Reports
Actions for Transport 2018
Transport 2018
The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.
This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.
This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.
Observation | Conclusions and recommendations |
2.1 Quality of financial reporting | |
Unqualified audit opinions were issued for all agencies' financial statements | Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement. |
2.2 Key accounting issues | |
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS. |
RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million. The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase. |
2.3 Timeliness of financial reporting | |
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. | Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018. |
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. | Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process. |
2.4 Financial sustainability | |
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018. | NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. |
2.5 Passenger revenue and patronage | |
Transport agencies revenue growth increased at a higher rate than patronage. | Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. |
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. | Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences. |
2.6 Cost recovery from public transport users | |
Overall cost recovery from users has decreased. | Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18. |
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from:
- our financial statement audits of agencies in the Transport cluster for 2018
- the areas of focus identified in the Audit Office annual work program.
The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.
Observation | Conclusions and recommendations |
3.1 Internal controls | |
There was an increase in findings on internal controls across the Transport cluster. | Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues. |
3.2 Audit Office Annual work program | |
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology. |
Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. |
RailCorp is expected to convert to TAHE from 1 July 2019. | Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements. |
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. | TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. |
Not all agencies monitor unplanned maintenance across the Transport cluster. | Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster. |
This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.
We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report.
In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.
Actions for Progress and measurement of the Premier's Priorities
Progress and measurement of the Premier's Priorities
The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.
The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.
The 12 Premier's Priorities | |
---|---|
|
|
|
|
|
|
|
|
|
|
|
|
Source: Department of Premier and Cabinet, Premier’s Priorities website.
Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.
The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.
This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.
The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.
The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.
The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.
Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.
The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.
Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.
Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.
We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.
The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.
By December 2018, the Department of Premier and Cabinet should:
- improve transparency of public reporting by:
- providing information about limitations of reported data and associated performance
- clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
- ensure that processes to check and verify data are in place for all agency data sources
- encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.
The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.
The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.
Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.
By June 2019, the Department of Premier and Cabinet should:
- establish routine collection of feedback about PIU performance including:
- independent assurance of PIU performance
- opportunity for agencies to provide confidential feedback.
Appendix one: Response from agency
Appendix three: About the audit
Appendix four: Performance auditing
Parliamentary reference - Report number #307 - released 13 September 2018
Actions for HealthRoster benefits realisation
HealthRoster benefits realisation
The HealthRoster system is delivering some business benefits but Local Health Districts are yet to use all of its features, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. HealthRoster is an IT system designed to more effectively roster staff to meet the needs of Local Health Districts and other NSW health agencies.
The NSW public health system employs over 100,000 people in clinical and non-clinical roles across the state. With increasing demand for services, it is vital that NSW Health effectively rosters staff to ensure high quality and efficient patient care, while maintaining good workplace practices to support staff in demanding roles.
NSW Health is implementing HealthRoster as its single state-wide rostering system to more effectively roster staff according to the demands of each location. Between 2013–14 and 2016–17, our financial audits of individual LHDs had reported issues with rostering and payroll processes and systems.
NSW Health grouped all Local Health Districts (LHDs), and other NSW Health organisations, into four clusters to manage the implementation of HealthRoster over four years. Refer to Exhibit 4 for a list of the NSW Health entities in each cluster.
- Cluster 1 implementation commenced in 2014–15 and was completed in 2015–16.
- Cluster 2 implementation commenced in 2015–16 and was completed in 2016–17.
- Cluster 3 began implementation in 2016–17 and was underway during the conduct of the audit.
- Cluster 4 began planning for implementation in 2017–18.
Full implementation, including capability for centralised data and reporting, is planned for completion in 2019.
This audit assessed the effectiveness of the HealthRoster system in delivering business benefits. In making this assessment, we examined whether:
- expected business benefits of HealthRoster were well-defined
- HealthRoster is achieving business benefits where implemented.
The HealthRoster project has a timespan from 2009 to 2019. We examined the HealthRoster implementation in LHDs, and other NSW Health organisations, focusing on the period from 2014, when eHealth assumed responsibility for project implementation, to early 2018.
Business benefits identified for HealthRoster accurately reflect business needs.
NSW Health has a good understanding of the issues in previous rostering systems and has designed HealthRoster to adequately address these issues. Interviews with frontline staff indicate that HealthRoster facilitates rostering which complies with industrial awards. This is a key business benefit that supports the provision of quality patient care. We saw no evidence that any major business needs or issues with the previous rostering systems are not being addressed by HealthRoster.
In the period examined in this audit since 2015, NSW Health has applied appropriate project management and governance structures to ensure that risks and issues are well managed during HealthRoster implementation.
HealthRoster has had two changes to its budget and timeline. Overall, the capital cost for the project has increased from $88.6 million to $125.6 million (42 per cent) and has delayed expected project completion by four years from 2015 to 2019. NSW Health attributes the increased cost and extended time frame to the large scale and complexity of the full implementation of HealthRoster.
NSW Health has established appropriate governance arrangements to ensure that HealthRoster is successfully implemented and that it will achieve business benefits in the long term. During implementation, local steering committees monitor risks and resolve implementation issues. Risks or issues that cannot be resolved locally are escalated to the state-wide steering committee.
NSW Health has grouped local health districts, and other NSW Health organisations, into four clusters for implementation. This has enabled NSW Health to apply lessons learnt from each implementation to improve future implementations.
NSW Health has a benefits realisation framework, but it is not fully applied to HealthRoster.
NSW Health can demonstrate that HealthRoster has delivered some functional business benefits, including rosters that comply with a wide variety of employment awards.
NSW Health is not yet measuring and tracking the value of business benefits achieved. NSW Health did not have benefits realisation plans with baseline measures defined for LHDs in cluster 1 and 2 before implementation. Without baseline measures NSW Health is unable to quantify business benefits achieved. However, analysis of post-implementation reviews and interviews with frontline staff indicate that benefits are being achieved. As a result, NSW Health now includes defining baseline measures and setting targets as part of LHD implementation planning. It has created a benefits realisation toolkit to assist this process from cluster 3 implementations onwards.
NSW Health conducted post-implementation reviews for clusters 1 and 2 and found that LHDs in these clusters were not using HealthRoster to realise all the benefits that HealthRoster could deliver.
By September 2018, NSW Health should:
- Ensure that Local Health Districts undertake benefits realisation planning according to the NSW Health benefits realisation framework
- Regularly measure benefits realised, at state and local health district levels, from the statewide implementation of HealthRoster
- Review the use of HealthRoster in Local Health Districts in clusters 1 and 2 and assist them to improve their HealthRoster related processes and practices.
By June 2019, NSW Health should:
- Ensure that all Local Health Districts are effectively using demand based rostering.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #301 - released 7 June 2018
Actions for Managing risks in the NSW public sector: risk culture and capability
Managing risks in the NSW public sector: risk culture and capability
The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.
We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.
Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.
This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:
- agencies can demonstrate that senior management is committed to risk management
- information about risk is communicated effectively throughout agencies
- agencies are building risk management capabilities.
The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.
In assessing an agency’s risk culture, we focused on four key areas:
Executive sponsorship (tone at the top)
In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.
That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.
For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.
Employee perceptions of risk management
Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.
Integration of risk management into daily activities and links to decision-making
We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.
Support and guidance to help staff manage risks
Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.
Recommendation
By May 2019, NSW Treasury should:
- Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.
Appendix one - Response from agencies
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #298 - released 23 April 2018
Actions for Managing demand for ambulance services 2017
Managing demand for ambulance services 2017
NSW Ambulance has introduced several initiatives over the past decade to better manage the number of unnecessary ambulance responses and transports to hospital emergency departments. However, there is no overall strategy to guide the development of these initiatives nor do NSW Ambulance's data systems properly monitor their impact. As a result, the Audit Office was unable to assess whether NSW Ambulance's approach to managing demand is improving the efficiency of ambulance services.
NSW Ambulance uses a telephone referral system to manage triple zero calls from people with medical issues that do not require an ambulance. This has the potential to achieve efficiency improvements but there are weaknesses in NSW Ambulance's use and monitoring of this system. Paramedics are now able to make decisions about whether patients need transport to a hospital emergency department. NSW Ambulance does not routinely measure or monitor the decisions paramedics make, so it does not know whether these decisions are improving efficiency. Extended Care Paramedics who have additional skills in diagnosing and treating patients with less urgent medical issues were introduced in 2007. NSW Ambulance analysis indicates that these paramedics have the potential to improve efficiency, but have not been used as effectively as possible.
Our 2013 audit of NSW Ambulance found that accurate monitoring of activity and performance was not being conducted. More than four years later, this remains the case.
NSW Ambulance has recognised the need to change the way it manages demand and has developed initiatives that have the potential to improve efficiency. However, there are significant weaknesses in the strategy for and implementation of its demand management initiatives.
NSW Ambulance has identified the goal of moving from an emergency transport provider to a mobile health service and developed several initiatives to support this. Its demand management initiatives have the potential to contribute to the broader policy directions for the health system in New South Wales. However, there is no clear overall strategy guiding these initiatives and their implementation has been poor.
NSW Ambulance's reasons for changing its approach to demand management have not been communicated proactively to the community. Demand management initiatives that have been operating for over a decade still do not have clear performance measures or targets. Project management of new initiatives has been inadequate, with insufficient organisational resources to oversee them and inadequate engagement with other healthcare providers.
NSW Ambulance uses an in-house Vocational Education and Training course to recruit some paramedics, as well as recruiting paramedics who have completed a university degree. No other Australian ambulance services continue to provide their own Vocational Education and Training qualifications. Paramedics will need more support in several key areas to be able to fulfil their expanded roles in providing a mobile health service. Performance and development systems for paramedics are not used effectively. Up to date technology would help paramedics make better decisions and improve NSW Ambulance's ability to monitor demand management activity.
There are gaps in NSW Ambulance's oversight of the risks of some of the initiatives it has introduced, particularly its lack of information on the outcomes for patients who are not transported to hospital. Weaknesses in the way NSW Ambulance uses its data limit its ability to properly assess the risks of the demand management initiatives it has introduced.
Parliamentary reference - Report number #295 - released 13 December 2017
Actions for Planning and evaluating palliative care services in NSW
Planning and evaluating palliative care services in NSW
NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.
Parliamentary reference - Report number #291 - released 17 August 2017
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017.
Financial reporting | |
Observation | Conclusion |
Only one qualified audit opinion was issued on the 2015–16 financial statements of NSW public sector agencies, compared to two in 2014–15. | The quality of financial reporting continued to improve across the NSW public sector. |
More 2015–16 financial statements and audit opinions were signed within three months of the year end. | Timely financial reporting was facilitated by more agencies resolving significant accounting issues early, completing asset valuations on time and compiling sufficient evidence to support financial statement balances. |
NSW Treasury’s early close procedures in 2015–16 were again successful in improving the quality and timeliness of financial reporting, largely facilitated by the early resolution of accounting issues. For 2016–17, NSW Treasury has narrowed the scope of mandatory early close procedures. |
The narrowed scope of mandatory early close procedures may diminish the good performance in ensuring the quality and timeliness of financial reporting achieved in recent years. To mitigate this risk, NSW Treasury has mandated that agencies perform non-financial asset valuations and prepare proforma financial statements in their early close procedures. It also encourages them to continue with the good practices embedded in recent years. |
Although most agencies complied with NSW Treasury’s early close asset revaluation procedures we identified areas where they can improve. | Asset revaluations need to commence early enough to ensure all assets are identified and the results are analysed, recorded and reflected accurately in the early close financial statements. |
Number of misstatements | |||||
Year ended 30 June | 2015-16 | 2014-15 | 2013-14 | 2012-13 | 2011-12 |
Total reported misstatements | 298 | 396 | 459 | 661 | 1,077 |
All material misstatements identified by agencies and audit teams were corrected before the financial statements and audit opinions were signed. A material misstatement relates to an incorrect amount, classification, presentation or disclosure in the financial statements that could reasonably be expected to influence the economic decisions of users.
Significant matters reported to the portfolio Minister, Treasurer and Agency Head
In 2015–16, we reported the following significant matters to the portfolio Minister, Treasurer and agency head in our Statutory Audit Reports:
Appropriate financial controls help ensure the efficient and effective use of resources and the implementation and administration of agency policies. They are essential for quality and timely decision making.
In 2015–16, our audit teams made the following key observations on the financial controls of NSW public sector agencies.
Financial controls | |
Observation | Conclusion |
More needs to be done to implement audit recommendations on a timely basis. We found 212 internal control issues identified in previous audits had not been adequately addressed by 30 June 2016. |
Delays in implementing audit recommendations can impact the quality of financial information and the effectiveness of decision making. Agencies need to ensure they have action plans, timeframes and assigned responsibilities to address recommendations in a timely manner. |
Agencies continue to face challenges managing information security. Most information technology issues we identified related to poor IT user administration in areas like password controls and inappropriate access. | Agencies should review the design and effectiveness of information security controls to ensure data is adequately protected. |
We found shared service provider agreements did not always adequately address information security requirements. |
Where agencies use shared service providers they should consider whether the service level arrangements adequately address information security. |
Thirteen of 108 agencies required to attest to having a minimum set of information security controls did not do so in their 2015 annual reports. | The 'NSW Government Digital Information Security Policy' recognises the growing need for effective information security. With cyber security threats continuing to increase as digital services expand we plan to look at cyber security as part of our 2017–18 performance audit program. |
We identified instances where service level agreements with shared service providers were outdated, signed too late or did not exist. | Corporate and shared service arrangements are more effective when service level arrangements are negotiated and signed in time, clearly detail rights and responsibilities and include meaningful KPIs, fee arrangements and dispute resolution processes. |
Internal controls at GovConnect, the private sector provider of transactional and information technology services to many NSW public sector agencies were ineffective in 2015–16. We found mitigating actions taken to manage transition risks from ServiceFirst to GovConnect were ineffective in ensuring effective control over client transactions and data. | The Department of Finance, Services and Innovation should ensure GovConnect addresses the control deficiencies. It should also examine the breakdowns in the transition of the shared service arrangements and apply the learnings to other services being transitioned to the private sector. |
Maintenance backlogs exist in several NSW public sector agencies, including Roads and Maritime Services, Sydney Trains, NSW Health, the Department of Education and the Department of Justice. | To address backlog maintenance it is important for agencies to have asset lifecycle planning strategies that ensure newly built and existing assets are funded and maintained to a desired service level. |
Actions for Volume Eight 2013 focusing on Transport and Ports
Volume Eight 2013 focusing on Transport and Ports
Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.
The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.
Actions for Attracting, retaining and managing Nurses in hospitals
Attracting, retaining and managing Nurses in hospitals
The department has done well to attract and retain nurses. Between 2001-02 and 2005-06 the average number of nurses employed increased to 39,804 with the annual resignation rate falling from 16 to 14 per cent. Overall, the public health sector gained 5,588 nurses, representing an average annual increase of four per cent. Despite the gains, there are indicators that there may still not be enough nurses.
Parliamentary reference - Report number #162 - released 12 December 2006
Actions for Helping older people access a residential aged care facility
Helping older people access a residential aged care facility
Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.
Parliamentary reference - Report number #160 - released 5 December 2006