Refine search Expand filter

Reports

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Volume Twelve 2014 Health

Volume Twelve 2014 Health

Health
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

The quality of financial statements in the health cluster continues to improve with significantly fewer misstatements. The financial statements of all cluster agencies received unqualified audit opinions. Health has maintained or bettered its emergency triage performance and the percentage of patients admitted for elective surgery within clinically appropriate timeframes has improved.

Published

Actions for Volume Seven 2014 Focusing on Transport

Volume Seven 2014 Focusing on Transport

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Volume Ten 2013 focusing on Health

Volume Ten 2013 focusing on Health

Health
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk
Shared services and collaboration

Unqualified opinions were issued for all agencies audited in the following report.

Some of the reports findings include:

  • Most cultural bodies rely heavily on government grants to fund services

  • The Sydney Opera House Trust earns most of its revenue from commercial operations

  • Less than half of the 2014-16 service agreements between HealthShare NSW and its customers have been signed. HealthShare NSW and health entities should finalise their 2014-2016 service agreements by no later than 31 January 2014

  • Five service level agreements with NSW Health Pathology for 2012-13 were never signed. NSW Health Pathology and local health districts/speciality networks should finalise their 2013-14 service agreements by no later than 31 December 2013

  • HealthShare NSW is committed to sharing internal audit findings across NSW Health

  • The Ministry has started a long-term project to review its policy directives

  • A recent review concluded the health sector has mature risk management practices

  • When changes to the Aboriginal Land Rights Act 1983 occur, the Minister should identify and assess any risks from the changes and develop strategies to mitigate against them.

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007.

We recognise that the RTA is unable to prevent all crashes. However, we consider that the RTA could do more to improve its ability to detect and respond to high risk heavy vehicles travelling on our roads.

 

Parliamentary reference - Report number #187 - released 13 May 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.

 

Parliamentary reference - Report number #160 - released 5 December 2006

Published

Actions for Major infectious disease outbreaks: Readiness to response

Major infectious disease outbreaks: Readiness to response

Health
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

NSW Health is working to increase its preparedness to respond to a major infectious disease outbreak. It is also contributing to the development of national policies, strategies and capabilities, which affect its level of preparedness. We found however little evidence that other jurisdictions were significantly further advanced than NSW in preparation and testing of plans for a pandemic. In our view NSW Health needs to balance the costs of over-preparedness and additional capacity that may never be used, against the very significant consequences of under-preparation. It needs to identify the desired level of preparedness for its Area Health Services, set measurable goals and identify key gaps between those goals and current capabilities. It needs to set clear plans for closing those gaps and then sustaining desired levels of preparedness.

 

Parliamentary reference - Report number #159 - released 22 November 2006