Refine search Expand filter

Reports

Published

Actions for Service NSW's handling of personal information

Service NSW's handling of personal information

Premier and Cabinet
Finance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the effectiveness of Service NSW’s handling of customers’ personal information to ensure its privacy.

The audit found that Service NSW is not effectively handling personal customer and business information to ensure its privacy. Service NSW continues to use business processes that pose a risk to the privacy of personal information. This includes the routine emailing of personal information between Service NSW service centres and other agencies, which is one of the processes that contributed to the data breach earlier this year. The audit found that previously identified risks and recommended solutions had not been implemented on a timely basis.

The Auditor-General made eight recommendations aimed at ensuring improved processes, technologies, and governance arrangements for how Service NSW handles customers’ personal information.

The Hon. Victor Dominello, MP, Minister for Customer Service, requested this audit under section 27(B)(3)(c) of the Public Finance and Audit Act 1983 following public reports in May 2020 of a cyber security attack which had led to a breach of Service NSW customer information. This audit also included the Department of Customer Service which supports Service NSW with privacy, risk and governance functions.

Service NSW was established in 2013 with the intention that it would, over time, 'become the primary interaction point for customers accessing New South Wales Government transaction services'.

Service NSW's functions are set out in the Service NSW (One stop Access to Government Services) Act 2013. This legislation allows for other NSW Government agencies to delegate to and enter into agreements with the Chief Executive Officer of Service NSW in order for Service NSW to undertake service functions for the agency.

Service NSW now has agreements with 36 NSW Government client agencies to facilitate over 1,200 types of interactions and transactions for the community.

The nature of each agreement between Service NSW and its client agencies varies. Some client agencies have delegated authority to allow Service NSW staff to conduct transactions on their behalf in the agencies' systems. Other arrangements do not include the same degree of delegation. In these cases, Service NSW provides services such as responding to enquiries and validating documents.

In addition, Service NSW conducts transactions for its own programs, such as the Seniors Card. Personal information for these programs, as well as information for customers' MyServiceNSW accounts, are stored by Service NSW on its Salesforce Customer Relationship Management (CRM) system.

In March 2020, Service NSW suffered two cyber security attacks in short succession. Technical analysis undertaken by the Department of Customer Service (DCS) concluded that these attacks resulted from a phishing exercise through which external threat actors gained access to the email accounts of 47 staff members. These attacks resulted in the breach of a large amount of personal customer information that was contained in these email accounts. See Section 1.1 for further details.

This audit is being conducted in response to a request from the Hon. Victor Dominello, Minister for Customer Service, under section 27B(3)(c) of the Public Finance and Audit Act 1983. Minister Dominello requested that the Auditor General conduct a performance audit in relation to Service NSW's handling of sensitive customer and business information.

This audit assessed how effectively Service NSW handles personal customer and business information to ensure its privacy.

It addressed the following:

  • Does Service NSW have processes and governance in place to identify and manage risks to the privacy of personal customer and business information?
  • Does Service NSW have policies, processes and systems in place that support the effective handling of personal customer and business information to ensure its privacy?
  • Has Service NSW effectively implemented its policies, processes and systems for managing personal customer and business information?

Conclusion

Service NSW is not effectively handling personal customer and business information to ensure its privacy. It continues to use business processes that pose a risk to the privacy of personal information. These include routinely emailing personal customer information to client agencies, which is one of the processes that contributed to the March 2020 data breach. Previously identified risks and recommended solutions had not been implemented on a timely basis.

Service NSW identifies privacy as a strategic risk in both its Risk Management Guideline and enterprise risk register and sets out a zero level appetite for privacy risk in its risk appetite statement. That said, the governance, policies, and processes established by Service NSW to mitigate privacy risk are not effective in ensuring the privacy of personal customer and business information. While Service NSW had risk identification and management processes in place at the time of the March 2020 data breach, these did not prevent the breach occurring.

Some of the practices that contributed to the data breach are still being followed by Service NSW staff. For example, business processes still require Service NSW staff to scan and email personal information to some client agencies.

The lack of multi factor authentication has been identified as another key contributing factor to the March 2020 data breach as this enabled the external threat actors to gain access to staff email accounts once they had obtained the user account details through a phishing exercise. Service NSW had identified the lack of multi factor authentication on its webmail platform as a risk more than a year prior to the breach and had committed to addressing this by June 2019. It was not implemented until after the breach occurred.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce Customer Relationship Management (CRM) system, which holds the personal information of over four million NSW residents.

Internal audits carried out by Service NSW, including one completed in August 2020, have identified significant weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These include deficiencies in the management of role based access, monitoring and audit of user access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers held in the system.

Lines of responsibility for meeting privacy obligations are not clearly drawn between Service NSW and its client agencies.

Service NSW has agreements in place with client agencies. However, the agreements lack detail and clarity about the roles and responsibilities of the agencies in relation to the collection, storage and security of customer's personal information. This lack of clarity raises the risk that privacy obligations will become confused and missed between the agencies.

Service NSW carries out privacy impact assessments for major new projects but does not routinely review existing processes and systems.

Service NSW carries out privacy impact assessments as part of its routine processes for implementing major new projects, ensuring that privacy management is considered as part of project design. Service NSW does not regularly undertake privacy impact assessments or reviews of existing or legacy processes and systems, which has resulted in some processes continuing despite posing significant risks to the privacy of personal information, such as the scanning, emailing, and storing of identification documents.

1. Key findings

Service NSW identifies privacy risks, but the controls and processes it put in place to mitigate these privacy risks were not adequate to prevent or limit the extent of the data breach that occurred in March 2020

Service NSW’s approach to risk management is framed by its Risk Management Guideline, which defines 'privacy and compliance' as one of the key types of risk for the agency. Service NSW's enterprise risk register identifies four strategic privacy related risks. Service NSW has set out a zero level appetite for privacy risk in its risk appetite statement.

Service NSW has assessed the adequacy of its controls for privacy risks as needing improvement. To be fully effective, the Risk Management Guideline says that these controls should have a focus that is ‘largely preventative and address the root causes’.

One of the business processes that was a key contributing factor to the data breach was the emailing of personal information by Service NSW staff to client agencies.

This process had been identified as a risk prior to the breach and some steps had been put in place to mitigate the risk. In particular, staff were required to manually delete emails that contained personal information. However, these measures were ineffective in preventing the breach, as the external threat actors still gained access to 47 staff email accounts that contained a large amount of personal information.

It is unclear why Service NSW did not effectively mitigate this risk prior to the breaches. However, Service NSW has advised that it implemented measures in June and October 2020 to automatically archive emails likely to contain personal information. This is expected to limit the quantity of information retained in email accounts for extended periods.

Service NSW has not put in place any technical or other solutions to avoid Service NSW staff having to scan and email personal information to some client agencies. Urgent action is needed to remove the requirement for staff to email personal information to client agencies, thereby mitigating the risk inherent in sending and storing this information using email.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system, which holds the personal information of over four million customers

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These weaknesses include deficiencies in governance of role based access, monitoring and audit of staff access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers which is stored in this system.

In addition, there is an absence of important controls to safeguard customers' privacy, such as multi factor authentication and reviewable logs of access history to their information. Such controls, when properly implemented, would enhance the control that customers are able to exercise over their personal information.

A privacy impact assessment conducted on Service NSW’s Salesforce CRM system in 2015 recommended that the system include the ability for customers to review access history to their personal information, as well as the option for customers to apply multi factor authentication to their accounts. While both these recommendations appeared positively received by Service NSW, neither have been implemented.

Since its inception, Service NSW’s use of Salesforce has extended to storing transaction data, particularly for transactions for which Service NSW is responsible, such as the Seniors Card. It also holds details of over four million MyServiceNSW account holders, including name, email address and phone number, and optional address details. It was not originally intended for the system to hold this volume and nature of customer information.

Lines of responsibility for meeting privacy obligations are unclear between Service NSW and its client agencies

Service NSW's privacy management plan does not clearly set out the privacy obligations of Service NSW and its client agencies. It sets out that 'compliance with the privacy principles will primarily be the responsibility of that [client] agency'. However, Service NSW has its own obligations under the security principles of the Privacy and Personal Information Protection Act 1998 (PPIP Act) to take reasonable steps to prevent unauthorised access to personal information, which is not made clear in the privacy management plan.

The agreements between Service NSW and client agencies reviewed for this audit only include general and high level references to privacy. Most do not include details of each parties' privacy responsibilities such as: which agency will provide the customer with a privacy notice explaining how their personal information will be handled, how personal information will be kept secure, how long Service NSW will retain information, what processes will be followed for internal reviews, and what specific planning is in place to respond to data breaches.

Service NSW's privacy management plan has not been updated to include new programs and governance changes

Service NSW's privacy management plan includes most of the matters required by law or good practice, with some exceptions. It does not explain any exemptions that the agency commonly relies on under the PPIP Act and does not address any health information that Service NSW may handle. It had also not been updated to reflect governance changes and the fact that, at the time this audit commenced, Service NSW was disclosing the content of internal review applications (the formal expression for 'complaints') to the Department of Customer Service (DCS). These governance changes were part of the centralisation of Service NSW's corporate support functions into DCS in late 2019, though internal review staff were seconded back into Service NSW during the course of this audit.

The current July 2019 privacy management plan has also not been updated since the rollout of a number of major new initiatives in 2020. These include 2019–20 bushfire emergency recovery initiatives (such as small business grants) and COVID 19 pandemic response initiatives (such as small business grants, border permits and the COVID safe check in app).

Service NSW routinely conducts privacy impact assessments for new initiatives, though privacy risks remain in legacy systems and processes

Service NSW routinely conducts privacy impact assessments for major new initiatives and the assessments reviewed for this audit largely accorded with good practice guidance.

Service NSW does not routinely review existing processes and systems to ensure that they are effective in ensuring the privacy of customer personal information. Business processes that create the highest risk to privacy, such as emailing of personal information, are more common in these longstanding legacy systems.

Service NSW's significant and rapid growth has outpaced the establishment of a robust control environment which has exacerbated privacy risks

Since it was established in 2013, Service NSW has experienced significant growth in the number and diversity of the types of transactions it provides, as well as the number of client agencies with which it works. The pace and extent of this growth has contributed to important controls not being properly implemented on a timely basis, which has heightened privacy risks, particularly in regard to existing, legacy systems and processes.

The pace of change and increasing demand for new program implementation has limited the opportunity for Service NSW, in collaboration with its client agencies, to revisit and redesign legacy business practices which pose a greater privacy risk. This includes the scanning and emailing of personal information.

While 2019–20 has seen additional demands placed on Service NSW in responding to the 2019–20 bushfire emergency and COVID 19 pandemic, it is the nature of the agency’s work that it operates in a fast paced and complex environment, where it is required to respond to multiple client agencies and stakeholders. Ensuring customer privacy should be integral to Service NSW’s business as usual operations.

2. Recommendations

Service NSW commissioned a number of external reviews and investigations stemming from the data breaches. The Auditor General's recommendations below have taken these other reviews into account. In order to offer assurance that it is appropriately protecting the privacy of its customers, Service NSW should address the full breadth of findings and recommendations made across all relevant reviews.

As a matter of urgency, Service NSW should:

1. in consultation with relevant client agencies and the Department of Customer Service, implement a solution for a secure method of transferring personal information between Service NSW and client agencies

2. review the need to store scanned copies of personal information and, if still required, implement a more secure method of storing this information and regular deletion of material.

By March 2021, Service NSW should:

3. ensure that all new agreements entered into with client agencies from 1 April 2021 address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

4. in collaboration with the Department of Customer Service, review its privacy management plan to address the deficiencies raised in this audit, including:

  • to clarify Service NSW's understanding of how responsibility for meeting privacy obligations are delineated between Service NSW and client agencies
  • to better reflect the full scope and complexity of personal information handled by Service NSW
  • to better explain how applications for internal review are handled between Service NSW and the Department of Customer Service
  • to ensure regular ongoing review, either according to a schedule or when Service NSW experiences substantial change to its programs and handling of personal information

5. in consultation with the Department of Customer Service, review its policies and processes for the management of privacy risks, including to:

  • ensure that there are appropriate mechanisms to escalate identified privacy risks from business units to the Executive Leadership Team
  • ensure that there are action plans to address strategic privacy risks that are assessed as having ineffective controls.
By June 2021, Service NSW should:

6. address deficiencies in the controls over, and security for, its Salesforce customer relationship management and related systems that hold customer personal information, including:

  • establish policies and processes for regular access reviews and monitoring of user activity in these systems, including for privileged users
  • enable partitioning and role based access restrictions to personal information collected for different programs
  • provide customers the choice to use multi factor authentication to further secure their MyServiceNSW accounts
  • enable customers to view the transaction history of their personal information to detect possible mishandling.
By December 2021, Service NSW should:

7. ensure that all existing agreements with client agencies address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

8. carry out a risk assessment of all processes, systems and transactions that involve the handling of personal information and undertake a privacy impact assessment for those that:

  • are identified as high risk and have not previously had a privacy impact assessment
  • have had major changes or updates since the privacy impact assessment was completed.

Appendix one – Responses from agencies

Appendix two – About the audit

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Central Agencies 2020

Central Agencies 2020

Premier and Cabinet
Treasury
Financial reporting
Internal controls and governance
Management and administration
Risk

This report analyses the results of our audits of the financial statements of the Treasury, Premier and Cabinet, Customer Service cluster agencies (central agencies), and the Legislature for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions and timeliness of reporting

Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature.

The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified.

All agencies met statutory deadlines for submitting
financial statements. 

Agencies were financially impacted by recent emergency events The NSW Government allocated $1.4 billion to provide small business support and bushfire recovery relief, support COVID-19 quarantine compliance management, recruit more staff to respond to increased customer demand, and meet additional COVID-19 cleaning requirements. Agencies spent $901 million (64 per cent of the allocated funding) for the financial year ended 30 June 2020. NSW Self Insurance Corporation reported an increase of $850 million in its liability for claims related to emergency events.
AASB 16 'Leases' resulted in significant changes to agencies' financial position The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
Implementation of new revenue standards NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue, which have been corrected in the final financial statements.

2. Audit observations

Management letter findings and repeat issues Our 2019–20 audits identified nine high risk and 122 moderate risk issues across central agencies and the Legislature. The high risk issues were identified in the audits of:
  • Insurance and Care NSW
  • New South Wales Government Telecommunications Authority
  • Rental Bond Board
  • Independent Commission Against Corruption
  • NSW Treasury
  • Crown Entity
  • Department of Premier and Cabinet.

High risk findings include:

  • Insurance and Care NSW (icare) allocates service costs to the Workers Compensation Nominal Insurer, and the other schemes it supports. The documentation supporting cost allocations does not demonstrate how these allocations reflect actual costs. There is a risk of the Workers Compensation Nominal Insurer being overcharged.
  • New South Wales Government Telecommunications Authority's delay in capitalisation and valuation of material capital projects; and insufficient work performed to implement the new accounting standard AASB 16 ‘Leases’.
  • NSW Treasury's four-year plan to transition RailCorp to a for-profit State Owned Corporation called Transport Asset Holding Entity of New South Wales (TAHE) by 1 July 2019, remains to be implemented. On 1 July 2020, RailCorp converted to TAHE. A large portion of the planned arrangements are still to be implemented. As at the time of the audit, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements were not finalised. In the absence of commercial arrangements with the public rail operators, there is a lack of evidence to demonstrate TAHE’s ability to create a commercial return in the long term. This matter has been included as a high risk finding in our management letter as there may be financial reporting implications to the State if TAHE does not generate a commercial return for its shareholders in line with the original intent. NSW Treasury and TAHE should ensure the commercial arrangements, operating model and SCI are finalised in 2020–21.

Of the 122 moderate risk issues, 36 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration, which increases the risk of inappropriate access to systems and records.

Grants administration for disaster relief Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by emergency events for the financial year ended 30 June 2020. A performance audit of grants administration for disaster relief is planned for 2020–21. It will assess whether grants programs administered under the Small Business Support Fund were effectively designed and implemented to provide disaster relief.
Internal controls at GovConnect NSW service providers require enhancement

GovConnect NSW provides transactional and information technology services to central agencies. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at service providers, namely Infosys, Unisys and the Department of Customer Service (DCS). The service auditor issued:

  • unqualified opinions on information technology and business process controls at Infosys and Unisys, but there was an increase in control deficiencies identified in the user access controls at these service providers
  • a qualified opinion on DCS's information technology (IT) security monitoring controls because security tools were not implemented and monitored for the entire financial year. Responsibility for IT security monitoring transitioned from Unisys to DCS in 2019–20. These control deficiencies can increase the risk of fraud and inappropriate use of sensitive data.

These may impact on the ability of agencies to detect and respond to a cyber incident.

Recommendation:

We recommend DCS work with GovConnect service providers to resolve the identified control deficiencies as a matter of priority.

The NSW Public Sector's cyber security resilience needs to improve

The NSW Cyber Security Policy requires agencies to provide a maturity self-assessment against the Australian Cyber Security Centre (ACSC) Essential 8 to the head of the agency and Cyber Security NSW annually. Completed self-assessment returns highlighted limited progress in implementing the Essential 8.

Repeat recommendation:

Cyber Security NSW and NSW government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency

Three Insurance and Care NSW (icare) entities had net asset deficiencies at 30 June 2020 The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. These icare entities did not hold sufficient assets to meet the estimated present value of all of their future payment obligations at 30 June 2020. The deterioration in net assets was largely due to increases in outstanding claims liabilities. Notwithstanding the overall net asset deficiencies, the financial statements for these entities were prepared on a going concern basis. This is because future payment obligations are not all due within the next 12 months. Settlement is instead expected to occur over years into the future, depending on the nature of the benefits provided by each scheme.
icare has not been able to demonstrate that its allocation of costs reflects the actual costs incurred by the Workers Compensation Nominal Insurer and other schemes

Costs are incurred by icare as the 'service entity' of the statutory scheme it administers, and then subsequently recovered from the schemes through 'service fees'. In the absence of documentation supported by robust supporting analysis, there is a risk of the schemes being overcharged, and the allocation of costs being in breach of legislative requirements.

Recommendation:

icare should ensure its approach to allocating service fees to the Workers Compensation Nominal Insurer and the other schemes it manages, is transparent and reflects actual costs.

icare did not comply with GIPA requirements icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20 and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
Implementation of Machinery of Government (MoG) changes MoG changes impacted the governance and business processes of some agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG implementation processes at Infrastructure NSW and in the Customer Service cluster.

This report provides Parliament and other users of NSW Government central agencies' financial statements and the Legislature's financial statements with the results of our financial audits, observations, analyses, conclusions and recommendations.

Emergency events, such as bushfires, floods and the COVID-19 pandemic significantly impacted agencies in 2019–20. Our findings on nine agencies that were most impacted by recent emergency events are included throughout this report.

Refer to Appendix one for the names of all central agencies and Appendix four for the nine agencies most impacted by emergency events.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations on the financial reporting of central agencies and the Legislature for 2020, including the financial implications from recent emergency events.

Section highlights

  • Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature. All agencies met the statutory deadlines for submitting their financial statements.
  • The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified as a result of a payment made without a Treasurer's delegation.
  • Agencies were impacted by emergency events during 2019–20. This included additional grants to fund specific deliverables.
  • The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
  • NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue in the financial statements. These misstatements were due to incorrect revenue calculations performed by the Transport agencies. The Crown Entity relies on information from Transport agencies as they are responsible for carrying out the State’s contractual obligations for Commonwealth funded transport projects. The extent of misstatements could have been reduced with more robust quality review processes in place by Treasury and Transport.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines:

  • our observations and insights from the financial statement audits of agencies in the central agencies and the Legislature
  • our assessment of how well agencies adapted their systems, policies, procedures and governance arrangements in response to recent emergencies.

Section highlights

  • The 2019–20 audits identified nine high risk and 122 moderate risk issues across the agencies. Of the 122 moderate risk issues, 44 (36 per cent) were repeat issues. The most common repeat issue relates to weaknesses in controls over information technology user access administration.
  • Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by these emergency events for the financial year ended 30 June 2020.
  • GovConnect NSW engaged an independent auditor (the service auditor) from the private sector to evaluate the internal controls of its service providers. DCS's information technology security monitoring controls were qualified by the service auditor because security tools were not implemented and monitored for the entire financial year. These may impact on the ability of agencies to detect and respond to a cyber incident.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. The financial statements for these entities continued to be prepared on a going concern basis as their liabilities are not all due for settlement within the next 12 months.
  • icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20, and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
  • Machinery of Government (MoG) changes impacted the governance and business processes of affected agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG changes at Infrastructure NSW and in the Customer Service cluster.

 

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for Volume Ten 2013 focusing on Health

Volume Ten 2013 focusing on Health

Health
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk
Shared services and collaboration

Unqualified opinions were issued for all agencies audited in the following report.

Some of the reports findings include:

  • Most cultural bodies rely heavily on government grants to fund services

  • The Sydney Opera House Trust earns most of its revenue from commercial operations

  • Less than half of the 2014-16 service agreements between HealthShare NSW and its customers have been signed. HealthShare NSW and health entities should finalise their 2014-2016 service agreements by no later than 31 January 2014

  • Five service level agreements with NSW Health Pathology for 2012-13 were never signed. NSW Health Pathology and local health districts/speciality networks should finalise their 2013-14 service agreements by no later than 31 December 2013

  • HealthShare NSW is committed to sharing internal audit findings across NSW Health

  • The Ministry has started a long-term project to review its policy directives

  • A recent review concluded the health sector has mature risk management practices

  • When changes to the Aboriginal Land Rights Act 1983 occur, the Minister should identify and assess any risks from the changes and develop strategies to mitigate against them.

Published

Actions for Managing Forensic Analysis: Fingerprints and DNA

Managing Forensic Analysis: Fingerprints and DNA

Justice
Health
Internal controls and governance
Management and administration
Procurement
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Fingerprints and DNA play a critical role in solving crime and serving justice, but DNA evidence can result in more arrests, more prosecutions and more convictions. We found that while police effectively prioritise fingerprint evidence, it could better manage the screening and analysis of both fingerprint and DNA evidence to reduce delays.

 

Parliamentary reference - Report number #195 - released 10 February 2010

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.

 

Parliamentary reference - Report number #160 - released 5 December 2006

Published

Actions for Major infectious disease outbreaks: Readiness to response

Major infectious disease outbreaks: Readiness to response

Health
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

NSW Health is working to increase its preparedness to respond to a major infectious disease outbreak. It is also contributing to the development of national policies, strategies and capabilities, which affect its level of preparedness. We found however little evidence that other jurisdictions were significantly further advanced than NSW in preparation and testing of plans for a pandemic. In our view NSW Health needs to balance the costs of over-preparedness and additional capacity that may never be used, against the very significant consequences of under-preparation. It needs to identify the desired level of preparedness for its Area Health Services, set measurable goals and identify key gaps between those goals and current capabilities. It needs to set clear plans for closing those gaps and then sustaining desired levels of preparedness.

 

Parliamentary reference - Report number #159 - released 22 November 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006