Actions for Volume Ten 2013 focusing on Health

Volume Ten 2013 focusing on Health

Health
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk
Shared services and collaboration

Unqualified opinions were issued for all agencies audited in the following report.

Some of the reports findings include:

  • Most cultural bodies rely heavily on government grants to fund services

  • The Sydney Opera House Trust earns most of its revenue from commercial operations

  • Less than half of the 2014-16 service agreements between HealthShare NSW and its customers have been signed. HealthShare NSW and health entities should finalise their 2014-2016 service agreements by no later than 31 January 2014

  • Five service level agreements with NSW Health Pathology for 2012-13 were never signed. NSW Health Pathology and local health districts/speciality networks should finalise their 2013-14 service agreements by no later than 31 December 2013

  • HealthShare NSW is committed to sharing internal audit findings across NSW Health

  • The Ministry has started a long-term project to review its policy directives

  • A recent review concluded the health sector has mature risk management practices

  • When changes to the Aboriginal Land Rights Act 1983 occur, the Minister should identify and assess any risks from the changes and develop strategies to mitigate against them.

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Cost of Alcohol Abuse to the NSW Government

Cost of Alcohol Abuse to the NSW Government

Treasury
Justice
Health
Premier and Cabinet
Management and administration
Regulation

The NSW Government does not estimate or report the total cost of alcohol abuse. The Audit Office of New South Wales’ sponsored research estimates it costs the government over $1 billion a year, or around $416 from each NSW household.

 

Parliamentary reference - Report number #235 - released 6 August 2013

Published

Actions for Reducing Ambulance Turnaround Time at Hospitals

Reducing Ambulance Turnaround Time at Hospitals

Health
Compliance
Management and administration
Service delivery

NSW Health has put in place initiatives to reduce the time ambulance crews have to wait at a hospital before they are able to leave and attend to other calls. Despite these actions, ambulance crews are waiting longer at NSW hospitals. Crews now wait on average nearly 32 minutes at a hospital before handing over a patient, up from about 24 minutes seven years ago.

 

Parliamentary reference - Report number #233 - released 24 July 2013

Published

Actions for Managing Operating Theatre Efficiency for Elective Surgery

Managing Operating Theatre Efficiency for Elective Surgery

Health
Compliance
Management and administration
Service delivery

Waiting times for elective surgery will continue to increase if NSW Health does not improve its management of operating theatres. On the positive side NSW public hospitals are performing more elective surgery than in previous years and are treating patients substantially within national clinical timeframes. However, more operations will be needed as targets are getting tighter and demand is growing.

 

Parliamentary reference - Report number #232 - released 17 July 2013

Published

Actions for Building Energy Use in NSW Public Hospitals

Building Energy Use in NSW Public Hospitals

Health
Treasury
Planning
Environment
Internal controls and governance
Management and administration

NSW Health has reduced its energy use and greenhouse gas emissions by two per cent over the last four years. It is pleasing that annual emissions are now 15,000 tonnes less than they were four years ago. However, this was not sufficient to meet its target of an 11 per cent drop in emissions. 

Despite a reduction in energy use, energy cost in NSW Health has increased by nearly 50 per cent over the last four years to $120 million per annum. This is expected to increase by another 50 per cent in the next five years.

 

Parliamentary reference - Report number #231 - released 4 June 2013

Published

Actions for Volume Ten 2011 Focusing on Health

Volume Ten 2011 Focusing on Health

Health
Financial reporting
Information technology
Internal controls and governance
Management and administration
Project management
Workforce and capability

This report includes comments on financial audits of government agencies in the Health sector. In 2010-11, Ambulance Officers spent an extra 77,200 hours waiting at emergency departments for patients to transfer to hospital care. In 2010-11, only 66 per cent of patients were moved from the emergency department to an inpatient bed within eight hours of their arrival. This is significantly down on last year’s 73 per cent and well below the 80 per cent target.

Published

Actions for Visiting medical officers and staff specialists

Visiting medical officers and staff specialists

Health
Management and administration
Service delivery
Workforce and capability

We found that hospitals are generally able to deploy their VMOs and staff specialists to be at the place and time required. However, a hospital’s ability to manage supply and demand at a local level is limited. This limitation will become more critical with the current national health reforms when public hospital funding will depend on their ability to set and meet activity targets and priorities. NSW Health cannot be sure that all payments made to VMOs are for agreed and delivered services. Across the hospitals visited we found limited checking of VMO claims for payment, limited quality information on staff specialist activities and limited hospital-level analysis of trends or inconsistencies in activities and treatments.

 

Parliamentary reference - Report number #219 - released 14 December 2011

Published

Actions for Responding to Domestic and Family Violence

Responding to Domestic and Family Violence

Community Services
Justice
Health
Internal controls and governance
Management and administration
Service delivery

Organisations generally work together to improve the safety of victims when there is an overt and serious crisis, particularly where children are involved. There are no standard ways for victims and perpetrators to access help that might prevent ongoing violence and address underlying issues. This is particularly problematic where there are repeat victims and perpetrators, many of whom have complex mental health, drug and alcohol problems and are difficult to work with. New South Wales has trialled a number of projects to improve the way that organisations work together to support vulnerable people in particular communities.

 

Parliamentary reference - Report number #218 - released 8 November 2011

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.