What this report is about 

This report assesses how effectively SafeWork NSW, a part of the Department of Customer Service (DCS), has performed its regulatory compliance functions for work health and safety in New South Wales. 

The report includes a case study examining SafeWork NSW's management of a project to develop a realtime monitoring device for airborne silica in workplaces. 

Findings 

There is limited transparency about SafeWork NSW's effectiveness as a regulator. The limited performance information that is available is either subsumed within DCS reporting (or other sources) and is focused on activity, not outcomes. 

As a work health and safety (WHS) regulator, SafeWork NSW lacks an effective strategic and data-driven approach to respond to emerging WHS risks. 

It was slow to respond to the risk of respirable crystalline silica in manufactured stone. 

SafeWork NSW is constrained by an information management system that is over 20 years old and has passed its effective useful life. 

While it has invested effort into ensuring consistent regulatory decisions, SafeWork NSW needs to maintain a focus on this objective, including by ensuring that there is a comprehensive approach to quality assurance. 

SafeWork NSW's engagement of a commercial partner to develop a real-time silica monitoring device did not comply with key procurement obligations. 

There was ineffective governance and process to address important concerns about the accuracy of the real-time silica monitoring device. 

As such, SafeWork NSW did not adequately manage potential WHS risks. 

Recommendations 

The report recommended that DCS should: 

  • ensure there is an independent investigation into the procurement of the research partner for the real-time silica detector 
  • embed a formal process to review and set its annual regulatory priorities 
  • publish a consolidated performance report 
  • set long-term priorities, including for workforce planning and technology uplift 
  • improve its use of data, and start work to replace its existing complaints handling system 
  • review its risk culture and its risk management framework 
  • review the quality assurance measures that support consistent regulatory decisions

 

Read the PDF report.

Parliamentary reference - Report number #390 - released 27 February 2024
 

Published

Actions for Regional road safety

Regional road safety

Transport
Health
Community Services
Internal controls and governance
Management and administration
Project management
Risk

What this report is about

Around one-third of the state’s population lives in regional NSW, but deaths on regional roads make up around two-thirds of the state’s road toll.

Transport for NSW (TfNSW) is responsible for managing road safety outcomes across the NSW road network. This audit assessed the effectiveness of TfNSW’s delivery of road safety strategies, plans and policies in regional areas.

The NSW Road Safety Action Plan 2022–2026 has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

What we found

There is a disproportionate amount of trauma on regional roads, but there are no specific road safety plans or trauma reduction targets for regional NSW.

TfNSW advises that the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. However, the proportion of road fatalities and serious injuries in regional NSW is almost the same as ten years ago.

There is no regional implementation plan to assist TfNSW to target the Road Safety Action Plan 2026 to regional areas.

TfNSW considers that local road safety outcomes should be managed by councils, but only 52% of regional councils participated in its Local Government Road Safety Program (LGRSP) in 2022–23. This program has not been updated since 2014, despite commitments to do so in 2021 and 2022.

TfNSW has not undertaken a systematic and integrated analysis of the combined impact of its road safety strategies and plans in regional NSW since 2012.

TfNSW reports against the Community Road Safety Fund (CRSF) annually but there is no consolidated, public reporting on total road safety funding allocated to regional NSW. The Fund underspend increased from 12% in 2019–20 to 20% in 2022–23.

What we recommended

We recommended TfNSW:

  • develop a regional implementation plan to support the NSW Road Safety Action Plan, including a framework to annually measure, analyse and publicly report on progress
  • develop a plan to measure and mitigate risks causing underspend in the CRSF
  • expedite the review of the LGRSP including recommendations to increase involvement of regional councils.

Disclosure of confidential information

Under the Government Sector Audit Act 1983 (the Act), the Auditor-General may disclose confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest, and that disclosure is necessary for the exercise of the Auditor-General’s functions.

Confidential information in the Act means Cabinet information or information subject to legal privilege. This performance audit report contained confidential information.

The NSW Premier has certified that in his opinion the disclosure of the confidential information was not in the public interest.

The confidential information has been redacted from this report.

Under section 36A(2) of the Government Sector Audit Act 1983, the Auditor-General may authorise the disclosure of confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest and necessary for the exercise of the Auditor-General’s functions. Confidential information under the Government Sector Audit Act 1983 means Cabinet information, or information that could be subject to a claim of privilege by the State or a public official in a court of law. This performance audit report contained confidential information which, in the opinion of the Auditor-General, is in the public interest to disclose and that disclosure is necessary for the exercise of the Auditor-General’s functions.

On 26 October 2023, pursuant to section 36A(2)(b) of the Government Sector Audit Act 1983, the Auditor-General notified the NSW Premier of the intention to include this information in the published report, having formed the opinion that its disclosure is in the public interest and is necessary for the exercise of the Auditor-General’s functions.

On 23 November 2023, pursuant to section 36A(2)(c) of the Government Sector Audit Act 1983, the NSW Premier certified that, in his opinion, the proposed disclosure of the confidential information contained in this report was not in the public interest. The Premier’s certificate follows. Section 36A(4) states that a certificate of the Premier that it is not in the public interest to disclose confidential information is conclusive evidence of that fact.

The issuance of the certificate by the NSW Premier prevents the publication of this information. The relevant sections of the report containing confidential information have been redacted.

One-third of the New South Wales population resides in regional areas, but two-thirds of the state’s road crash fatalities take place on regional roads.

Between 2017 and 2021, the average number of fatalities for every 100,000 of the population living in regional New South Wales was 8.33 — approximately four times higher than the equivalent measure for Greater Sydney. Similarly, the average number of serious injuries in regional New South Wales over the same period was 75.24 per 100,000 of the population, compared with 50.53 in Greater Sydney. Further, more than 70% of people who lose their lives in accidents on regional roads are residents of regional areas.

Residents of regional areas face particular transport challenges. They often need to travel longer distances for work, health care, or recreation purposes, yet their public transport options are more limited than metropolitan residents. Vehicle safety is also an issue. According to the NSW Road Safety Progress Report 2021, of the light vehicles registered in New South Wales that were manufactured in or after 2000, 48.4% of light vehicles in regional areas had a five-star Australasian New Car Assessment Program (ANCAP) rating, compared to 54.8% in metropolitan areas. Road conditions in regional areas can also be more challenging for drivers.

Regional New South Wales covers 98.5% of the total area of the state. The road network in New South Wales is vast — spanning approximately 200,000 kilometres.

The road network includes major highways, state roads and local roads. Speed limits range from 10 km/hr in high pedestrian shared zones, up to 110 km/hr on high volume and critical road corridors. Eighty per cent of the network has a 100 km/h speed limit, which is mostly applied as a default speed limit, regardless of the presence of safety features and treatments.

Speed is the primary causal factor in more crashes in New South Wales than any other factor, and car crashes in regional areas are more likely to be fatal because of the higher average speeds involved.

The responsibility for managing road safety outcomes across the entire New South Wales road network lies with Transport for NSW (TfNSW), pursuant to Schedule 1 of the Transport Administration Act 1988.

While its safety responsibilities are state-wide, TfNSW does not own or directly manage all of the road network in regional New South Wales, which spans approximately 200,000 kilometres. Approximately 80% of the roads are classified as Local Roads and are administered and managed by local councils. Local councils also maintain Regional Roads that run through their local government areas. TfNSW is responsible for managing State Roads (approximately 20% of roads), which are major arterial roads. It also provides funding for councils to manage over 18,000 km (approximately 10%) of state-significant Regional Roads.

According to TfNSW, between 2016 and 2020, there were 9,776 people killed or seriously injured on roads in regional New South Wales. Adding to the tragic loss of life, according to TfNSW, the estimated cost to the community between 2016 and 2020 resulting from regional road trauma and fatalities was around $13.7 billion.

TfNSW also noted that the ‘risk of road trauma is pervasive, and a combination of effective road safety measures is required to systematically reduce this risk’.

TfNSW released its first long-term road-safety strategy in December 2012, which introduced the goal of ‘Vision Zero’ — a long-term goal of zero deaths or serious injuries on NSW roads. The terminology was changed to ‘Towards Zero’ in the 2021 Road Safety Plan and has been retained in the NSW Road Safety Action Plan 2022–2026. Towards Zero has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

The objective of this audit is to assess the effectiveness of TfNSW’s delivery of ‘Towards Zero’ in regional areas.

In making this assessment, the audit examined whether TfNSW:

  • is effectively reducing the number of fatalities and serious injuries on regional roads
  • has an effective framework, including governance arrangements, for designing and refreshing the NSW Road Safety Strategy 2012–2021 and the NSW Road Safety Action Plan 2022–2026
  • effectively makes use of whole-of-government and other relevant sources of data to support decision-making, and to evaluate progress and outcomes
  • effectively manages accountabilities, including roles and responsibilities, with respect to road safety outcomes and the use of data.

This audit focused on the policies and strategies used by TfNSW for managing road safety outcomes in regional areas. We did not evaluate individual road safety projects, programs and initiatives as part of this audit.

Whilst Regional Roads and Local Roads (as defined by the Road Network Classifications) are owned and maintained by local councils, we included these roads in this audit as TfNSW may advise and assist councils to promote and improve road safety, as well as manage grant programs that focus on improving road safety outcomes on these roads. Hereafter, unless otherwise stated, references to ‘regional roads’ refer to all classifications of roads in the state which are in regional New South Wales, irrespective of their ownership.

Local councils in regional areas are key stakeholders for the purposes of this audit, and we interviewed eight as part of the audit process (noting that this was not intended to be a representative sample). Road asset management by local councils is also out of scope for this audit as it is the focus of a subsequent performance audit by the Audit Office of New South Wales.b

The Audit Office of New South Wales has undertaken several performance audits relating to road safety since 2009 and these have been referenced while undertaking this audit. They include:

  • Condition of State Roads (August 2006)
  • Improving Road Safety: Heavy Vehicles (May 2009)
  • Improving Road Safety: School Zones (March 2010)
  • Improving Road Safety: Speed Cameras (July 2011)
  • Regional Assistance Programs (May 2018)
  • Mobile speed cameras (October 2018)
  • Rail freight and Greater Sydney (October 2021).

Conclusion

TfNSW has acknowledged that there is a disproportionate amount of road trauma on regional roads in the NSW Road Safety Strategy 2012–2021, the NSW Road Safety Plan 2021, and the NSW Road Safety Action Plan 2022–2026. However, TfNSW has not articulated or evaluated a strategy for implementing road safety policy in regional New South Wales to assist in guiding targeted activities to address regional road trauma. There is also no transparency about the total amount of funding invested in improving road safety outcomes for regional New South Wales.

People living in regional New South Wales make up one-third of the state’s population, but deaths on regional roads make up around two-thirds of the state’s total road toll. This statistic is almost the same in 2023 as it was ten years ago when TfNSW released its first long-term road safety strategy.

More than 70% of people who died on roads between 2012 and 2022 in regional New South Wales were residents of regional areas. Speed is the greatest contributing factor to road fatalities and serious injuries across the entire state. However, it is responsible for more fatalities on regional roads (43%) than in Greater Sydney (34%).

TfNSW’s road safety strategies and plans acknowledge that most road fatalities occur in regional New South Wales but none of its existing strategies or plans show evidence of tailoring measures to suit particular regional settings or ‘hot spots’. There are infrastructure initiatives (such as Saving Lives on Country Roads) and behavioural programs targeting regional areas (such as Driver Reviver). However, these activities are not aligned to a regional-specific strategy or plan that addresses issues specific to regional areas.

TfNSW has state-wide responsibility for managing road safety outcomes. TfNSW advised the audit that a regional plan and regional trauma reduction targets are not needed as the state-wide plan and targets apply equally for all areas of New South Wales, and local road safety factors are best managed by local councils. TfNSW partners with local councils. However, only 52% of councils in regional New South Wales participate in TfNSW’s Local Government Road Safety Program, compared to 84% of councils in metropolitan areas. TfNSW has not undertaken any evaluations to determine whether projects completed under the Local Government Road Safety Program have reduced road trauma at the local level.

Notwithstanding the above points, TfNSW works with local councils (who are road authorities for local roads in their respective areas under the Roads Act 1993) and other key stakeholders such as the NSW Police Force to achieve the NSW Government’s road safety policy objectives.

TfNSW advised that ‘the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. Importantly, delivery of road safety countermeasures is tailored and applied with a focus on road user groups across all geographic locations to maximise trauma reductions’. There may be legitimate reasons for the existing approach, as articulated by TfNSW. However, the proportion of road fatalities in regional New South Wales roads has not reduced since 2012 – despite a long-term reduction in the overall number of deaths on the state’s roads between 2012–2021. The audit report has recommended that a regionally focused implementation plan could address this issue. TfNSW has accepted this report’s recommendation that such a plan be developed.

Specific road safety initiatives targeted to regional areas have not been implemented or expanded

Text removed pursuant to section 36A of the Government Sector Audit Act 1983 (NSW), in compliance with the issuance of a Premier’s certificate preventing the publication of this information.

TfNSW increased the use of other forms of automated enforcement (such as tripling enforcement hours in mobile speed cameras).
However, the use of automated enforcement has a strong metropolitan focus with most red light and fixed speed cameras being in metropolitan areas. Average speed cameras are the only camera type overwhelmingly located in regional areas but these apply only to heavy vehicles and are positioned on major freight routes. 

There is no consolidated, public reporting of what proportion of total road safety funding is directed to regional New South Wales each year. The main source of funding for road safety in New South Wales, the Community Road Safety Fund, has been underspent since 2019.

Fines from camera-detected speeding, red-light and mobile phone use offences are required to be used solely for road safety purposes through the Community Road Safety Fund (CRSF), as set out in the Transport Administration Amendment (Community Road Safety Fund) Act 2012.

The CRSF has been underspent every year since 2019–20. The underspend has increased from 12% in 2019–20 to 20% in 2022–23 where the full year underspend was forecasted to be $104 million. Of this underspend, $13.5 million was dedicated for regional road infrastructure projects. TfNSW advised the audit that much of the underspend is the result of delays to infrastructure projects due to COVID-19, bushfires, and floods, as well as skills shortages. However, TfNSW has not provided any evidence that it had a plan to mitigate these risks – meaning the level of underspend could continue to grow. TfNSW also advised ‘there is no reason to expect budget management and controls will not return to pre-COVID circumstances’.

In total, TfNSW received $700 million in funding for road safety in 2021–22 (including federal contributions and the Community Road Safety Fund). Of this, $411 million (or ~59%) was directed to regional New South Wales. This is the most recent comprehensive financial data that was provided by TfNSW to the audit team. The 2022–23 NSW Budget allocated $880 million for road safety in 2022–23, with a forecasted total allocation for road safety of $1.6 billion in recurrent expenses and $0.8 billion in capital expenditure over the period 2022–23 to 2025–26.

Appendix one – Response from Transport for NSW

Appendix two – The Safe Systems framework and NSW road safety strategies and plans

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #386 - released 30 November 2023

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Planning and managing bushfire equipment

Planning and managing bushfire equipment

Community Services
Justice
Planning
Environment
Local Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Shared services and collaboration
Workforce and capability

What the report is about

This audit assessed the effectiveness of the NSW Rural Fire Service (RFS) and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression.

What we found

The RFS has focused its fleet development activity on modernising and improving the safety of its firefighting fleet, and on the purchase of new firefighting aircraft.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements with local councils, where maintenance responsibilities are described.

What we recommended

  1. Develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability, and research into appropriate technologies to respond to emerging fire risks.
  2. Develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on fire response times, fire response outcomes, and completions of fire hazard reduction works.
  3. Report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks.
  4. Develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in RFS Districts where they are required.
  5. Establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils.
  6. Review and improve processes for timely recording of fleet asset movements, locations, and maintenance status.

This audit assessed how effectively the NSW Rural Fire Service (the RFS) plans and manages the firefighting equipment needed to prevent, mitigate, and suppress bushfires. This audit also examined the role of local councils in managing bushfire equipment fleet assets. Local councils have vested legal ownership of the majority of the land-based firefighting fleet, including a range of legislated responsibilities to carry out fleet maintenance and repairs. The RFS has responsibilities to plan and purchase firefighting fleet assets, and ensure they are ready for use in response to fires and other emergencies.

This report describes the challenges in planning and managing the firefighting fleet, including a confusion of roles and responsibilities between the RFS and local councils in relation to managing certain land-based rural firefighting fleet – a point that has been made in our Local Government financial audits over several years. This role confusion is further demonstrated in the responses of the RFS and local councils to this audit report – included at Appendix one.

The lack of cohesion in roles and responsibilities for managing rural firefighting vehicles increases the risk that these firefighting assets are not properly maintained and managed, and introduces a risk that this could affect their readiness to be mobilised when needed.

While the audit findings and recommendations address some of the operational and organisational inefficiencies in relation to rural firefighting equipment management, they do not question the legislative arrangements that govern them. This is a matter for the NSW Government to consider in ensuring the fleet arrangements are fit for purpose, and are clearly understood by the relevant agencies.

The NSW Rural Fire Service (hereafter the RFS) is the lead combat agency for bushfires in New South Wales, and has the power to take charge of bushfire prevention and response operations anywhere in the State. The RFS has responsibilities to prevent, mitigate and suppress bushfires across 95% of the State, predominantly in the non-metropolitan areas of New South Wales. Fire and Rescue NSW is responsible for fire response activity in the cities and large townships that make up the remaining five per cent of the State.

The RFS bushfire fleet is an integral part of the agency's overall bushfire risk management. The RFS also uses this fleet to respond to other emergencies such as floods and storms, motor vehicle accidents, and structural fires. Fleet planning and management is one of a number of activities that is necessary for fire mitigation and suppression.

The Rural Fires Act 1997 (Rural Fires Act) imposes obligations on all landowners and land managers to prevent the occurrence of bushfires and reduce the risk of bushfires from spreading. Local councils have fire prevention responsibilities within their local government areas, principally to reduce fire hazards near council owned or managed assets, and minor roads.

The RFS is led by a Commissioner and is comprised of both paid employees and volunteer rural firefighters. Its functions are prescribed in the Rural Fires Act and related legislation such as the State Emergency Rescue Management Act 1989. The RFS functions are also described in Bush Fire Risk Management Plans, the State Emergency Management Plan, District Service Agreements, and RFS procedural documents. Some of the core responsibilities of the RFS include:

  • preventing, mitigating, and suppressing fires across New South Wales
  • recruiting and managing volunteer firefighters in rural fire brigades
  • purchasing and allocating firefighting fleet assets to local councils
  • establishing District Service Agreements with local councils to give the RFS permissions to use the fleet assets that are vested with local councils
  • carrying out fleet maintenance and repairs when authorised to do so by local councils
  • inspecting the firefighting fleet
  • supporting land managers and private property owners with fire prevention activity.

In order to carry out its legislated firefighting functions, the RFS relies on land-based vehicles, marine craft, and aircraft. These different firefighting appliance types are referred to in this report as the firefighting fleet or fleet assets.

RFS records show that in 2021 there were 6,345 firefighting fleet assets across NSW. Most of the land-based appliances commonly associated with firefighting, such as water pumpers and water tankers, are purchased by the RFS and vested with local councils under the Rural Fires Act. The vesting of firefighting assets with local councils means that the assets are legally owned by the council for which the asset has been purchased. The RFS is able to use the firefighting assets through District Service Agreements with local councils or groups of councils.

In addition to the land-based firefighting fleet, the RFS owns a fleet of aircraft with capabilities for fire mitigation, suppression, and reconnaissance during fire events. The RFS hires a fleet of different appliances to assist with fire prevention and hazard reduction works. These include aircraft for firefighting and fire reconnaissance, and heavy plant equipment such as graders and bulldozers for hazard reduction. Hazard reduction works include the clearance of bush and grasslands around major roads and protected assets, and the creation and maintenance of fire trails and fire corridors to assist with fire response activity.

The RFS is organised into 44 RFS Districts and seven Area Commands. The RFS relies on volunteer firefighters to assist in carrying out most of its firefighting functions. These functions may include the operation of the fleet during fire response activities and training exercises, and the routine inspection of the fleet to ensure it is maintained according to fleet service standards. Volunteer fleet inspections are supervised by the RFS Fire Control Officer.

In 2021 there were approximately 73,000 volunteers located in 1,993 rural fire brigades across the State, making the RFS the largest volunteer fire emergency service in Australia. In addition to brigade volunteers, the RFS has approximately 1,100 salaried staff who occupy leadership and administrative roles at RFS headquarters and in the 44 RFS Districts.

Local councils have legislative responsibilities relating to bushfire planning and management. Some of the core responsibilities of local councils include:

  • establishing and equipping rural fire brigades
  • contributing to the Rural Fire Fighting Fund
  • vested ownership of land-based rural firefighting equipment
  • carrying out firefighting fleet maintenance and repairs
  • conducting bushfire prevention and hazard reduction activity.

The objective of this audit was to assess the effectiveness of the RFS and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression. From the period of 2017 to 2022 inclusive, we addressed the audit objective by examining whether the NSW RFS and local councils effectively:

  • plan for current and future bushfire fleet requirements
  • manage and maintain the fleet required to prevent, mitigate, and suppress bushfires in NSW.

This audit did not assess:

  • the operational effectiveness of the RFS bushfire response
  • the effectiveness of personal protective equipment and clothing
  • the process of vesting of rural firefighting equipment with local councils
  • activities of any other statutory authorities responsible for managing bushfires in NSW.

As the lead combat agency for the bushfire response in NSW, the RFS has primary responsibility for bushfire prevention, mitigation, and suppression.

Three local councils were selected as case studies for this audit, Hawkesbury City Council, Wagga Wagga City Council and Uralla Shire Council. These case studies highlight the ways in which the RFS and local councils collaborate and communicate in rural fire districts.

Conclusion

The RFS has focused its fleet development activity on modernising and improving the safety of its land-based firefighting fleet, and on the purchase of new firefighting aircraft

The RFS has reduced the average age of the firefighting fleet from approximately 21 years in 2017, to approximately 16 years in 2022. The RFS has also enhanced the aerial fleet with the addition of six new aircraft to add to the existing three aircraft.

Recommendations from inquiries into the 2019–20 bushfires have driven significant levels of fleet improvement activity, mainly focused on the addition of safety features to existing fleet appliances. The RFS has dedicated most of its efforts to purchasing and refurbishing firefighting appliances of the same type and in the same volumes year on year.

However, the RFS is unable to demonstrate how the composition, size, or the locations of the NSW firefighting fleet is linked to current fire prevention, mitigation, and suppression requirements, or future fire risks.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks

The RFS has not established a methodology to assess the composition or volumes of the firefighting fleet against fire activity and fire risks in the 44 NSW Rural Fire Districts. The RFS has not developed performance measures or targets to assess or report on fire response times in each of its districts, nor has it developed measures to assess the effectiveness of responses according to fire sizes and fire types. Similarly, the RFS has limited performance measures to assess fire prevention activity, or to assess fuel load reduction works, so it is not possible to assess whether its fleet capabilities are fit for these purposes.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet

RFS fleet planning and fleet allocations are based on historical fleet sizes and compositions, and distributed to locations where there are appropriately trained brigade volunteers.

The RFS takes an asset protection approach to bushfire prevention and planning that is based on the Australian and New Zealand Standard for Risk Management. This approach requires that the RFS identify assets at risk of fire, and develop treatment plans to protect these assets. However, fleet requirements are not linked to NSW asset protection plans, meaning that fleet is not allocated according to the identified risks in these plans. Further, the RFS does not develop fire prevention plans for areas where there are no identified assets.

The RFS has not conducted future-focused fleet research or planning into technologies that match fleet capabilities to emerging or future fire risks. Since the significant fire events of 2019–2020, the RFS has not changed its approach to planning for, or assessing, the operational capabilities of the fleet. The RFS advises it is scoping a project to match resources to risk, which it plans to commence in 2023.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements where maintenance responsibilities are described

The RFS does not have a framework to ensure that District Service Agreements with local councils are accurate. Almost two thirds of service agreements have not been reviewed in the last ten years, and some do not reflect actual maintenance practices. There is no formalised process to ensure communication occurs between the RFS and local councils for fleet management and maintenance.

RFS fleet management systems at the central level are not integrated with RFS district-level databases to indicate when fleet assets are in workshops being maintained and serviced. The RFS has a new centralised Computer Aided Dispatch System that relies on accurate fleet locations and fleet condition information in order to dispatch vehicles to incidents and fires. A lack of interface between the district-level fleet systems and the centralised RFS fleet dispatch system, may impact on operational responses to bushfires. 

The RFS has not made significant changes to the size or composition of the firefighting fleet in the past five years and does not have an overarching strategy to drive fleet development

Since 2017, the RFS has made minimal changes to its firefighting fleet volumes or vehicle types. The RFS is taking a fleet renewal approach to fleet planning, with a focus on refurbishing and replacing ageing firefighting assets with newer appliances and vehicles of the same classification and type. While the RFS has adopted a fleet renewal approach, driven by its Appliance Replacement Program Guide, it does not have a strategy or framework to guide its future-focused fleet development. There is no document that identifies and analyses bushfire events and risks in NSW, and matches fleet resources and fleet technologies to meet those risks. The RFS does not have fleet performance measures or targets to assess whether the size and composition of the fleet is meeting current or emerging bushfire climate hazards, or fuel load risks across its 44 NSW Fire Districts.

The RFS fleet currently comprises approximately 4,000 frontline, operational firefighting assets such as tankers, pumpers, and air and marine craft, and approximately 2,300 logistical vehicles, such as personnel transport vehicles and specialist support vehicles. Of the land-based firefighting vehicles, the RFS has maintained a steady number of approximately 3,800 tankers and 65 pumpers, year on year, for the past five years. This appliance type is an essential component of the RFS land-based, firefighting fleet with capabilities to suppress and extinguish fires.

Since 2017, most RFS fleet enhancement activity has been directed to upgrades and the modernisation of older fleet assets with new safety features. There is limited evidence of research into new fleet technologies for modern firefighting. The RFS fleet volumes and fleet types have remained relatively static since 2017, with the exception of the aerial firefighting fleet. Since 2017, the RFS has planned for, and purchased, six additional aircraft to add to the existing three aircraft in its permanent fleet.

While the RFS has made minimal changes to its fleet since 2017, in 2016 it reduced the overall number of smaller transport vehicles, by purchasing larger vehicles with increased capacity for personnel transport. The consolidation of logistical and transport vehicles accounts for an attrition in fleet numbers from 7,058 in 2016, to 6,315 in 2017 as shown in Exhibit 2.

The firefighting fleet management system is not always updated in a timely manner due to insufficient RFS personnel with permissions to make changes in the system

The RFS uses a fleet management system known as SAP EAM to record the location and status of firefighting fleet assets. The system holds information about the condition of the firefighting fleet, the home location of each fleet asset, and the maintenance, servicing, and inspection records of all assets. The RFS uses the system for almost all functions related to the firefighting fleet, including the location of vehicles so that they can be dispatched during operational exercises or fire responses.

Staff at RFS Headquarters are responsible for creating and maintaining asset records in the fleet management system. RFS District staff have limited permissions in relation to SAP EAM. They are able to raise work orders for repairs and maintenance, upload evidence to show that work has been done, and close actions in the system.

RFS District staff are not able to enter or update some fleet information in the system, such as the location of vehicles. When an RFS District receives a fleet appliance, it cannot be allocated to a brigade until the location of the asset is accurately recorded in the system. The location of the asset must be updated in the SAP EAM system by staff at RFS Headquarters. District staff can request system support from staff at RFS Headquarters to enter this information. At the time of writing, the position responsible for updating the fleet management system at RFS Headquarters was vacant, and RFS District personnel reported significant wait times in response to their service requests.

The RFS conducts annual audits of SAP EAM system information to ensure data is accurate and complete. RFS staff are currently doing data cleansing work to ensure that fleet allocations are recorded correctly in the system.

Communication between brigades, local councils and the RFS needs improvement to ensure that fleet information is promptly updated in the fleet management system

RFS brigade volunteers do not have access to the fleet management system. When fleet assets are used or moved, volunteers report information about the location and condition of the fleet to RFS District staff using a paper-based form, or by email or phone. Information such as vehicle mileage, engine hours, and defects are all captured by volunteers in a logbook which is scanned and sent to RFS District staff. RFS District staff then enter the relevant information into the fleet management system, or raise a service ticket with RFS Headquarters to enter the information.

Brigade volunteers move fleet assets for a range of reasons, including for fire practice exercises. If volunteers are unable to report the movement of assets to RFS District staff in a timely manner, this can lead to system inaccuracies. Lapses and backlogs in record keeping can occur when RFS staff at district offices or at Headquarters are not available to update records at the times that volunteers report information. A lack of accurate record keeping can potentially impact on RFS operational activities, including fire response activity.

Brigade volunteers notify RFS District staff when fleet appliances are defective, or if they have not been repaired properly. District staff then enter the information into the fleet management system. The inability of volunteers to enter information into the system means they have no visibility over their requests, including whether they have been approved, actioned, or rejected.

Local councils are responsible for servicing and maintaining the firefighting fleet according to the Rural Fires Act, but this responsibility can be transferred to the RFS through arrangements described in local service agreements. Council staff record all fleet servicing and maintenance information in their local systems. The types of fleet information that is captured in local council records can vary between councils. RFS staff described the level of council reporting, and the effectiveness of this process, as 'mixed'.

Councils use different databases and systems to record fleet assets, and some councils are better resourced for this activity than others

Firefighting fleet information is recorded in different asset management systems across NSW. Each council uses its own asset management system to record details about the vested fleet assets. All three councils that were interviewed for this audit had different systems to record information about the fleet. In addition, the type of information captured by the three councils was varied.

Exhibit 10: Systems used by local councils to manage the firefighting fleet
System Hawkesbury City Council Uralla Shire Council Wagga Wagga City Council
Financial asset management system TechnologyOne Civica Assetic
Asset management system TechnologyOne Manual MEX

Source: Audit Office analysis of information provided by the RFS and local councils.

Local councils have varying levels of resources and capabilities to manage the administrative tasks associated with the firefighting fleet. Some of the factors that impact on the ability of councils to manage administrative tasks include: the size of the council; the capabilities of the information management systems, the size of the staff team, and the levels of staff training in asset management.

Uralla Shire Council is a small rural council in northern NSW. This council uses financial software to record information about the firefighting fleet. While staff record information about the condition of the asset, its replacement value, and its depreciation, staff do not record the age of the asset, or its location. Staff manually enter fleet maintenance information into their systems. Uralla Shire Council would like to purchase asset maintenance software that generates work orders for fleet repairs and maintenance. However, the council does not have trained staff in the use of asset management software, and the small size of the fleet may not make it financially worthwhile.

The Hawkesbury City Council uses a single system to capture financial and asset information associated with the firefighting fleet. Hawkesbury is a large metropolitan council located north-west of Sydney, with a relatively large staff team in comparison with Uralla Shire Council. The Hawkesbury City Council has given RFS District staff access to their fleet information system. RFS District staff can directly raise work orders for fleet repairs and maintenance through the council system, and receive automated notifications when the work is complete.

Two of the three audited councils report that they conduct annual reviews of fleet assets to assess whether the information they hold is accurate and up-to-date.

More than half of the fleet maintenance service agreements between the RFS and local councils have not been reviewed in ten years, and some do not reflect local practices

Local councils have a legislated responsibility to service, repair, and maintain the firefighting fleet to service standards set by the RFS. Councils may transfer this responsibility to the RFS through District Service Agreements. The RFS Districts are responsible for ensuring that the service agreements are current and effective.

The RFS does not have monitoring and quality control processes to ensure that service agreements with local councils are reviewed regularly. The RFS has 73 service agreements with local councils or groups of councils. Sixty-three per cent of service agreements had not been reviewed in the last ten years. Only four service agreements specify an end date and, of those, one agreement expired in 2010 and had not been reviewed at the time of this audit.

The RFS does not have a framework to ensure that service agreements with local councils reflect actual practices. Of the three councils selected for audit, one agreement does not describe the actual arrangements for fleet maintenance practices in RFS Districts. The service agreement with Hawkesbury City Council specifies that the RFS will maintain the firefighting fleet on behalf of council when, in fact, council maintains the firefighting fleet. The current agreement commenced in 2012, and at the time of writing had not been updated to reflect local maintenance practices.

When District Service Agreements are not reviewed periodically, there is a risk that neither local councils nor the RFS have clear oversight of the status of fleet servicing, maintenance, and repairs.

RFS District Service Agreements set out a requirement that RFS and local councils establish a liaison committee. Liaison committees typically include council staff, RFS District staff, and RFS brigade volunteers. While service agreements state that liaison committees must meet periodically to monitor and review the performance of the service agreement, committee members determine when and how often the committee meets.

RFS District staff and staff at the three audited councils are not meeting routinely to review or update their service agreements. At Wagga Wagga City Council, staff meet with RFS District staff each year to report on activity to fulfil service agreement requirements. Uralla Shire Council staff did not meet routinely with RFS District staff before 2021. When liaison committees do not meet regularly, there is a risk that the RFS and local councils have incorrect or outdated information about the location, status, or condition of the firefighting fleet. Given that councils lack systems to track and monitor fleet locations, regular communication between the RFS and local councils is essential.

The RFS has not established processes to ensure that local councils and RFS District personnel meet and exchange information about the fleet. Of the three councils selected for this audit, one council had not received information about the number, type, or status of the fleet for at least five years, and did not receive an updated list of appliances until there was a change in RFS District personnel. This has impacted on the accuracy of council record keeping. Councils do not always receive notification about new assets or information about the location of assets from the RFS, and therefore cannot reflect this information in their accounting and reporting.

RFS area commands audit system records to ensure fleet inspections occur as planned, but central systems are not always updated, creating operational risks

RFS District staff are required by the Rural Fires Act to ensure the firefighting fleet is inspected at least once a year. Regular inspections of the fleet are vital to ensure that vehicles are fit-for-purpose and safe for brigade volunteers. Inspections are also fundamental to the operational readiness and capability of RFS to respond to fire incidents.

RFS Area Command personnel conduct audits of fleet maintenance data to ensure that fleet inspections are occurring as planned. These inspections provide the RFS with assurance that the fleet is being maintained and serviced by local council workshops, or third-party maintenance contractors.

Some RFS Districts run their own fleet management systems outside of the central management system. They do this to manage their fleet inspection activity effectively. Annual fleet inspection dates are programmed by staff at RFS Headquarters. Most of the inspection dates generated by RFS Headquarters are clustered together and RFS Districts need to separate inspection times to manage workloads over the year. Spreading inspection dates is necessary to avoid exceeding the capacity of local council workshops or third party contractors, and to ensure that fleet are available during the bushfire season.

The fleet inspection records at RFS Headquarters are not always updated in a timely manner to reflect actual inspection and service dates of vehicles. District staff are not able to change fleet inspection and service dates in the central management system because they do not have the necessary permissions to access the system. The usual practice is for RFS District staff to notify staff at RFS Headquarters, and ask them to retrospectively update the system. As there is a lag in updating the central database, at a point in time, the actual inspection and service dates of vehicles can be different to the dates entered in the central fleet management system.

Fleet inspection and maintenance records must be accurately recorded in the central RFS management system for operational reasons. RFS Headquarters personnel need to know the location and maintenance status of fleet vehicles at all times in order to dispatch vehicles to incidents and fires. The RFS fleet management system is integrated with a new Computer Aided Dispatch System. The Computer Aided Dispatch System assigns the nearest and most appropriate vehicles to fire incidents. The system relies on accurate fleet locations and fleet condition information in order to dispatch these vehicles.

There is a risk that RFS Headquarters' systems do not contain accurate information about the location and status of vehicles. Some may be in workshops for servicing and repair, while the system may record them as available for dispatch. As there are many thousands of fleet vehicles, all requiring an annual service and inspection, a lack of accurate record keeping has wide implications for State fire operations.

RFS is currently exploring ways to improve the ways in which fleet inspections are programmed into the fleet management system.

RFS provides funds to councils to assist with maintaining the firefighting fleet, but does not receive fleet maintenance cost information from all local councils

Each year the RFS provides local councils with a lump sum to assist with the cost of repairing and maintaining the firefighting fleet. This lump sum funding is also used for meeting the costs of maintaining brigade stations, utilities, and other miscellaneous matters associated with RFS business.

In 2020–21, the RFS provided NSW local councils with approximately $23 million for maintenance and repairs of appliances, buildings, and utilities. Ninety councils were provided with lump sum funding in 2021, receiving on average $257,000. The amounts received by individual councils ranged from $56,200 to $1,029,884.

Some councils provide itemised repairs and maintenance reports to RFS District staff, showing the work completed and the cost of that work. However, not all councils collect this information or provide it to the RFS. Local councils collect fleet maintenance information in their local council systems. In some cases, the responsibility for fleet maintenance is shared across a group of councils, and not all councils have oversight of this process.

The RFS has not taken steps to require local councils to provide itemised maintenance costings for the firefighting fleet. Thus, the RFS does not have a clear understanding of how local councils are spending their annual fleet maintenance funding allocations. The RFS does not know if the funding allocations are keeping pace with the actual cost of repairing and maintaining the fleet.

RFS District staff report that funding shortfalls are impacting on the prioritisation of fleet servicing and maintenance works in some council areas. When fleet servicing and maintenance is not completed routinely or effectively, there is a risk that it can negatively impact the overall condition and lifespan of the vehicle. Poor processes in relation to fleet maintenance and repair risk impacting on the operational capabilities of the fleet during fire events.

The timeliness and effectiveness of fleet servicing and maintenance is affected by resource levels in RFS Districts and local councils

Local councils have a legislated responsibility to service and maintain the firefighting fleet to the service standards set by the RFS. Fleet maintenance is usually done by the entity with the appropriate workshops and resources, and the maintenance arrangements are described in District Service Agreements. RFS District staff conduct annual inspections to ensure that the firefighting fleet has been serviced and maintained appropriately, and is safe for use by brigade volunteers. If the fleet has not been maintained to RFS service standards or timelines, RFS District staff may work with local councils to support or remediate these works.

The effectiveness of this quality control activity is dependent on relationships and communication between the RFS Districts and local councils. While some RFS staff reported having positive relationships with local councils, others said they struggled to get fleet maintenance work done in a timely manner. Some councils reported that funding shortfalls for fleet maintenance activity was impacting on the prioritisation of RFS fleet maintenance works. When fleet maintenance work is not completed routinely or effectively, it can negatively impact on the overall condition and lifespan of the vehicle. It can also reduce the capacity of the RFS to respond to fire events.

Fleet quality control activities are carried out by RFS District staff. In some of the smaller RFS Districts, one person is responsible for liaising with local councils and brigade volunteers about fleet maintenance and repairs. In the regions where resources are limited, there is less ability to maintain ongoing communication. This is impacting on fleet service and maintenance timelines and the timeliness of fleet monitoring activity.

The RFS has mutual support arrangements with agencies in NSW and interstate, though shared fleet levels are yet to be quantified

The RFS has arrangements with state, federal, and international fire authorities to provide mutual support during fire incidents. In NSW, the RFS has agreements with the three statutory authorities – Fire and Rescue NSW, the Forestry Corporation of NSW, and the NSW National Parks and Wildlife Service. The agreement with Fire and Rescue NSW provides a framework for cooperation and joint operations between the agencies. The agreements with the Forestry Corporation of NSW and the NSW National Parks and Wildlife Service describe the control and coordination arrangements for bush and grass fires across NSW. These arrangements are set out in legislation and incorporated into local Bush Fire Risk Management Plans.

The RFS has agreements with fire authorities in three of the four Australian states and territories that share a border with NSW – the Australian Capital Territory, Queensland, and South Australia. Each agreement sets out the arrangements for mutual assistance and joint operations, including arrangements for sharing aircraft. The agreement between the RFS and Victoria had lapsed. The RFS told the NSW Bushfire Inquiry that the agreement with Victoria would be finalised by June 2020. In June 2022, the RFS reported that the agreement was in the process of being finalised.

The arrangements for mutual aid from Western Australia, Northern Territory and Tasmania, are managed by the National Resource Sharing Centre. These agreements set out the arrangements for interstate assistance between Australian fire services, emergency services, and land management agencies in those states and territories.

These mutual support arrangements may assist during state-based fire events. However, when there are competing demands for resources, such as during the bushfires of 2019–2020, there can be limits on fleet availability. During the 2019–2020 fires, resources were stretched in all jurisdictions as these fires affected NSW, Victoria, and Queensland.

There are opportunities for the RFS and other NSW agencies to quantify fleet resources across the State and identify assets that can be mobilised for different fire activities. This form of fleet planning may be used to enhance surge capabilities during times of high fire activity. There are also opportunities for the RFS and other agencies to match the levels of shared assets to projected bushfire risks.

Appendix one – Responses from agencies 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #376 - released 27 February 2023

 

Published

Actions for New South Wales COVID-19 vaccine rollout

New South Wales COVID-19 vaccine rollout

Health
Internal controls and governance
Management and administration
Project management
Risk
Service delivery

What the report is about

The Australian Government led and implemented the Australian COVID-19 vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

This audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine roll out in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over.

What we found

On 16 October 2021, NSW Health, in partnership with the Australian Government's vaccination program, achieved its first objective to fully vaccinate 80% of people in NSW aged 16 and over. Demand for the vaccine reduced in December 2021, and NSW Health did not reach its target of 95% fully vaccinated for people aged 16 and over until June 2022.

Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

As at 19 October 2022, vaccination rates for Aboriginal peoples and culturally and linguistically diverse people remained below the 95% target.

What we recommended

By June 2023, NSW Health should conduct a comprehensive review of the COVID-19 vaccine rollout and incorporate lessons learned into pandemic response plans.

The first three cases of COVID-19 in New South Wales were diagnosed in January 2020. By 30 June 2021, 128 people were being treated in hospital and one person was in intensive care. By the end of December 2021, 187,504 total cases and 663 deaths were reported in New South Wales. As at 27 October 2022, NSW Health reported more than three million total cases and 5,430 deaths.

The COVID-19 pandemic continues to have a significant impact on the people and the health sector of New South Wales. The Australian, state, territory, and local governments have directed significant resources towards health responses and economic recovery.

On 13 November 2020, National Cabinet (comprised of the Australian, state, and territory governments) endorsed the Australian COVID-19 Vaccination Policy. Australia's vaccination program was launched on 21 February 2021 with the goal of providing safe and effective vaccines to the people who most needed them as quickly as possible, to support the physical, mental and economic wellbeing of the nation.

The Australian Government led and implemented the Australian vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

The overall objective of this audit was to assess the effectiveness and efficiency of NSW Health’s contribution to the Australian COVID-19 vaccine rollout. It is important to note that in New South Wales, primary care providers (GPs and pharmacies) and aged care providers administered the majority of vaccines. Primary care providers and aged care providers are the responsibility of the Australian Government.

The audit had a particular focus on whether NSW Health:

  • set clear vaccination targets underpinned and/or guided by evidence
  • managed the rollout of the vaccination program effectively and efficiently
  • managed demand of vaccines effectively and efficiently.

The audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine rollout in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over. We did not audit the subsequent rollout for ages five to 15, or the booster rollout (third and fourth doses) as these activities mostly occurred outside the date of our review.

This audit also did not assess the Australian Government’s allocation of vaccine supplies to New South Wales because we do not audit the Australian Government's activities. On 17 August 2022, the Australian National Audit Office completed a performance audit which assessed the Australian Department of Health and Aged Care's effectiveness in the planning and implementation of Australia's COVID-19 vaccine rollout.

This audit is one of a series of audits that have been completed or are in progress regarding the New South Wales COVID-19 emergency response. This includes the planned performance audit ‘Coordination of the response to COVID-19 (June to November 2021)’, and financial audit assurance activities focusing on Local Health District processes and controls to manage the receipt, distribution and inventory management of vaccine stock. The Audit Office New South Wales '2022–25 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

Conclusion

By 12 December 2021, NSW Health had administered two doses of vaccines to one third of eligible people in New South Wales aged 16 and over – contributing significantly to the achievement of the NSW Government vaccination target of 80% fully vaccinated before 31 December 2021. Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

Vaccination levels in some vulnerable populations remain below the 95% double dose target currently in place. Access to quality data to regularly measure vaccination rates in some vulnerable populations remains an ongoing challenge for the NSW and Australian Governments. As a result, NSW Health is unable to fully ensure it has delivered on its shared responsibility with the Australian Government to vaccinate vulnerable people.

NSW Health managed challenges regarding the uncertain supply of vaccines from the Australian Government and filled gaps beyond its agreed responsibilities in the National Partnership on COVID-19 Response. During the Delta outbreak of the pandemic, NSW Health sought to achieve the best possible public health outcome from limited vaccine supply by opening up additional vaccination clinics in highly affected areas and redistributing vaccine supplies from areas with fewer cases to highly affected local government areas in south west Sydney.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available. Our financial audit report, 'Health 2022', includes additional information on vaccine supply stock held by NSW Health.

NSW Health demonstrated agility by using a range of strategies to promote vaccination, including direct engagement with communities to develop culturally appropriate services such as pop-up clinics. NSW Heath recruited prominent community members, such as faith leaders, elders and sportspeople, to promote vaccination within their communities. However, at the date of this report, there are still vulnerable populations with vaccination rates lower than the current 95% double dose vaccination target. There is also a lack of regularly updated data for some cohorts which prevents NSW Health from accurately monitoring vaccination rates in some populations it has identified as vulnerable.

In March 2021, NSW Health identified that the booking system provided by the Australian Government was an online directory of vaccine clinics and would not manage bookings. To overcome this, NSW Health amended an internal-use system to be publicly facing. This solution was not user-friendly for staff or those seeking to make an appointment. Between June to September 2021, NSW Health progressively resolved booking system related issues, by developing and rolling out a new purpose-built booking solution for NSW Health vaccination clinics.

Appendix one – Response from agency

Appendix two – Australian audits on the vaccine rollouts

Appendix three – Committee members 

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #369 - released 7 December 2022

Published

Actions for NSW planning portal

NSW planning portal

Planning
Industry
Environment
Local Government
Information technology
Project management
Risk

What the report is about

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal).

Using the portal, relevant planning activities can be carried out online, including all stages of development applications.

The portal has been developed under three separate business cases in 2013, 2014 and 2020.

In late 2019, the government mandated the use of the portal for all development applications. This decision took effect across 2020–21.

This audit assessed the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. 

What we found

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information, and allow them to prepare and submit development applications online.

Shortcomings in the department's initial planning and management of the program led to a significant time overrun. It has taken the department longer and cost significantly more to implement the portal than first anticipated. 

In recent years the department has improved the planning, implementation and governance of the ePlanning program, resulting in improved delivery of the portal’s core functions.

The department now has a clear view of the scope necessary to finalise the program, but has not yet published the services it plans to implement in 2022 and 2023.

Mandating the use of the portal for all development applications changed the program's strategic risk environment and required the department to work more closely with a cohort of stakeholders, many of whom did not want to adopt the portal.

Despite this change, the department kept its overall delivery approach the same.

While implementation of the portal has delivered financial benefits, the department has overestimated their value.

The Department has only reported benefits since 2019 and has not independently assured the calculation of benefits.

What we recommended

By December 2022, the department should:

  • publish a roadmap of the services it expects to release on the portal across 2022 and 2023
  • update its ePlanning program assumptions, benefits targets and change management approach to reflect the government's decision to mandate the use of the portal for all stages of a development application
  • independently assure and report publicly the correct calculation of ePlanning program benefits.

Fast facts

  • 10 years taken to implement the portal when completed
  • 3 years longer than initially planned to implement the portal
  • $146m capital expenditure on the portal when completed
  • $38.5m more spent than planned in the business cases.

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal, or the planning portal). The department defines the portal as an online environment where community, industry and government can work together to better understand and meet their obligations under the Environmental Planning and Assessment Act 1979 (NSW). Using the portal, relevant planning activities can be carried out online throughout New South Wales. This includes, but is not limited to:

  • applying for and gaining planning approval
  • applying for and gaining approval for building works, sub-dividing land and similar activities
  • issuing occupancy and other certificates.

The portal has been developed under three separate business cases. The first business case in 2013 led to the creation of a central portal, which made planning information available to view by planning applicants and allowed some planning applications to be lodged and tracked online.

Under a second business case prepared in 2014, the department set out to improve and widen the functions available via the portal. The department prepared a third business case in 2020 to fund further improvements to the portal over the period July 2020 to June 2023. The third business case also extended the portal's functions to support the building and occupation stages of the planning cycle.

In late 2019, the government mandated the use of the portal for all stages of development applications. This decision took effect across 2020–21 and applied to all councils as well as certifiers and others involved in the planning process.

The objective of this performance audit was to assess the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. We investigated whether:

  • delivery of the NSW planning portal was planned effectively
  • sound governance arrangements are in place to ensure effective implementation of the program
  • users of the NSW planning portal are supported effectively to adopt and use the system.
Conclusion

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information and allow them to prepare and submit development applications online. Implementation was initially hindered by deficiencies in planning and it has taken the department significantly longer and cost significantly more to implement the portal than first anticipated. While the portal's implementation has delivered financial benefits, the department has overestimated their value. As a result, the department cannot yet demonstrate that the portal has achieved overall financial benefits, relative to its costs.

In the first two years of the ePlanning program, the department delivered a portal that allowed planners, developers, certifiers and the public to view important planning information. However, the department found the delivery of a second, transactional version of the portal in 2017 to be much more challenging. This version was intended to offer more integrated information and allow development applications to be submitted and managed online. The department did not rollout this version after a pilot showed significant weaknesses with the portal's performance. A subsequent review found that this was partly because the department did not have a clear view of the portal’s role or the best way to implement it. In recent years the department has improved the planning, implementation and governance of the ePlanning program resulting in improved delivery of the portal’s core functions.

By the time the program reaches its scheduled completion in 2023, it will have taken the department ten years and around $146 million in capital expenditure to implement the portal. This will be significantly longer and more expensive than the department originally expected. This overrun is partly due to an increased scope of services delivered through the portal and an initial under-appreciation of what is involved in creating a standard, central resource such as the portal. The department also experienced some significant implementation difficulties – which saw the transactional portal discontinued after it was found to be not fit for purpose. Following this, the department re-set the program in 2017–18 and re-planned much of the portal's subsequent development.

In November 2019, the New South Wales Government decided to mandate the use of the portal for all stages of development applications by the end of 2020–21. The department had previously planned that the portal would be progressively adopted by all councils and other stakeholders over the five years to 2025. The decision to mandate the portal's use for all development applications brought forward many of the portal's benefits as well as the challenges of its implementation. The department did not change its overall delivery approach in response to the changed risks associated with the government's decision to mandate use of the portal.

The current version of the portal has given the department more timely and comprehensive planning information and has helped New South Wales to provide continuous planning services during COVID-19 lockdowns, which interrupted many other public functions. The portal has also delivered financial benefits, however the department has not independently assured benefits calculations carried out by its consultant, and the reported benefits are overstated. In addition, some stakeholders report that the portal is a net cost to their organisation. This has included some certifiers and some councils which had implemented or had started to implement their own ePlanning reforms when use of the portal was mandated in 2019. The department now needs to address the issues faced by these stakeholders while continuing to deliver the remaining improvements and enhancements to the portal. Over the remaining year of the program, it will be critical that the department focuses on the agreed program scope and carefully evaluates any opportunities to further develop the portal to support future planning reforms.

This part of the report sets out how:

  • the ePlanning program has been planned and delivered
  • users of the portal have been supported
  • the program has been governed.

This part of the report sets out the ePlanning program's:

  • expected and reported financial benefits
  • calculation of financial benefits.

In 2019, the department increased its expectations for net financial benefits

The department's three ePlanning business cases each forecast substantial financial benefits from the implementation of the planning portal. The department expected that most financial benefits would flow to planning applicants due to a quicker and more consistent planning process. It also expected that government agencies and councils would benefit from the portal.

Exhibit 6: Summary of the financial benefits originally expected
  Business case 1
($ million)
Business case 2
($ million)
Business case 3
($ million)
Total
($ million)
Benefits 90.0 44.3 270.9 405.2
Costs 43.3 29.4 89.8 162.5
Net benefits 46.7 15.0 181.1 242.7

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for business case 1, 2 and 3 amounts are expressed in 2013, 2015 and 2019 dollars respectively. All amounts are discounted at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

In 2019 the department commissioned a review to explore opportunities to better identify, monitor and realise the benefits of the ePlanning program. Using this work, the department updated the expected benefits for business cases 1 and 2 to take account of:

  • errors and miscalculations in the original benefits calculations
  • slower delivery of the portal and changes to the take-up of portal services by councils
  • changes to the services supported by the portal.
Exhibit 7: Summary of the financial benefits expected for business case 1 and 2 after the 2019 update
  Original business case 1 and 2 (combined)
($ million)
New business case 1 and 2 (combined)
($ million)
Benefits 134.3 210.6
Costs 72.7 96.3
Net benefits 61.7 114.3

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for the original business case 1 and 2 are expressed in 2013 and 2015 dollars respectively. The new combined amount is expressed in 2019 dollars. All amounts are discounted or inflated at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

Reported benefits significantly exceed the current targets

In September 2021, the department reported that the program had achieved $334 million of benefits over the three financial years up to June 2021 plus the first two months of 2021–22. These reported benefits were significantly higher than expected. 

Exhibit 8: Reported financial benefits from the ePlanning program
  2018–19
($ million)
2019–20
($ million)
2020–21
($ million)
July to August 2021
($ million)
Total
($ million)
Benefits 5.2 68.8 214.7 45.1 333.8
Target 2.5 14.4 56.7 19.2 92.8
Amount and per cent above target 2.7
108%
54.4
378%
158
279%
25.9
135%
241
260%

Source: Audit Office analysis of data provided by the Department of Planning and Environment.

The department attributes the higher-than-expected financial benefits to the following:

  • benefit targets have not been updated to reflect the impact of the 2019 decision to mandate the use of the portal for all development applications. This decision brought forward the expected benefits as well as potential costs of the program. However, the department did not update its third business case which was draft at the time. The business case was subsequently approved in July 2020
  • one-off cost savings for agencies not having to develop their own systems
  • public exhibitions of planning proposals continuing to be available online during 2020 when some newspapers stopping printing due to COVID-19.

The calculation of benefits is overstated

The department reported $334 million of benefits in September 2021 due to the ePlanning program. This calculation is overstated because:

  • a proportion of reported benefits is likely to be due to other planning reforms
  • the calculation of the largest single benefit is incorrect
  • the reported benefits may not fully account for dis-benefits reported by some stakeholders.

The program’s benefits are calculated primarily from changes in planning performance data, such as the time it takes to determine a planning development application. The department currently attributes the benefits from shorter planning cycles entirely to the effect of the ePlanning program. However, planning cycles are impacted by many other factors such as the complexity of planning regulations and the availability of planning professionals. Planning cycles may also be impacted by other departmental initiatives which are designed to improve the time that it takes for a planning application to be evaluated. The Introduction describes some of these initiatives.

The largest contribution to the department’s September 2021 benefit report was an estimated saving of $151 million for developers due to lower costs associated with holding their investment for a shorter time. However, the department’s calculation of this benefit assumes a high baseline for the time to determine a development application. It also assumes that all development applications except for additions or alterations to existing properties will incur financing costs. However, a small but material number of these applications will be self-financed. The calculation also includes several data errors in spreadsheets.

The calculation of some benefits relies upon an extrapolation of the benefits experienced by a small number of early-adopter councils, including lower printing and scanning costs, fewer forms and quicker processing times. However, some councils report that their costs have increased following the introduction of the portal, primarily because aspects of the portal duplicate work that they carry out in their own systems. The portal has also required some councils to re-engineer aspects of their own systems, such as the integration of their planning systems with other council systems such as finance or property and rating systems. It has also required councils to create new ways of integrating council information systems with the planning portal.

The department has published information to help councils and certifiers to automatically integrate their systems with the planning portal. This approach uses application programming interfaces (or APIs) which are an industry-standard way for systems to share information. In April and May 2021, the government granted $4.8 million to 96 regional councils to assist with the cost of developing, implementing and maintaining APIs. The maximum amount of funding for each council was $50,000. The department is closely monitoring the implementation of APIs by councils and other portal users. Once they are fully implemented the department expects APIs to reduce costs incurred by stakeholders.

The department has not yet measured stakeholder costs. It was beyond the scope of this audit to validate these costs.

The department has not independently assured the calculation of reported benefits

In 2020 the department appointed an external provider to calculate the benefits achieved by the ePlanning program. The department advised that it chose to outsource the calculation of benefits because the provider had the required expertise and because it wanted an independent calculation of the benefits. The process involves:

  • extraction and verification of planning performance data by the department
  • population of data input sheets by the department
  • calculation of benefits by the external provider using the data input
  • confirmation by the department that the calculation includes all expected benefit sources.

The department does not have access to the benefits calculation model which is owned and operated by the external provider. The department trusts that the provider correctly calculates the benefits and does not verify the reported benefit numbers. However, as the benefits model involves many linked spreadsheets and approximately 300 individual data points, there is a risk that the calculation model contains errors beyond those discussed in this audit.

The reported benefits have only been calculated since 2019

The department originally intended to track benefits from October 2014. However, it only started to track benefits in 2019 when it appointed an external provider to calculate the benefits achieved by the portal. Any benefits or dis-benefits between the introduction of the portal and 2019 are unknown and not included in the department’s calculation of benefits.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #366 - released 21 June 2022

Published

Actions for Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Health
Internal controls and governance
Management and administration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining NSW Health’s management of health and safety risks to nurses and junior doctors in high demand hospital wards over the past five years, including during the first six months of the 2020 COVID-19 health emergency.

The Auditor-General found that while NSW Health effectively managed most incidents and risks to the physical health and safety of hospital staff during ‘business as usual’ activities, systems and resources are not fully effective to manage staff psychological and wellbeing risks, particularly for nurses.

The Auditor-General found that NSW Health was effective in managing most COVID-19 health and safety risks to hospital staff. Overall effectiveness could have been improved had pandemic preparedness training been delivered across all Local Health Districts. Additionally, state-wide communication systems could have been improved to provide hospital clinicians with access to a ‘single source of truth’ with the latest advice from NSW Health authorities.

NSW Health’s planning and preparation for the supply of Personal Protective Equipment (PPE) was partially effective. At various times, some PPE items could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting from usual items, and in some hospitals, substituted masks were used without being locally fit tested by hospital staff.

The Auditor-General made seven recommendations aimed at enhancing hospital health and safety risk reporting practices, along with a recommendation that NSW Health conduct a post pandemic 'lessons learned' review and make policy and operational recommendations for future pandemic responses.

Over the past decade, there have been increases in the numbers of health and safety incidents affecting nurses and junior doctors in NSW hospitals. These increases have been associated with higher numbers of patients with acute mental health conditions, age-related cognitive impairments, and patients presenting in emergency departments under the influence of drugs and alcohol.  

This audit commenced in August 2019, with a focus on the health, safety and wellbeing of nurses and junior doctors in high demand hospital wards. Our audit focused on emergency departments, mental health wards and aged care wards during 'business as usual’ periods of hospital operations. 

In the early months of 2020, the novel coronavirus (COVID-19) brought new health and safety risks to hospital staff. These risks included the potential for infection amongst health workers, increased staff workloads, and impacts on staff wellbeing.  

In May 2020, we expanded the focus of the audit to assess the effectiveness of NSW Health’s management of the health and safety risks to staff during the COVID-19 health emergency. We assessed the impacts on emergency departments and intensive care units, as these were the wards where staff were most likely to come into contact with COVID-19.  

The Audit Office acknowledges the ongoing health and safety challenges that the pandemic has brought to NSW Health staff – in particular to hospital clinicians and the managers who support them.  

This audit assessed the effectiveness of NSW Health’s:

  • systems, forums and workplace cultures to support reporting and generate data about risk
  • initiatives to support safe workplaces and effectively respond to health and safety incidents
  • actions to continuously improve staff health, safety and wellbeing in hospital environments.

The first three chapters of this report describe the effectiveness of NSW Health’s ‘business as usual’ health and safety risk management. The fourth and fifth chapters describe the effectiveness of NSW Health’s health and safety risk management during the COVID-19 pandemic.  

Conclusion
NSW Health’s management of health and safety risks in NSW hospitals

NSW Health is effectively monitoring and managing most incidents and risks to the physical health and safety of nurses and junior doctors in NSW hospitals. However, systems and resources are not fully effective across all Local Health Districts for monitoring or managing psychological and wellbeing risks - particularly in relation to nurses.

NSW Health’s incident management system is effective for recording health and safety incidents in hospital wards where incidents occur infrequently, and staff have time to log incident details during shift hours. However, in high demand wards where incidents and risks are common, staff report that they are unable to log all incidents due to the frequency of events, and the time it takes to record incidents in the system.

NSW Health is taking reasonable steps to manage and respond to physical health and safety incidents in NSW hospitals, but psychological and wellbeing risks and incidents are not routinely recorded or escalated to managers. Stress debriefing is not consistently available to staff after difficult or traumatic workplace incidents.

The Ministry of Health could improve its information sharing and data reporting on state-wide health and safety risks in NSW hospitals, and communicate risk trends to the wider NSW health system. This would assist managers to identify common health and safety issues, and target their responses. The Ministry has not set up systems or strategies to identify or support the expansion of successful health and safety initiatives across the NSW health system.

NSW Health’s management of health and safety risks associated with COVID-19

To date, NSW Health has effectively managed most COVID-19 related health and safety risks to hospital staff. The overall effectiveness of NSW Health's preparations and responses to COVID-19 could have been improved in the early phases of the health emergency - from January to early April 2020 - by ensuring that hospital staff in all Local Health Districts had access to pandemic training, that all emergency response policies had been updated and circulated, that state-wide communication systems were able to be rapidly upscaled to deliver consistent messages to hospital staff across the health system, and that PPE supply lines could provide sufficient stock to meet requirements during all pandemic response phases.

Local Health District executives and hospital managers effectively guided and supported nurses and junior doctors to manage and minimise most COVID-19 health and safety risks in hospital environments. However, communication with frontline staff could have been improved in the early stages of the pandemic. The Ministry did not set up a centralised communication channel to communicate consistent messages and advice to hospital clinicians until April 2020. This finding is consistent with a finding from the 2009 review into NSW Health’s response to the H1N1 influenza outbreak. Clinical staff advised that the lack of a centralised communication channel, substantially increased their workloads as they checked numerous sources for the latest and most authoritative advice.

Prior to COVID-19, pandemic response training was limited across the NSW Health system. Nurse managers of emergency departments and intensive care units reported that there was limited training or familiarisation with the NSW Pandemic Plan. Key policies describing infection control principles for emergency departments and intensive care units were outdated and had not been revised within required timelines.

NSW Health's planning and preparation for the supply and management of personal protective equipment (PPE) has been partially effective, with PPE available to hospital staff at all times. However, at various intervals, some PPE could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting, from the usual PPE stock. Staff reported that in the early stages of the pandemic, substituted masks were not locally fit tested by hospital staff in some emergency departments.

1. Audit recommendations

By December 2021, NSW Health should:

  1. Evaluate the effectiveness of the new incident management system to enable full reporting of health and safety incidents and risks in all hospital wards, including those where incidents and risks are common, and monitor for consistency of reporting over time
  2. Expand the categories of hospital incident data reported to Ministry executives in the Work Health and Safety Dashboard reports, including by linking injury data to incident types by hospital ward category, and monitor in conjunction with Local Health Districts for emerging trends and improvement over time
  3. Ensure that nurses and junior doctors have regular opportunities to report on risks to their psychological health and wellbeing, and that system managers have access to aggregate data to guide responses to mitigate these risks
  4. Develop and implement an evidence-based guiding framework and strategy to support hospital staff in the aftermath of traumatic or unexpected workplace incidents, and monitor implementation
  5. At regular intervals, publicly report aggregate Root Cause Analysis data detailing the hospital system factors that contribute to clinical incidents
  6. Develop and implement a systemwide platform for sharing research and information about hospital health and safety initiatives across the health system
  7. Conduct a post-pandemic 'lessons learned' review focusing on the effectiveness of key strategies deployed in the management of the COVID-19 pandemic and make policy and operational recommendations for future pandemic responses. In particular, ensure:
    • regular scenario-based pandemic training for hospital staff
    • updated policies and protocols for hospital infection controls
    • capability to upscale authoritative communication with frontline health workers at the earliest notification of a health emergency and for the duration of the emergency
    • systems and safeguards to ensure the supply and availability of clinically appropriate personal protective equipment (PPE) during all phases of a pandemic.

Local Health Districts were effective in leading health and safety infection control activity

According the NSW Health Influenza Pandemic Plan (Pandemic Plan), the Chief Executives of Local Health Districts have ultimate responsibility for public health unit preparations during health emergencies. If necessary, they can ‘draw on the support of the State Pandemic Management Team and local emergency management resources’.

During the preparations and early response phases to the COVID-19 pandemic, Local Health Districts were at the forefront of most NSW hospital activity. They took the lead role in developing hospital infection control protocols and guidance about the appropriate uses of Personal Protective Equipment (PPE). Each Local Health District established its own responses to the health emergency, based on the best clinical advice available to them. The localised approach meant that there were some minor differences in infection control practices across the NSW health system.

Throughout February and March 2020, there was limited centralised policy or guidance from the Ministry and its Pillar Health agencies about COVID-19 infection control practices. It was not possible to mandate practices at a time when information about the virus was evolving. Clinical responses were changing as more became known about COVID-19, especially about its patterns of transmission and its impacts on people with the disease.

During February and March 2020, Local Health District executives communicated with hospital staff via a range of methods. Some sent daily e-memos with the latest updates. Some scheduled more regular meetings with hospital clinicians. Some Districts set up extensive staff training sessions and information briefings to keep all personnel updated with the latest advice. Physical distancing made it difficult to bring staff together in large groups, so a range of communications measures were implemented.

Clinical staff also utilised their clinical training and expertise to prepare their wards and train frontline staff in infection control procedures. Some sourced information from national and international colleagues to add to localised knowledge of the virus.

When the first evidence of COVID-19 community transmission was identified in the Northern Sydney Local Health District, hospital staff followed infection control protocols that were based on local guidance and information. With the support from the District executive team and infectious diseases experts, hospital clinicians set up their own infection control protocols and PPE protections. Within a week the District had produced a matrix to guide staff in the uses of PPE during COVID-19 procedures, and had circulated the guidance to all hospital clinicians.

At the end of March 2020, a version of the Northern Sydney PPE matrix was published on the Clinical Excellence Commission’s website and it has now become NSW Health’s standard guideline for PPE during COVID-19 procedures. Once this guideline was published centrally, infection control practices were standardised across NSW hospitals.

This form of District-led policy making is not ‘business as usual’ practice for NSW Health. Policy making processes were somewhat reversed during the early response phases to COVID-19. This flexible policy approach supports the governance arrangements described in the Pandemic Plan, which assigns responsibility for ‘supporting and maintaining quality care across health services and implementing infection control measures as appropriate’ to Local Health Districts.

In non-health emergency situations, clinical policy and protocols are usually initiated and developed by the Ministry and the Clinical Excellence Commission and are subsequently shared across the health system after a quality control process. The localised approach adopted in the months from February to March 2020, allowed for rapid and flexible responses to changing information – to protect the health and safety of the hospital workforce and the wider community.

Hospital staff across NSW would have been better prepared for COVID-19 if pandemic training had been delivered across all Local Health Districts in the past decade

Local Health Districts are responsible for training hospital staff in preparation for public health emergencies. NSW’s policy describing Public Health Emergency Response Preparedness Minimum Standards requires that clinical staff participate in at least one annual emergency training exercise if they hold a position where they are likely to be called upon in an emergency. Staff must participate in an actual response exercise or a relevant training session. The training must also include re-familiarisation with PPE.

Available evidence about emergency response training in NSW indicates that at least two Local Health Districts have delivered pandemic focussed training in the past decade. Our interviews with managers of emergency departments and intensive care units indicates that most other Districts have focused their emergency training on mass patient trauma incidents such as plane crashes, train crashes and terrorist attacks. While the potential for these types of mass trauma events is real, and warrants training and preparation, significant global outbreaks of diseases have also had potential to threaten NSW communities. In previous decades, global health communities have been at risk of diseases such as the Severe Acute Respiratory Syndrome (SARS) and Middle East Respiratory Syndrome (MERS).

In the two Districts where pandemic training was provided in NSW, staff participated in community influenza vaccination exercises. These were focused on upskilling staff to follow emergency command structures, manage high volume patient flows, and organise sanitisation logistics during a hospital-based training exercise.

Our interviews with nurse managers in emergency departments and intensive care units indicate that in the majority of other Local Health Districts, key personnel were unaware of the NSW Pandemic Plan. Interviewed staff also reported insufficient scenario-based training in pandemic responses over the last ten years.

The Ministry, the Clinical Excellence Commission and the Health Education and Training Institute (HETI) are responsible for online training and 'state-wide strategies and resources to maintain high levels of compliance with infection control and patient safety recommendations'. The HETI website contains online training modules in infection control and PPE donning and doffing procedures. Other infection control information and research is available on the websites of the Clinical Excellence Commission and the Agency for Clinical Innovation.

Online training modules are effective for upskilling staff in a range of skills, but are not a substitute for real-time, rapid incident response training. Face-to-face training provides opportunities for first responders to test procedures in hospital environments. Incident response training provides opportunities for staff to assess their levels of compliance with protocols and their competence with equipment in scenario situations. It is the responsibility of Local Health Districts to provide this form of training to the health staff in their District.

Two NSW Health policies that govern clinical arrangements during pandemics are outdated

The Ministry had not updated two policies that had the potential to assist emergency departments and intensive care units in aspects of their ward preparation for the COVID-19 pandemic. Both policies were on the NSW Health website, but neither were shared with hospital staff in the planning phases for the pandemic. Both policies are out of date and have not been revised within required timeframes.

The 2010 Influenza Pandemic - Providing Critical Care policy was due for review in May 2015 and was not updated at the time of the COVID-19 health emergency. Similarly, the 2007 policy Hospital Response to Pandemic Influenza Part 1: Emergency Department Response was due for review in June 2012 and has not been updated.

These policies were designed to assist clinical staff to make necessary ward arrangements for infection control. They set out the steps for rapid identification of contingent workforces, isolation procedures, and management of patient flows to separate those with suspected infection from other patient cohorts. They were a potential addendum to the NSW Pandemic Plan which describes the command and control responsibilities of health agencies in health emergencies.

Our interviews with nurse managers from emergency departments and intensive care units indicate that in the absence of pandemic policy, they sought clinical guidance from external sources and Local Health District experts. Interviewees told us that a lack of policy guidance about ward arrangements and infection control practices in a pandemic increased their workloads and hours of overtime in the early response phases to COVID-19. With the support of Local Health Districts, clinical staff made rapid adjustments in order to respond to changing testing requirements and ward arrangements.

The Ministry was slow to establish a centralised communication channel to communicate with frontline staff

NSW Health’s governance and communication arrangements during a pandemic are set out in the Pandemic Plan. The Plan requires that government agencies ‘commence enhanced arrangements, establish communications measures’ and confirm ‘governance arrangements’ when there is evidence of person to person transmission during an influenza outbreak. NSW Health received the first notifications of the novel coronavirus risks in January 2020.

During the preparation and early response phases to COVID-19, the Ministry and its central agencies were slow in establishing a single, authoritative channel through which to communicate consistent messages to frontline staff. Clinical staff required up-to-date information about COVID-19 testing criteria as requirements were changing rapidly, sometimes daily. While there was no expectation for fixed policy at this time, hospital staff required the latest instructions about treatment requirements, and updates on the numbers of COVID-19 infections in their region.

As information about COVID-19 was evolving, information was communicated across the health system via ‘multiple channels and sources’. While the Ministry and its central agencies communicated extensively with Local Health Districts during March 2020, hospital staff reported to us that they weren’t always sure where they could find the latest advice about testing protocols or infection controls.

Frontline staff told audit office staff that they were checking multiple sources and time-stamping advice to ensure they had the most up to date information on a daily basis. While some Local Health Districts managed clear communication links with frontline staff, nurse managers told us that communication was ‘chaotic’ during the early phases of pandemic preparation. Key personnel were not always available outside business hours and nurse managers advise that they spent hours at the end of shifts, seeking and printing the latest advice for weekend and night shift personnel. By the end of March 2020, the Ministry and the Clinical Excellence Commission websites became better organised to communicate with frontline clinicians.

A recommendation to the Ministry of Health after H1N1 swine flu could be equally applied in the COVID-19 context. The NSW Government’s report: Key Recommendations on Pandemic (H1N1) 2009 Influenza recommended the establishment of ‘clear pathways of communication … so that all employees have confidence in where their information will come from and who they should approach if they need additional information.’

NSW Health acknowledges the challenges and the lessons from the early phases of the COVID-19 pandemic. For example, a strategy released in August 2020, sets out NSW Health’s own recommendation for the future management of PPE including: ‘Aligning a single source of truth for PPE education and evidence-based guidance to ensure clarity of information on appropriate use, supported by an influential network of Infection Prevention and Control (IPC) practitioners at the forefront.

Ministry executives advise that communication with health staff has improved since the early phases of the pandemic. The Ministry now sends weekly COVID-19 updates to over 130,000 health staff via email. In addition, NSW Health now has two COVID-19 tabs on its website with current information, including COVID-19 testing advice. According to Ministry executives, these communication channels could be used or replicated if needed for future health emergencies. The Ministry also provides health information and updates via a phone application called Med App. This App is preferred by doctors and is less likely to be used by nurses. As at October 2020, there are 13,000 users of Med App. Push notifications can be made on Med App through SMS alerts.

Personal protective equipment (PPE) was not always available in required sizes and some hospital masks and gowns were substituted with products that differed from the usual items

Since the emergence of COVID-19 in Australia, all clinicians in NSW hospitals have had access to some form of PPE for their clinical requirements. If staff did not have appropriate equipment for each COVID-19 related procedure, they were guided by the formal advice issued to the NSW Health workforce on 11 March 2020 stating that: ‘The safety of NSW Health staff is a priority at all times, especially during COVID-19. Where safe working practices confirm specific PPE (e.g. face shields/masks or other equipment) are required for the protection of staff due to COVID-19, in all circumstances:

  • staff are to wear prescribed PPE as instructed
  • staff are not to undertake or be required to undertake tasks requiring PPE if the PPE is not available for use. Any such tasks are not to proceed until required PPE is available
  • any staff member who is concerned about their safety must raise their concerns immediately to their manager.’

At periods during March and April 2020, some PPE items were not available in the required sizes or the regular brands to which staff were accustomed. HealthShare NSW was not able to source PPE from usual suppliers. HealthShare NSW sourced PPE including N95 masks from non-traditional suppliers. Some PPE items differed in shape and size from the usual hospital equipment. While senior executives from HealthShare NSW advise that all products were approved by the Therapeutic Goods Administration (TGA), in some hospitals, nurse managers advise that staff were not able to ‘fit test’ substituted masks. Fit testing determines the type and the size of the respirator mask that achieves an adequate seal on an individual’s face.

In March and April 2020, ‘duck bill’ (N95) masks were not available in some hospitals. According to stock managers and clinical managers in Local Health Districts, duck bills are the preferred mask for staff with smaller faces, particularly female staff members. The duck bill mask is a standard PPE product, and as such, is fit tested during mandatory PPE training. During the early response phases to COVID-19, most Local Health Districts were provided with substitute N95 masks. Fit testing of the substituted N95 masks was not able to be conducted in all NSW hospitals during the early phases of COVID-19. During the first wave of COVID-19 in March and April 2020, hospital staff told audit staff that there was no time and a lack of equipment to appropriately fit test substituted N95 masks.

Nurse managers in emergency departments advise that in some instances, staff made adaptations to PPE to improve protections, such as doubling masks, adding elastics or bringing their own equipment. These adaptations were not consistent with guidelines. Nurse managers advise that in some cases, adaptations to PPE or ill-fitting masks created pressure sores and contact dermatitis. Just over half of the stock managers of Local Health Districts advised that PPE stock was procured from outside the HealthShare NSW system. Stock managers in some Districts advise that facial shields and goggles sourced from non-traditional suppliers by HealthShare NSW were of a lesser quality than standard equipment. Stock managers and nurse managers reported that the changes in PPE products caused confusion and stress amongst staff.

Local Health Districts were proactive in assisting hospital staff to mitigate risks of COVID-19 infections. Some Local Health Districts assigned ‘tiger teams’ to assist staff with their PPE practices. Tiger teams provide clinical expertise and advice to staff, answer questions about infection control and provide training on PPE practice in hospital ward environments. They assist and support PPE donning and doffing practices to ensure the appropriate sequencing of applying and removing PPE for effective infection control. They provide mask fit checking guidance to assist staff in correct PPE practices.

Districts ran extensive refresher PPE training sessions for clinical staff. Some hospitals ran regular PPE demonstrations so that staff could observe correct PPE procedures at set times during the day. These activities assisted staff to implement appropriate infection control in the period before the Clinical Excellence Commission’s web-based materials and videos became available in late March and early April 2020. These online resources now provide comprehensive guidance to hospital staff in PPE practices.

HealthShare NSW placed limits or caps on some high-demand PPE items that were too low to meet requirements in some Local Health Districts and had to be adjusted to meet actual demand

The NSW Pandemic Plan describes the responsibilities of the Ministry and its central agencies to manage and maintain the State Medical Stockpile of essential PPE supplies and antiviral medications. During a pandemic, HealthShare NSW has responsibility for warehousing, monitoring and distributing health supplies to the health workforce.

Due to a reported global shortage of PPE and limits to the NSW stockpile, HealthShare NSW placed limits on the provision of approximately 100 high-demand items to NSW hospitals. HealthShare NSW advise that the PPE order capping ceilings were implemented ‘to ensure local stockpiling does not occur’. A centralised ordering process was established with Local Health Districts so that PPE product ordering occurred through single hospital locations (214 across the State), rather than at the ward level. Escalation processes were established to allow Districts to request one-off increases to supply, and a process was set up to permanently increase the order cap limit for any PPE item by facility.

According to HealthShare NSW, ‘as incoming central supply has improved, order caps have subsequently increased in line with strong engagement and governance with the Local Health Districts to ensure the appropriate levels of supply are provided’. The original capped levels were determined by assessing PPE usage in wards during the flu season of 2019. As the flu season case numbers of 2019 were relatively low, some Local Health District managers advised that the levels of PPE during 2019 were not comparable to the level of PPE required for the COVID-19 pandemic.

After advocacy from hospital stock managers and clinicians, HealthShare NSW increased capped PPE levels in many Local Health Districts.

Executive members of the State Health Emergency Operations Centre (SHEOC) advise that its PPE supply strategy needs to be carefully developed as there are vast differences in PPE usage rates during 'business as usual' periods and pandemic periods. If NSW Health kept the level of PPE required in planning for a worst-case scenario, this would equate to an extensive surplus of PPE that could not be utilised during business as usual periods. The SHEOC Executive advise that it is not feasible or economical to store this level of PPE. They advise that given the costs of PPE, and the fact that the products have a shelf life, a diversified supply line is a more reliable method for ensuring PPE during surge and non-surge periods.

Early data modelling showed ICU patient numbers at levels not manageable with levels of ventilators and equipment

Early projections of patient numbers requiring acute care for COVID-19, were at levels that would not have been manageable with the equipment and resources of NSW hospitals. Throughout March through to May 2020, government data modelling indicated significant surges of community infections and surges in intensive care patients.

Early estimates were based on overseas trends, and if actual cases had matched projections, NSW hospitals would not have had sufficient ventilators to meet demand. The knowledge of this shortfall caused high levels of anxiety among nursing and medical staff.

While the data was based on the best available information, it had negative implications for the health and safety of the nurse and junior doctor workforce. Managers of intensive care wards and emergency departments reported stress amongst the workforce. Staff concerns were primarily about being faced with ‘the unmanageable’, along with heightened fears about contracting the virus with the knowledge that there was insufficient equipment to treat acute patients.

As it transpired, overall numbers of COVID-19 infections were lower than projected during the early months of the pandemic. The lower infection rates in the general population have meant fewer instances of patients requiring intensive care in NSW hospitals. In addition, HealthShare NSW has been able to increase the numbers of ventilators in NSW hospitals to prepare for future surges in patients requiring acute respiratory care.

SHEOC Executive advise that NSW Health undertook an accelerated procurement strategy in early 2020 to increase its stock of ventilators, and that ventilator capacity has always far-exceeded actual requirements.

NSW Health has developed a strategy to improve the management of PPE for the NSW health workforce

In August 2020, NSW Health released a strategy that sets out its future management and planning approaches to the provision of PPE for the NSW Health workforce. NSW Health’s Personal Protective Equipment (PPE) Strategy describes the learnings and challenges during the COVID-19 pandemic in sourcing and distributing PPE. It sets out the systems and methods for distributing PPE to staff and patients and focuses on how staff are kept informed on the appropriate use of PPE at all times. A supporting communications strategy has been developed to support its implementation.

The strategy contains enhanced transparency measures to regularly inform staff about PPE stock levels and to provide data about PPE usage rates by item types in wards in NSW hospitals. The NSW Health PPE strategy describes a changed approach to ordering, storing and allocating PPE. This includes diversifying the supply lines for PPE products to increase supply options in circumstances where supply lines become disrupted. It includes a centralised system for coordinating the supply of hospital PPE through Local Heath District coordination points and centralised distribution points in large hospitals.

Our interviews with hospital PPE stock managers and nurse managers indicate that staff find the new ordering system to be an improvement upon the previous stock ordering method.

According to the Personal Protective Equipment (PPE) Strategy, NSW health is upgrading its models for monitoring and benchmarking PPE usage across the health system. Systems are being improved for forecasting demand volumes during business as usual periods and during health emergency surges.

Appendix one – Response from agency

Appendix two – Audit methodology

Appendix three – About the audit 

Appendix four – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #344 - released 9 December 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for Ensuring contract management capability in government - HealthShare NSW

Ensuring contract management capability in government - HealthShare NSW

Health
Management and administration
Procurement
Project management

This report examined whether HealthShare NSW, a part of NSW Health, has the required contract management capability to effectively manage goods and services contracts valued over $250,000. 

The report found that HealthShare has a procurement framework that should support effective contract management, but it is not applying it consistently. In particular, the audit found that HealthShare was not applying key contract management elements to over 80 per cent of the high-value contracts it manages. The audit also found that HealthShare’s contract management practices were limited by inadequate performance monitoring.

'Effective contract management is essential to ensure the contracts HealthShare enters into are delivering as expected and ensuring value for money,' said the Auditor-General. 'Without this, the value for money or savings HealthShare achieves when it negotiates these contracts is at risk of being eroded over the life of the contract.'

The report recommends that NSW Health develop a performance improvement plan to ensure HealthShare is fully compliant with procurement policies and that NSW Health meets its obligations under the Government's Accreditation Program for Goods and Services Procurement.

HealthShare is a NSW Health entity responsible for providing shared services, including procurement, to support the delivery of patient care within the NSW health system. In 2018, HealthShare procured high value goods and services contracts with an annual estimated total spend of around $1.8 billion, with most of the contracts of long duration.

NSW Government agencies are increasingly delivering services and projects through contracts with third parties. These contracts can be complex and governments face challenges in negotiating and implementing them effectively. A robust contract management framework helps ensure all parties meet their obligations, contractual relationships are well managed, agencies achieve value for money, and deliverables meet the required standards and agreed timeframes.

Contract management capability is a broad term, which can include aspects of individual staff capability (such as staff knowledge, skills and experience) as well as organisational capability (such as policies, frameworks and processes).

The NSW Procurement Board is responsible for overseeing the Government's procurement system, setting policy and ensuring compliance. It has accredited the Health Administration Corporation (HAC) to procure goods and services with no upper financial limit. Under the terms of this accreditation, the Secretary, NSW Health (as head of HAC) has delegated the procurement of high-value (over $250,000) goods and services contracts within NSW Health to only the Ministry of Health and HealthShare NSW (HealthShare).

HealthShare NSW (HealthShare) is a NSW Health entity responsible for providing shared services, including procurement, to support the delivery of patient care within the NSW health system. In 2018, HealthShare procured high-value goods and services contracts with an annual estimated total spend of around $1.8 billion, with most of the contracts of long duration.

HealthShare’s Contract Management Guide states that, without rigorous contract management, 75 per cent of projected sourcing savings can disappear within 18 months of the contract starting.

This audit examined whether HealthShare has the required capability to effectively manage high-value goods and services contracts. Contracts we examined included critical items such as food services in hospitals, patient transport services, intravenous equipment and kidney dialysis services, where risks include patient safety as well as value for money. We did not examine infrastructure, construction or information communication and technology contracts. We also did not examine HealthShare’s sourcing processes, including identifying business needs, tendering and contract award.

We assessed HealthShare against the following criteria:

  1. HealthShare's systems, policies and procedures support effective contract management and are consistent with relevant frameworks, policies and guidelines.
  2. HealthShare has capable personnel to effectively conduct the monitoring activities throughout the life of the contract.

We included the NSW Public Service Commission and NSW Treasury, through NSW Procurement, as auditees because they administer policies which directly affect contract management capability. These include:

  • NSW Procurement Board Directions and policies
  • NSW Government Procurement Policy Framework
  • Accreditation Program for Goods and Services Procurement
  • the NSW Public Sector Capability Framework.

NSW Procurement was transferred to NSW Treasury from the former Department of Finance, Services and Innovation on 1 July 2019 as part of changes to government administrative arrangements.

Conclusion
HealthShare is not applying the capability needed to effectively manage high-value (over $250,000) goods and services contracts. HealthShare's procurement framework includes elements that should support effective contract management, and it has a systematic approach to managing staff contract management capability. That said, HealthShare is not implementing key contract management elements of its own framework. As such, the value for money or savings it achieves when it negotiates contracts is at risk of being eroded over the life of these contracts.
Effective contract management is essential for HealthShare to ensure contracts it enters into are delivering the goods and services expected and achieving value for money, safety and quality. The Ministry of Health and HealthShare have invested in developing and implementing systems and tools to support effective contract management. In line with its obligations under the Agency Accreditation Program for Goods and Services Procurement (accreditation program), the Ministry of Health mandates the use of contract management plans for high-value contracts. The Ministry of Health also requires that all health entities use the PROcure contract management system for ongoing management of contracts with a value over $150,000. HealthShare is not complying with these directions for over 80 per cent of the contracts it manages.
In the absence of HealthShare following its framework, and the Ministry of Health’s directions, we looked for other evidence that HealthShare was effectively managing high-value contracts. We found that HealthShare’s contract management practices were limited by inadequate performance monitoring.
When Local Health Districts (LHDs) need to procure high-value goods and services, the Ministry of Health’s procurement policy requires that they use HealthShare to source and manage the procurement. This is to manage risk and provide oversight of procurement and contracts across the NSW health system. Despite this policy, HealthShare was only managing the sourcing stage of the procurement and transferring responsibility for contract management to the relevant LHD.

Appendix one – Response from agencies

Appendix two – Contract performance management summary

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #328 - released 31 October 2019