Refine search Expand filter

Reports

Published

Actions for Volume Eleven 2012 focusing on Health

Volume Eleven 2012 focusing on Health

Health
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

One in three ambulance crews were delayed for longer than 30 minutes at hospital. Over the year these delays totalled 84,680 hours of lost time, up from 78,224 last year and 58,399 the year before. The longer ambulance crews are at hospitals the less time they are available to respond to the next emergency.

Published

Actions for Volume One 2012 focusing on themes from 2011

Volume One 2012 focusing on themes from 2011

Health
Industry
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Shared services and collaboration

The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.

Published

Actions for Managing IT Services Contracts

Managing IT Services Contracts

Finance
Health
Justice
Compliance
Information technology
Internal controls and governance
Procurement
Project management
Risk

Neither agency (NSW Ministry of Health and NSW Police Force) demonstrated that they continued to get value for money over the life of these long term contracts or that they had effectively managed all critical elements of the three contracts we reviewed post award. This is because both agencies treated contract extensions or renewals as simply continuing previous contractual arrangements, rather than as establishing a new contract and financial commitment. Consequently, there was not a robust analysis of the continuing need for the mix and quantity of services being provided or an assessment of value for money in terms of the prices being paid.

 

Parliamentary reference - Report number #220 - released 1 February 2012

Published

Actions for Regulating the Clearing of Native Vegetation

Regulating the Clearing of Native Vegetation

Environment
Internal controls and governance
Regulation

Native vegetation is a complex and difficult area to regulate. There is an inherent tension between economic development and conservation. In our opinion, the complexities and the lack of accountability have contributed to the present position, whereby a whole-of-government approach to the protection of native vegetation in NSW has not been developed. There are currently no objectives or targets to measure progress in conserving native vegetation. Only one, of a possible twenty-two regional management plans, has been approved since the Act commenced. There is also a lack of comprehensive information about the status of, and changes to, native vegetation across rural NSW.

 

Parliamentary reference - Report number #101 - released 20 August 2002

Published

Actions for Ambulance Service of NSW: Readiness to respond

Ambulance Service of NSW: Readiness to respond

Health
Internal controls and governance
Management and administration
Shared services and collaboration
Workforce and capability

This performance audit indicates that the Service has considerable work to do to reach its aspirations of being recognised amongst leading examples of best practice services. The commitment of the Service to serving the community and the professionalism of the Service's officers is not in question. It is, however, apparent that a number of barriers to performance will need to be overcome for the Service to perform as well as it would wish.

 

Parliamentary reference - Report number #80 - released 7 March 2001