, agencies implemented protocols and procedures to manage risks associated with the remote working arrangements, and also needed to address certain technology issues.

The Department is responsible for the new Planning System Acceleration Program, which aims to fast‑track planning assessments, boost the State's economy and keep people in jobs during COVID‑19 pandemic. Between April and October 2020, the Department announced and determined 101 major projects and planning proposals.

Recognition of Crown land

Crown land is an important asset of the State. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel.

Auditor-General's Reports to Parliament since 2017 have recommended that the Department should ensure the database of Crown land is complete and accurate. Whilst the Department has commenced actions to improve the database, this remained an issue in 2019–20.

Recommendation (repeat issue):

The Department should prioritise action to ensure the Crown land database is complete and accurate. This allows state agencies and local councils to be better informed about the Crown land they control.

Implementation of Machinery of Government (MoG) changes

Since its creation on 1 July 2019, the Department has largely established its governance arrangements, including setting up the Audit and Risk Committee and internal audit function for the Department and relevant cluster agencies.

The Department still operated three main financial reporting systems in 2019–20, and has commenced the process to consolidate some of the systems.

The recent Regional NSW MoG change led to the transfer of $446 million net assets and $284 million 2019–20 budget from the Department to the newly created Department of Regional NSW on 2 April 2020.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID‑19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID‑19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the Consolidated fund until the enactment of the 2020–21 budget – impacting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2020 financial statements audits. Timeliness of financial reporting remains an issue for 13 agencies.
  • Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations. Cluster agencies can also improve their management of lease information provided by Property NSW.
  • The number of unprocessed Aboriginal land claims continued to increase. During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

The Department has not yet developed a statutory reporting framework for Crown land managers and will need to provide additional resources to help Crown land managers meet their financial reporting obligations.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Cluster agencies experienced a range of control and governance related issues in recent years. An increased number of high risk issues and greater proportion of repeat issues were identified as part of our audits. It is important for cluster agencies to promptly address these issues.

Section highlights

  • Six high risk issues were identified during 2019–20 audits. One in three issues identified and reported to management in 2019–20 were repeat issues.
  • The Department has fast tracked the assessment and determination of 101 projects as a part of the Planning System Acceleration Program.
  • There continues to be significant deficiencies in Crown land records. The Department should ensure the Crown land database is complete and accurate.

Published

Actions for Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Health
Internal controls and governance
Management and administration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining NSW Health’s management of health and safety risks to nurses and junior doctors in high demand hospital wards over the past five years, including during the first six months of the 2020 COVID-19 health emergency.

The Auditor-General found that while NSW Health effectively managed most incidents and risks to the physical health and safety of hospital staff during ‘business as usual’ activities, systems and resources are not fully effective to manage staff psychological and wellbeing risks, particularly for nurses.

The Auditor-General found that NSW Health was effective in managing most COVID-19 health and safety risks to hospital staff. Overall effectiveness could have been improved had pandemic preparedness training been delivered across all Local Health Districts. Additionally, state-wide communication systems could have been improved to provide hospital clinicians with access to a ‘single source of truth’ with the latest advice from NSW Health authorities.

NSW Health’s planning and preparation for the supply of Personal Protective Equipment (PPE) was partially effective. At various times, some PPE items could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting from usual items, and in some hospitals, substituted masks were used without being locally fit tested by hospital staff.

The Auditor-General made seven recommendations aimed at enhancing hospital health and safety risk reporting practices, along with a recommendation that NSW Health conduct a post pandemic 'lessons learned' review and make policy and operational recommendations for future pandemic responses.

Over the past decade, there have been increases in the numbers of health and safety incidents affecting nurses and junior doctors in NSW hospitals. These increases have been associated with higher numbers of patients with acute mental health conditions, age-related cognitive impairments, and patients presenting in emergency departments under the influence of drugs and alcohol.  

This audit commenced in August 2019, with a focus on the health, safety and wellbeing of nurses and junior doctors in high demand hospital wards. Our audit focused on emergency departments, mental health wards and aged care wards during 'business as usual’ periods of hospital operations. 

In the early months of 2020, the novel coronavirus (COVID-19) brought new health and safety risks to hospital staff. These risks included the potential for infection amongst health workers, increased staff workloads, and impacts on staff wellbeing.  

In May 2020, we expanded the focus of the audit to assess the effectiveness of NSW Health’s management of the health and safety risks to staff during the COVID-19 health emergency. We assessed the impacts on emergency departments and intensive care units, as these were the wards where staff were most likely to come into contact with COVID-19.  

The Audit Office acknowledges the ongoing health and safety challenges that the pandemic has brought to NSW Health staff – in particular to hospital clinicians and the managers who support them.  

This audit assessed the effectiveness of NSW Health’s:

  • systems, forums and workplace cultures to support reporting and generate data about risk
  • initiatives to support safe workplaces and effectively respond to health and safety incidents
  • actions to continuously improve staff health, safety and wellbeing in hospital environments.

The first three chapters of this report describe the effectiveness of NSW Health’s ‘business as usual’ health and safety risk management. The fourth and fifth chapters describe the effectiveness of NSW Health’s health and safety risk management during the COVID-19 pandemic.  

Conclusion
NSW Health’s management of health and safety risks in NSW hospitals

NSW Health is effectively monitoring and managing most incidents and risks to the physical health and safety of nurses and junior doctors in NSW hospitals. However, systems and resources are not fully effective across all Local Health Districts for monitoring or managing psychological and wellbeing risks - particularly in relation to nurses.

NSW Health’s incident management system is effective for recording health and safety incidents in hospital wards where incidents occur infrequently, and staff have time to log incident details during shift hours. However, in high demand wards where incidents and risks are common, staff report that they are unable to log all incidents due to the frequency of events, and the time it takes to record incidents in the system.

NSW Health is taking reasonable steps to manage and respond to physical health and safety incidents in NSW hospitals, but psychological and wellbeing risks and incidents are not routinely recorded or escalated to managers. Stress debriefing is not consistently available to staff after difficult or traumatic workplace incidents.

The Ministry of Health could improve its information sharing and data reporting on state-wide health and safety risks in NSW hospitals, and communicate risk trends to the wider NSW health system. This would assist managers to identify common health and safety issues, and target their responses. The Ministry has not set up systems or strategies to identify or support the expansion of successful health and safety initiatives across the NSW health system.

NSW Health’s management of health and safety risks associated with COVID-19

To date, NSW Health has effectively managed most COVID-19 related health and safety risks to hospital staff. The overall effectiveness of NSW Health's preparations and responses to COVID-19 could have been improved in the early phases of the health emergency - from January to early April 2020 - by ensuring that hospital staff in all Local Health Districts had access to pandemic training, that all emergency response policies had been updated and circulated, that state-wide communication systems were able to be rapidly upscaled to deliver consistent messages to hospital staff across the health system, and that PPE supply lines could provide sufficient stock to meet requirements during all pandemic response phases.

Local Health District executives and hospital managers effectively guided and supported nurses and junior doctors to manage and minimise most COVID-19 health and safety risks in hospital environments. However, communication with frontline staff could have been improved in the early stages of the pandemic. The Ministry did not set up a centralised communication channel to communicate consistent messages and advice to hospital clinicians until April 2020. This finding is consistent with a finding from the 2009 review into NSW Health’s response to the H1N1 influenza outbreak. Clinical staff advised that the lack of a centralised communication channel, substantially increased their workloads as they checked numerous sources for the latest and most authoritative advice.

Prior to COVID-19, pandemic response training was limited across the NSW Health system. Nurse managers of emergency departments and intensive care units reported that there was limited training or familiarisation with the NSW Pandemic Plan. Key policies describing infection control principles for emergency departments and intensive care units were outdated and had not been revised within required timelines.

NSW Health's planning and preparation for the supply and management of personal protective equipment (PPE) has been partially effective, with PPE available to hospital staff at all times. However, at various intervals, some PPE could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting, from the usual PPE stock. Staff reported that in the early stages of the pandemic, substituted masks were not locally fit tested by hospital staff in some emergency departments.

1. Audit recommendations

By December 2021, NSW Health should:

  1. Evaluate the effectiveness of the new incident management system to enable full reporting of health and safety incidents and risks in all hospital wards, including those where incidents and risks are common, and monitor for consistency of reporting over time
  2. Expand the categories of hospital incident data reported to Ministry executives in the Work Health and Safety Dashboard reports, including by linking injury data to incident types by hospital ward category, and monitor in conjunction with Local Health Districts for emerging trends and improvement over time
  3. Ensure that nurses and junior doctors have regular opportunities to report on risks to their psychological health and wellbeing, and that system managers have access to aggregate data to guide responses to mitigate these risks
  4. Develop and implement an evidence-based guiding framework and strategy to support hospital staff in the aftermath of traumatic or unexpected workplace incidents, and monitor implementation
  5. At regular intervals, publicly report aggregate Root Cause Analysis data detailing the hospital system factors that contribute to clinical incidents
  6. Develop and implement a systemwide platform for sharing research and information about hospital health and safety initiatives across the health system
  7. Conduct a post-pandemic 'lessons learned' review focusing on the effectiveness of key strategies deployed in the management of the COVID-19 pandemic and make policy and operational recommendations for future pandemic responses. In particular, ensure:
    • regular scenario-based pandemic training for hospital staff
    • updated policies and protocols for hospital infection controls
    • capability to upscale authoritative communication with frontline health workers at the earliest notification of a health emergency and for the duration of the emergency
    • systems and safeguards to ensure the supply and availability of clinically appropriate personal protective equipment (PPE) during all phases of a pandemic.

Local Health Districts were effective in leading health and safety infection control activity

According the NSW Health Influenza Pandemic Plan (Pandemic Plan), the Chief Executives of Local Health Districts have ultimate responsibility for public health unit preparations during health emergencies. If necessary, they can ‘draw on the support of the State Pandemic Management Team and local emergency management resources’.

During the preparations and early response phases to the COVID-19 pandemic, Local Health Districts were at the forefront of most NSW hospital activity. They took the lead role in developing hospital infection control protocols and guidance about the appropriate uses of Personal Protective Equipment (PPE). Each Local Health District established its own responses to the health emergency, based on the best clinical advice available to them. The localised approach meant that there were some minor differences in infection control practices across the NSW health system.

Throughout February and March 2020, there was limited centralised policy or guidance from the Ministry and its Pillar Health agencies about COVID-19 infection control practices. It was not possible to mandate practices at a time when information about the virus was evolving. Clinical responses were changing as more became known about COVID-19, especially about its patterns of transmission and its impacts on people with the disease.

During February and March 2020, Local Health District executives communicated with hospital staff via a range of methods. Some sent daily e-memos with the latest updates. Some scheduled more regular meetings with hospital clinicians. Some Districts set up extensive staff training sessions and information briefings to keep all personnel updated with the latest advice. Physical distancing made it difficult to bring staff together in large groups, so a range of communications measures were implemented.

Clinical staff also utilised their clinical training and expertise to prepare their wards and train frontline staff in infection control procedures. Some sourced information from national and international colleagues to add to localised knowledge of the virus.

When the first evidence of COVID-19 community transmission was identified in the Northern Sydney Local Health District, hospital staff followed infection control protocols that were based on local guidance and information. With the support from the District executive team and infectious diseases experts, hospital clinicians set up their own infection control protocols and PPE protections. Within a week the District had produced a matrix to guide staff in the uses of PPE during COVID-19 procedures, and had circulated the guidance to all hospital clinicians.

At the end of March 2020, a version of the Northern Sydney PPE matrix was published on the Clinical Excellence Commission’s website and it has now become NSW Health’s standard guideline for PPE during COVID-19 procedures. Once this guideline was published centrally, infection control practices were standardised across NSW hospitals.

This form of District-led policy making is not ‘business as usual’ practice for NSW Health. Policy making processes were somewhat reversed during the early response phases to COVID-19. This flexible policy approach supports the governance arrangements described in the Pandemic Plan, which assigns responsibility for ‘supporting and maintaining quality care across health services and implementing infection control measures as appropriate’ to Local Health Districts.

In non-health emergency situations, clinical policy and protocols are usually initiated and developed by the Ministry and the Clinical Excellence Commission and are subsequently shared across the health system after a quality control process. The localised approach adopted in the months from February to March 2020, allowed for rapid and flexible responses to changing information – to protect the health and safety of the hospital workforce and the wider community.

Hospital staff across NSW would have been better prepared for COVID-19 if pandemic training had been delivered across all Local Health Districts in the past decade

Local Health Districts are responsible for training hospital staff in preparation for public health emergencies. NSW’s policy describing Public Health Emergency Response Preparedness Minimum Standards requires that clinical staff participate in at least one annual emergency training exercise if they hold a position where they are likely to be called upon in an emergency. Staff must participate in an actual response exercise or a relevant training session. The training must also include re-familiarisation with PPE.

Available evidence about emergency response training in NSW indicates that at least two Local Health Districts have delivered pandemic focussed training in the past decade. Our interviews with managers of emergency departments and intensive care units indicates that most other Districts have focused their emergency training on mass patient trauma incidents such as plane crashes, train crashes and terrorist attacks. While the potential for these types of mass trauma events is real, and warrants training and preparation, significant global outbreaks of diseases have also had potential to threaten NSW communities. In previous decades, global health communities have been at risk of diseases such as the Severe Acute Respiratory Syndrome (SARS) and Middle East Respiratory Syndrome (MERS).

In the two Districts where pandemic training was provided in NSW, staff participated in community influenza vaccination exercises. These were focused on upskilling staff to follow emergency command structures, manage high volume patient flows, and organise sanitisation logistics during a hospital-based training exercise.

Our interviews with nurse managers in emergency departments and intensive care units indicate that in the majority of other Local Health Districts, key personnel were unaware of the NSW Pandemic Plan. Interviewed staff also reported insufficient scenario-based training in pandemic responses over the last ten years.

The Ministry, the Clinical Excellence Commission and the Health Education and Training Institute (HETI) are responsible for online training and 'state-wide strategies and resources to maintain high levels of compliance with infection control and patient safety recommendations'. The HETI website contains online training modules in infection control and PPE donning and doffing procedures. Other infection control information and research is available on the websites of the Clinical Excellence Commission and the Agency for Clinical Innovation.

Online training modules are effective for upskilling staff in a range of skills, but are not a substitute for real-time, rapid incident response training. Face-to-face training provides opportunities for first responders to test procedures in hospital environments. Incident response training provides opportunities for staff to assess their levels of compliance with protocols and their competence with equipment in scenario situations. It is the responsibility of Local Health Districts to provide this form of training to the health staff in their District.

Two NSW Health policies that govern clinical arrangements during pandemics are outdated

The Ministry had not updated two policies that had the potential to assist emergency departments and intensive care units in aspects of their ward preparation for the COVID-19 pandemic. Both policies were on the NSW Health website, but neither were shared with hospital staff in the planning phases for the pandemic. Both policies are out of date and have not been revised within required timeframes.

The 2010 Influenza Pandemic - Providing Critical Care policy was due for review in May 2015 and was not updated at the time of the COVID-19 health emergency. Similarly, the 2007 policy Hospital Response to Pandemic Influenza Part 1: Emergency Department Response was due for review in June 2012 and has not been updated.

These policies were designed to assist clinical staff to make necessary ward arrangements for infection control. They set out the steps for rapid identification of contingent workforces, isolation procedures, and management of patient flows to separate those with suspected infection from other patient cohorts. They were a potential addendum to the NSW Pandemic Plan which describes the command and control responsibilities of health agencies in health emergencies.

Our interviews with nurse managers from emergency departments and intensive care units indicate that in the absence of pandemic policy, they sought clinical guidance from external sources and Local Health District experts. Interviewees told us that a lack of policy guidance about ward arrangements and infection control practices in a pandemic increased their workloads and hours of overtime in the early response phases to COVID-19. With the support of Local Health Districts, clinical staff made rapid adjustments in order to respond to changing testing requirements and ward arrangements.

The Ministry was slow to establish a centralised communication channel to communicate with frontline staff

NSW Health’s governance and communication arrangements during a pandemic are set out in the Pandemic Plan. The Plan requires that government agencies ‘commence enhanced arrangements, establish communications measures’ and confirm ‘governance arrangements’ when there is evidence of person to person transmission during an influenza outbreak. NSW Health received the first notifications of the novel coronavirus risks in January 2020.

During the preparation and early response phases to COVID-19, the Ministry and its central agencies were slow in establishing a single, authoritative channel through which to communicate consistent messages to frontline staff. Clinical staff required up-to-date information about COVID-19 testing criteria as requirements were changing rapidly, sometimes daily. While there was no expectation for fixed policy at this time, hospital staff required the latest instructions about treatment requirements, and updates on the numbers of COVID-19 infections in their region.

As information about COVID-19 was evolving, information was communicated across the health system via ‘multiple channels and sources’. While the Ministry and its central agencies communicated extensively with Local Health Districts during March 2020, hospital staff reported to us that they weren’t always sure where they could find the latest advice about testing protocols or infection controls.

Frontline staff told audit office staff that they were checking multiple sources and time-stamping advice to ensure they had the most up to date information on a daily basis. While some Local Health Districts managed clear communication links with frontline staff, nurse managers told us that communication was ‘chaotic’ during the early phases of pandemic preparation. Key personnel were not always available outside business hours and nurse managers advise that they spent hours at the end of shifts, seeking and printing the latest advice for weekend and night shift personnel. By the end of March 2020, the Ministry and the Clinical Excellence Commission websites became better organised to communicate with frontline clinicians.

A recommendation to the Ministry of Health after H1N1 swine flu could be equally applied in the COVID-19 context. The NSW Government’s report: Key Recommendations on Pandemic (H1N1) 2009 Influenza recommended the establishment of ‘clear pathways of communication … so that all employees have confidence in where their information will come from and who they should approach if they need additional information.’

NSW Health acknowledges the challenges and the lessons from the early phases of the COVID-19 pandemic. For example, a strategy released in August 2020, sets out NSW Health’s own recommendation for the future management of PPE including: ‘Aligning a single source of truth for PPE education and evidence-based guidance to ensure clarity of information on appropriate use, supported by an influential network of Infection Prevention and Control (IPC) practitioners at the forefront.

Ministry executives advise that communication with health staff has improved since the early phases of the pandemic. The Ministry now sends weekly COVID-19 updates to over 130,000 health staff via email. In addition, NSW Health now has two COVID-19 tabs on its website with current information, including COVID-19 testing advice. According to Ministry executives, these communication channels could be used or replicated if needed for future health emergencies. The Ministry also provides health information and updates via a phone application called Med App. This App is preferred by doctors and is less likely to be used by nurses. As at October 2020, there are 13,000 users of Med App. Push notifications can be made on Med App through SMS alerts.

Personal protective equipment (PPE) was not always available in required sizes and some hospital masks and gowns were substituted with products that differed from the usual items

Since the emergence of COVID-19 in Australia, all clinicians in NSW hospitals have had access to some form of PPE for their clinical requirements. If staff did not have appropriate equipment for each COVID-19 related procedure, they were guided by the formal advice issued to the NSW Health workforce on 11 March 2020 stating that: ‘The safety of NSW Health staff is a priority at all times, especially during COVID-19. Where safe working practices confirm specific PPE (e.g. face shields/masks or other equipment) are required for the protection of staff due to COVID-19, in all circumstances:

  • staff are to wear prescribed PPE as instructed
  • staff are not to undertake or be required to undertake tasks requiring PPE if the PPE is not available for use. Any such tasks are not to proceed until required PPE is available
  • any staff member who is concerned about their safety must raise their concerns immediately to their manager.’

At periods during March and April 2020, some PPE items were not available in the required sizes or the regular brands to which staff were accustomed. HealthShare NSW was not able to source PPE from usual suppliers. HealthShare NSW sourced PPE including N95 masks from non-traditional suppliers. Some PPE items differed in shape and size from the usual hospital equipment. While senior executives from HealthShare NSW advise that all products were approved by the Therapeutic Goods Administration (TGA), in some hospitals, nurse managers advise that staff were not able to ‘fit test’ substituted masks. Fit testing determines the type and the size of the respirator mask that achieves an adequate seal on an individual’s face.

In March and April 2020, ‘duck bill’ (N95) masks were not available in some hospitals. According to stock managers and clinical managers in Local Health Districts, duck bills are the preferred mask for staff with smaller faces, particularly female staff members. The duck bill mask is a standard PPE product, and as such, is fit tested during mandatory PPE training. During the early response phases to COVID-19, most Local Health Districts were provided with substitute N95 masks. Fit testing of the substituted N95 masks was not able to be conducted in all NSW hospitals during the early phases of COVID-19. During the first wave of COVID-19 in March and April 2020, hospital staff told audit staff that there was no time and a lack of equipment to appropriately fit test substituted N95 masks.

Nurse managers in emergency departments advise that in some instances, staff made adaptations to PPE to improve protections, such as doubling masks, adding elastics or bringing their own equipment. These adaptations were not consistent with guidelines. Nurse managers advise that in some cases, adaptations to PPE or ill-fitting masks created pressure sores and contact dermatitis. Just over half of the stock managers of Local Health Districts advised that PPE stock was procured from outside the HealthShare NSW system. Stock managers in some Districts advise that facial shields and goggles sourced from non-traditional suppliers by HealthShare NSW were of a lesser quality than standard equipment. Stock managers and nurse managers reported that the changes in PPE products caused confusion and stress amongst staff.

Local Health Districts were proactive in assisting hospital staff to mitigate risks of COVID-19 infections. Some Local Health Districts assigned ‘tiger teams’ to assist staff with their PPE practices. Tiger teams provide clinical expertise and advice to staff, answer questions about infection control and provide training on PPE practice in hospital ward environments. They assist and support PPE donning and doffing practices to ensure the appropriate sequencing of applying and removing PPE for effective infection control. They provide mask fit checking guidance to assist staff in correct PPE practices.

Districts ran extensive refresher PPE training sessions for clinical staff. Some hospitals ran regular PPE demonstrations so that staff could observe correct PPE procedures at set times during the day. These activities assisted staff to implement appropriate infection control in the period before the Clinical Excellence Commission’s web-based materials and videos became available in late March and early April 2020. These online resources now provide comprehensive guidance to hospital staff in PPE practices.

HealthShare NSW placed limits or caps on some high-demand PPE items that were too low to meet requirements in some Local Health Districts and had to be adjusted to meet actual demand

The NSW Pandemic Plan describes the responsibilities of the Ministry and its central agencies to manage and maintain the State Medical Stockpile of essential PPE supplies and antiviral medications. During a pandemic, HealthShare NSW has responsibility for warehousing, monitoring and distributing health supplies to the health workforce.

Due to a reported global shortage of PPE and limits to the NSW stockpile, HealthShare NSW placed limits on the provision of approximately 100 high-demand items to NSW hospitals. HealthShare NSW advise that the PPE order capping ceilings were implemented ‘to ensure local stockpiling does not occur’. A centralised ordering process was established with Local Health Districts so that PPE product ordering occurred through single hospital locations (214 across the State), rather than at the ward level. Escalation processes were established to allow Districts to request one-off increases to supply, and a process was set up to permanently increase the order cap limit for any PPE item by facility.

According to HealthShare NSW, ‘as incoming central supply has improved, order caps have subsequently increased in line with strong engagement and governance with the Local Health Districts to ensure the appropriate levels of supply are provided’. The original capped levels were determined by assessing PPE usage in wards during the flu season of 2019. As the flu season case numbers of 2019 were relatively low, some Local Health District managers advised that the levels of PPE during 2019 were not comparable to the level of PPE required for the COVID-19 pandemic.

After advocacy from hospital stock managers and clinicians, HealthShare NSW increased capped PPE levels in many Local Health Districts.

Executive members of the State Health Emergency Operations Centre (SHEOC) advise that its PPE supply strategy needs to be carefully developed as there are vast differences in PPE usage rates during 'business as usual' periods and pandemic periods. If NSW Health kept the level of PPE required in planning for a worst-case scenario, this would equate to an extensive surplus of PPE that could not be utilised during business as usual periods. The SHEOC Executive advise that it is not feasible or economical to store this level of PPE. They advise that given the costs of PPE, and the fact that the products have a shelf life, a diversified supply line is a more reliable method for ensuring PPE during surge and non-surge periods.

Early data modelling showed ICU patient numbers at levels not manageable with levels of ventilators and equipment

Early projections of patient numbers requiring acute care for COVID-19, were at levels that would not have been manageable with the equipment and resources of NSW hospitals. Throughout March through to May 2020, government data modelling indicated significant surges of community infections and surges in intensive care patients.

Early estimates were based on overseas trends, and if actual cases had matched projections, NSW hospitals would not have had sufficient ventilators to meet demand. The knowledge of this shortfall caused high levels of anxiety among nursing and medical staff.

While the data was based on the best available information, it had negative implications for the health and safety of the nurse and junior doctor workforce. Managers of intensive care wards and emergency departments reported stress amongst the workforce. Staff concerns were primarily about being faced with ‘the unmanageable’, along with heightened fears about contracting the virus with the knowledge that there was insufficient equipment to treat acute patients.

As it transpired, overall numbers of COVID-19 infections were lower than projected during the early months of the pandemic. The lower infection rates in the general population have meant fewer instances of patients requiring intensive care in NSW hospitals. In addition, HealthShare NSW has been able to increase the numbers of ventilators in NSW hospitals to prepare for future surges in patients requiring acute respiratory care.

SHEOC Executive advise that NSW Health undertook an accelerated procurement strategy in early 2020 to increase its stock of ventilators, and that ventilator capacity has always far-exceeded actual requirements.

NSW Health has developed a strategy to improve the management of PPE for the NSW health workforce

In August 2020, NSW Health released a strategy that sets out its future management and planning approaches to the provision of PPE for the NSW Health workforce. NSW Health’s Personal Protective Equipment (PPE) Strategy describes the learnings and challenges during the COVID-19 pandemic in sourcing and distributing PPE. It sets out the systems and methods for distributing PPE to staff and patients and focuses on how staff are kept informed on the appropriate use of PPE at all times. A supporting communications strategy has been developed to support its implementation.

The strategy contains enhanced transparency measures to regularly inform staff about PPE stock levels and to provide data about PPE usage rates by item types in wards in NSW hospitals. The NSW Health PPE strategy describes a changed approach to ordering, storing and allocating PPE. This includes diversifying the supply lines for PPE products to increase supply options in circumstances where supply lines become disrupted. It includes a centralised system for coordinating the supply of hospital PPE through Local Heath District coordination points and centralised distribution points in large hospitals.

Our interviews with hospital PPE stock managers and nurse managers indicate that staff find the new ordering system to be an improvement upon the previous stock ordering method.

According to the Personal Protective Equipment (PPE) Strategy, NSW health is upgrading its models for monitoring and benchmarking PPE usage across the health system. Systems are being improved for forecasting demand volumes during business as usual periods and during health emergency surges.

Appendix one – Response from agency

Appendix two – Audit methodology

Appendix three – About the audit 

Appendix four – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #344 - released 9 December 2020

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020